Craig D. Sutton Manager, Nuclear Radiation Protection Diablo Canyon Power Plant Mail code 104/6/521 P.O. Box 56 Avila Beach, CA 93424 805.545.4208 Craig.Sutton@pge.com PG&E Letter HIL-23-004 REIRS Project Manager 10 CFR 20.2206 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation Annual Report of Occupational Radiation Exposure for 2022 REIRS Project Manager:
In accordance with 10 CFR 20.1502, Pacific Gas and Electric Company (PG&E) has submitted the Annual Report of Occupational Radiation Exposure for individuals monitored at Humboldt Bay Power Plant Independent Spent Fuel Storage Installation during calendar year 2022. The report was created by scanning the applicable NRC Form 5 information into a password protected pdf file. The pdf file, "20230206150227.pdf" was submitted electronically on the Radiation Exposure Information and Reporting System web page on April 4, 2023.
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.
If you have questions about the report, please contact me at 805-545-4208.
Sincerely, Craig D. Sutton Date armb/50947986 cc:
William C. Allen, NRC Project Manager Robert J. Lewis, NRC Acting Region IV Administrator NRC Document Control Desk HBPP Humboldt Distribution 4/19/2023