ML051960053

From kanterella
Jump to navigation Jump to search
U1R28 Today
ML051960053
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 05/20/2004
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML051960053 (2)


Text

NMC Comnisfted to Nudes# ErC&e DAY Point Beach Refueling N 47 Outage Edition

, =Sw$1 May 20, 2004 CONTACT INFORMATION Control Room Emergency - x2911 EMT Pager 6442 Work Control Center - x6703 OCC - x 7190 - Option 1 Lessons Learned - x7190 - Option 2 Plant Status - x7190 - Option 3 Accomplishments

  • Reactor Head Pen #33 Honing & Removed Thermal Sleeve
  • 1X03 Transformer H52-20 and H52-05 Breakers
  • RM 3200 RE-21 1/RE-212 Monitor Supply Solenoid Schedule Focus Areas/Priorities
  • Reactor Head Pen #26 Relief Request Issues
  • Setup and Prepare Mockup for Rx Head Pen #26 Grinding
  • Reactor Head Pen #33 UT
  • Re-Energize 1X03 Transformer
  • D106 Battery Cell Replacement and Spare Cell Staging Personnel Last 24 Hours Outage to ALARA ' Last 24 Hours Outage to Date Safety Date

'Roa - Recordable-I '

0.174 55.749 R t Disabling - 0 Disabling - 0 "OSHA Recordable - Back strain. Dose as of the end of Day 45 ,tl/ q iforman in is record was deleted hI acianc w;h tPFr om o hIbm"abn Ac2eP_

V 71V'..-.1'.-.:..

,,% 'i 7 --

, I,;- :; . ..

May 20, 2004 OUTAGE GOALS NUCLEAR SAFETY GOAL A=CTUAL HUMANPERFORMANCE GOAL ACTUAL PERFORMANCE _

Unplanned orange/red paths None None Security Violations S 12 loggable events 3-Reactor trips (either unit) None None ________

Station resets__

human performance dock _ _

None 4_ _ _ _

Safeguards actuation (either unit) None None Rework S 1% On Goal Loss of shutdown cooling None None SCHEDULE PERFORMANCE Outage Duration Loss of Rx vessel level control None None (excludes extensions due to £ 30 days Off Goal extended head or BMI Inspections)

INDUSTRIAL SAFETY On Goal Mod Implementation 100% of Rev 0 PERFORMANCE _

> 85% schedule Lost time accidents None None Schedule Compliance compliance with Off Goal outage milestone Personnel iriuries (OSHA recordable) None 1 Emergent work (during £ 2%late additions On Goal Implementation) s 5% Emergent _ ___

RADIOLOGICAL PERFORMANCE Scope Completev95% of On Goal Radiation exposure (Excludes additional 100% of Scheduled dose from any head or BMI repair 5 75 R E5.749 R Operator Burdens Operator Burdens On Goal contingencies) _ complete Personnel contaminations S 18w 10 Post Outage availability 2 150 days of AvaIlable at continuous operation a later date Radiological events (defined as unplanned uptake wlassigned dose >10 mrem or S1 event BUDGETPERFORMANCE Within -2% to 0%of Seriously dose event based on ED alarms_

BUDGET0outage budget Challenged Radmaterial event (defined as any rad SI event 0

  • 5/15104 Tailgating event: Door 265 #2183 material outside RCA 2 100 CPM) ___event_ _

Human Performance Operating Experience When Is a Pre-Job Brief Required? OE14482 - Equipment Inadvertently Mispositioned During Housekeeping Activities Tasks that pose a risk to:

  • Personnel Safety On June 26, 2002, Surry Operations personnel in the
  • Nuclear safety Surry Condensate Polishing (CP) Building found the control switch for the Unit 1 CP Building air compressor
  • Nuclear-safety related SSC (systems, structures, cooling tower in the "OFF" position versus the NAUTO" components) position. The normal position for this control switch Is
  • Plant operation 'AUTO' when the associated air compressor is in
  • Power generation "AUTOMATIC'. CP Building watchstanders observed that the compressor cooling water outlet temperature was at Tasks identified as: 210 deg F. The cooling tower control switch was returned
  • Error-likely tasks to 'AUTO' and CP Building watchstanders observed that
  • High or medium risk tasks the CP Building compressor temperature returned to

When requested by the performer. rooms. Following completion of these cleanup activities, operations personnel conducted a walkdown of the applicable areas to verify proper alignment and position of valves and switches. During this walkdown, a vent test valve for the number 2 EDG air start subsystem was Safety Snippet discovered open with Its associated pipe cap Installed.

If your load starts to slip, get out of the way - quick Lessons Learned: In each case, station housekeeping efforts had been conducted on or prior to the dates of December 1997 - An employee at a hospital was discovery for each specific occurrence. The apparent pushing a food cart down a ramp when she lost control cause for each of these events Is work practices as It of it. As she tried to stop the cart, she was crushed appears the affected equipment was bumped or between It and a wall. She was hospitalized for a Inadvertently positioned during housekeeping fractured ankle and a lacerated ear.

activities.