ML051960053

From kanterella
Jump to navigation Jump to search
U1R28 Today
ML051960053
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 05/20/2004
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML051960053 (2)


Text

NMC Comnisfted to Nudes# ErC&e Point Beach Refueling Outage Edition DAY N

47

, =Sw$1 May 20, 2004 CONTACT INFORMATION Control Room Emergency - x2911 EMT Pager 6442 Work Control Center - x6703 OCC - x 7190 - Option 1 Lessons Learned - x7190 - Option 2 Plant Status - x7190 - Option 3 Accomplishments

  • Reactor Head Pen #33 Honing & Removed Thermal Sleeve
  • 1 X03 Transformer H52-20 and H52-05 Breakers
  • RM 3200 RE-21 1/RE-212 Monitor Supply Solenoid Schedule Focus Areas/Priorities
  • Reactor Head Pen #26 Relief Request Issues
  • Setup and Prepare Mockup for Rx Head Pen #26 Grinding
  • Reactor Head Pen #33 UT
  • Re-Energize 1X03 Transformer
  • D106 Battery Cell Replacement and Spare Cell Staging Personnel Last 24 Hours Outage to Safety Date

'Roa Recordable-I '

t Disabling - 0 Disabling - 0 "OSHA Recordable - Back strain.

ALARA '

Last 24 Hours Outage to Date 0.174 55.749 R Dose as of the end of Day 45

,tl/

q iforman in is record was deleted hI acianc w;h tPFr om o hIbm"abn Ac2eP_

V 71V'..-.1'.-.:..

,,% 'i 7 --, I,;- :;.

May 20, 2004 NUCLEAR SAFETY GOAL A

PERFORMANCE Unplanned orange/red paths None Reactor trips (either unit)

None Safeguards actuation (either unit)

None Loss of shutdown cooling None Loss of Rx vessel level control None INDUSTRIAL SAFETY PERFORMANCE Lost time accidents None Personnel iriuries (OSHA recordable)

None RADIOLOGICAL PERFORMANCE Radiation exposure (Excludes additional dose from any head or BMI repair 5 75 R E

contingencies)

Personnel contaminations S 18w Radiological events (defined as unplanned uptake wlassigned dose >10 mrem or S1 event dose event based on ED alarms_

Radmaterial event (defined as any rad SI event material outside RCA 2 100 CPM)

___event_

OUTAGE GOALS

=CTUAL HUMANPERFORMANCE GOAL ACTUAL None Security Violations S 12 loggable events 3 -

None Station human performance dock None 4

resets__

None Rework S 1%

On Goal None SCHEDULE PERFORMANCE Outage Duration None (excludes extensions due to

£ 30 days Off Goal extended head or BMI Inspections)

Mod Implementation 100% of Rev 0 On Goal

> 85% schedule None Schedule Compliance compliance with Off Goal outage milestone 1

Emergent work (during

£ 2% late additions On Goal Implementation) s 5% Emergent Scope Completev95% of On Goal 100% of Scheduled 5.749 R Operator Burdens Operator Burdens On Goal complete 10 Post Outage availability 2 150 days of AvaIlable at continuous operation a later date BUDGETPERFORMANCE Within -2% to 0% of Seriously BUDGET0outage budget Challenged 0

  • 5/15104 Tailgating event: Door 265 #2183 Human Performance When Is a Pre-Job Brief Required?

Tasks that pose a risk to:

Personnel Safety Nuclear safety Nuclear-safety related SSC (systems, structures, components)

Plant operation Power generation Tasks identified as:

Error-likely tasks High or medium risk tasks IPTE tasks When requested by the performer.

Operating Experience OE14482 - Equipment Inadvertently Mispositioned During Housekeeping Activities On June 26, 2002, Surry Operations personnel in the Surry Condensate Polishing (CP) Building found the control switch for the Unit 1 CP Building air compressor cooling tower in the "OFF" position versus the NAUTO" position. The normal position for this control switch Is

'AUTO' when the associated air compressor is in "AUTOMATIC'. CP Building watchstanders observed that the compressor cooling water outlet temperature was at 210 deg F. The cooling tower control switch was returned to 'AUTO' and CP Building watchstanders observed that the CP Building compressor temperature returned to normal. On July 19, 2002, station cleanup activities were performed in all three Emergency Diesel Generator (EDG).

rooms. Following completion of these cleanup activities, operations personnel conducted a walkdown of the applicable areas to verify proper alignment and position of valves and switches. During this walkdown, a vent test valve for the number 2 EDG air start subsystem was discovered open with Its associated pipe cap Installed.

Lessons Learned: In each case, station housekeeping efforts had been conducted on or prior to the dates of discovery for each specific occurrence. The apparent cause for each of these events Is work practices as It appears the affected equipment was bumped or Inadvertently positioned during housekeeping activities.

Safety Snippet If your load starts to slip, get out of the way - quick December 1997 - An employee at a hospital was pushing a food cart down a ramp when she lost control of it. As she tried to stop the cart, she was crushed between It and a wall. She was hospitalized for a fractured ankle and a lacerated ear.