ML051960052
| ML051960052 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 05/19/2004 |
| From: | Nuclear Management Co |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| FOIA/PA-2004-0282 | |
| Download: ML051960052 (2) | |
Text
=-V
-*/ I
.- S-NIVIC Commlfted to Nucdear ExcellenceF Point Beach Refueling Outage Edition
..r DAY 46 Iz tat N
VI>\\J
-P t1.
x
$2~
TOA
.I, t
l n
May 19, 2004 CONTACT INFORMATION Control Room Emergency - x2911 EMT Pager 6442 Work Control Center - x6703 OCC - x 7190 - Option I Lessons Learned - x7190 - Option 2 Plant Status - x7190 - Option 3 Accomplishmes
- Main Generator 60# Air Test
/
- Reactor Head Pen #33 Honing Schedule Focus AreaslPriorities
- Reactor Head PeI~6relief Request Issues Pa
- Setup and Prepare Mockup for Rx Head Pen #26 Grinding
- Work Package to Grind Out Over Lap on Pen #26
- Reactor Head Pen #3hermal Sleeve
- IT-280A for 1MS-2018 A SIG Main Steam Stop
- 1X03 Transformer H52-20 and H52-05 Breakers Personnel Last 24 Hours Outage to Safety Date ZD1%
Recordable -0 Recordable - V Disabling - 0 Disabling - 0
- OSHA Recordable - Back strain.
Infom n i hIt record Was dId kIn wmd 1`cwfii 0Feedom of lrformabon Add
- .t Last 24 Hours Outage to Date ALARA I
0.241 55.575 R Dose as of the end of Day 44 lo 1/
May 19, 2004 OUTAGE GOALS NUCLEAR SAFETY GOAL ACTUAL PERFORMANCE Unplanned orangelred paths None None Reactor trips (either unit)
None None Safeguards actuation (either unit)
None None Loss of shutdown cooling None None Loss of Rx vessel level control None None INDUSTRIAL SAFETY PERFORMANCE Lost time accidents None None Personnel injuries (OSHA recordable)
None I
RADIOLOGICAL PERFORMANCE Radiation exposure (Excludes additional dose from any head or BMI repair s 75 R 55.575 R contingencies)
Personnel contaminations
>5K18 w/
1_
0 Radiological events (defined as unplanned uptake wlassigned dose >10 mrem or s1 event 1
dose event based on ED alarms Radmaterial event (defined as any rad
- t event 0
material outside RCA 2 100 CPM) event_0 HUMAN PERFORMANCE GOAL ACTUAL Security Violations s 12 loggable events 3
- Station human performance dock None 4
resets Rework s
1%
On Goal SCHEDULE PERFORMANCE Outage Duration (excludes extensions due to s 30 days Off Goal extended head or BMI inspections)
Mod Implementation 100% of Rev 0 On Goal
> 85% schedule Schedule Compliance compliance with Off Goal outage milestone Emergent work (during s
2/6 late additions Implementation) s 5% Emergent n Goal Scope Complete 2 95% of On Goal Rev 0_scope 100% of Scheduled Operator Burdens Operator Burdens On Goal complete Post Outage availability 2 150 days of Available at continuous operation a later date UDGETPERFORMANCE thin
-2% to 0% of Seriously BUGTPROM NEoutage budget IChtallenged
' 5/15/04 Tailgating event Door 265 #2183 Human Performance Who does what? Senior Line Managers, Department Managers and Supervisors, and all Site Personnel have specific responsibilities associated with briefings.
Senior Line Managers - Perform briefings for Infrequently Performed Tests or Evolutions Department Managers and Supervisors -
Establish briefing requirements, and perform briefs for high or medium risk activities Site Personnel - Request briefings, participate in briefings using Q,V & V, and safely & correctly perform the task or evolution.
Operating Experience OE12590 - Inadequate Piping Modification Controls Causes System Inoperability A pre-refuel outage inspection of seismic snubbers found that two snubbers associated with a support on an operable ECCS system were fully extended. The system was declared inoperable pending evaluation. When the snubbers were removed to evaluate their condition, the piping in the vicinity of the snubbers moved in the upward direction. Spring cans associated with this piping were then adjusted to relieve the upward force exerted on the piping. Though these adjustments lessened the upward piping displacement, the piping remained too high for proper reinstallation of the snubbers.
Lessons Learned: Work practices that contributed to the event Included: design and work concentration at the point of the cut without evaluation of the effect of the cut on the local system piping and supports; the absence of an as-left design verification of affected system piping; not removing snubbers that could be damaged by piping movement; the Installation of temporary restraints as determined by the work group with engineering guidance rather than by a preplanned restraint scheme; and not pinning spring cans.
Safety Snippet If your load starts to slip, get out of the way - quick December 1997 An employee at a hospital was pushing a food cart down a ramp when she lost control of it. As she tried to stop the cart, she was crushed between it and a wall. She was hospitalized for a fractured ankle and a lacerated ear.