ML052030086

From kanterella
Jump to navigation Jump to search
U1R28 Today
ML052030086
Person / Time
Site: Point Beach 
(DPR-024)
Issue date: 05/23/2004
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML052030086 (2)


Text

I W

NMC Commhied to Nucear Ew Iffer",

Point Beach Refueling Outage Edition

.-U

'JDUIIEYDF

~50 1ER~ELL fltE KH 11=8 k.

/'

F

'V

1Z ti -

r

-, fl May 23, 2004 Enwmmnx%

~-

'U.

)

T.

I CONTACT INFORMATION Control Room Emergency - x2911 EMT Pager 6442 Work Control Center - x6703 OCC - x 7190 - Option I Lessons Learned - x7190 - Option 2 Plant Status - x7190 - Option 3 Accomplishments

  • Clean Conoseal Ports
  • Started Up Condensate System
  • Framatone Underhead Inspection Equipment Removed
  • Head Inspection Scaffold Removed
  • 1 Sl-878B MOV Work Schedule Focus AreaslPriorities
  • Reactor Head Penetration #26 Relief Request Issues
  • Drain RCS to 70% Reactor Vessel Level
  • Replace RV Head O-Rings and Inspect Seal Lift & Set Reactor Vessel Head Upper Cavity Decon Nozzle Dam Removal Primary Manway Installation Personnel Last 24 Hours Outage to Safety Date

'I-l - 0 Recordable -1' I

Disabling - 0 Disabling - 0

  • OSHA Recordable - Back strain.

t

, t Last 24 Hours Outage to Date ALARA',I "

2.858 73.049 R Dose as of the end of Day 48 V--/611 JBU01iEY TD iEXCELLERCE P0111T BERCH

  • U11128

t May 23, 2004 OUTAGE GOALS NUCLEAR SAFETY GOAL ACTUAL PERFORMANCE Unplanned orangelred paths None None Reactor trips (either unit)

None None Safeguards actuation (either unit)

None None Loss of shutdown cooling None None Loss of Rx vessel level control None None INDUSTRIAL SAFETY PERFORMANCE Lost time accidents None None Personnel Injuries (OSHA recordable)

None 1

RADIOLOGICAL PERFORMANCE Radiation exposure (Excludes additional dose from any head or sMI repair s 92 R 73.049 R contingencies)

Personnel contaminations

>5K CPM 10 Radiological events (defined as unplanned uptake w/assigned dose >10 mrem or s1 event I

dose event based on ED alarms Radmaterial event (defined as any rad t

0 material outside RCA ; 100 CPM) event HUMAN PERFORMANCE GOAL ACTUAL Security Violations

s 12 loggable events 3

Station human performance dock None 4

resets Rework

1%

. On Goal SCHEDULE PERFORMANCE_

Outage Duration (excludes extensions due to s 30 days Off Goal extended head or BMI inspections)

Mod Implementation 100% of Rev 0 On Goal

> 85% schedule Schedule Compliance compliance with Off Goal outage milestone Emergent work (during s 2% late additions On Goal kmplementation) s 5% Emergent

_oal Scope Complete a 95% of On Goal Rev 0 scope 100% of Scheduled Operator Burdens Operator Burdens On Goal complete Post Outage availability 2 150 days of Available at continuous operation a later date BUDGET PERFORMANCE W thin

-2% to 0% of Seriously outage budget Challenged Human Performance Briefings in Review Guidance is found in NP 1.6.10 Briefings are required for all jobs and evolutions The level of discussion and documentation is dependent on o Risk of the job o Error-likely situations involved with the job o Past-performance experience o Consequences of improper performance Operating Experience OEI 1214 - 22 Steam Generator Cold Leg Bowl Drain Plug Installed in the Wrong Drain Hole Unit 2 was shutdown for refueling with the Reactor Coolant System (RCS) in a reduced inventory condition. The RCS level was being maintained below the top of the hot leg for removal of the Steam Generator (SG) primary manways and installation of nozzle dams. At the completion of SG nozzle dam installation RCS fill was started in accordance with 2D2, "RCS Reduced Inventory Operation," to return RCS level to 1 foot below the Reactor Vessel Flange to bring the RCS out of the reduced inventory condition. While filling the RCS, water started coming out of 22 SG cold leg manway. The control room was immediately contacted when discovered. The control room operators stopped filling the RCS and opened the RCS drain valves per 2D2 to lower the RCS level. The RCS level was lowered until water stopped coming out of the SG manway. Containment workers also started a Randolph pump to pump water out of the SG channel head to minimize the water spilling out of the manway while the RCS level was being lowered.

Lessons Learned: Causes were determined to be inadequate procedures and Insufficient hands-on training. Stop When Unsurel Safety Snippet Is there an obstruction in your way that might not stay?

OE1 3857 May 2002, Fort Calhoun -While moving the reactor vessel head assembly during a refueling outage, the control pendant for the polar crane caught a handrail vertical support pipe, lifting the pipe out of its mount and causing it to fall 20 ft to the walkway below. Individuals were in the area at the time, but not injured. A review indicated the pendant caught on nearby equipment many times during past refueling outages and corrective actions were not put in place. Are there any items were our equipment gets caught during moves that we have not resolved?