Letter Sequence RAI |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML040300802, ML040631055, ML042520157, ML042670485, ML050870511, ML051090111, ML052290107, ML052800176, W3F1-2004-0076, To Amendment Request NPF-38-256, Alternate Source Term, W3F1-2004-0085, Schedule Clarification for Amendment Request NPF-38-249, Extended Power Uprate, W3F1-2004-0095, To Amendment Request NPF-38-256 Alternate Source Term, W3F1-2004-0101, To Amendment Request NPF-38-256, Alternate Source Term, Waterford Steam Electric Station, Unit 3
|
MONTHYEARML0425201572004-01-14014 January 2004 E-mail to T. Alexion Dated 1/14/04 Waterford - Extended Power Uprate Project stage: Other ML0401405152004-01-14014 January 2004 Meeting with Entergy, Waterford Steam Electric Station, Unit 3 Extended Power Uprate Amendment Request Dated 11/13/2003 Project stage: Meeting ML0403302602004-01-28028 January 2004 1/28/04 Waterford 3 - RAI Revision to Facility Operating License & TS - Extended Power Uprate Request. TAC MC1355 Project stage: RAI ML0403008022004-01-28028 January 2004 FRN -Notice of Consideration of Issuance of Amendment for Extended Power Uprate and Opportunity for Hearing Project stage: Other W3F1-2004-0004, Supplemental Information Extended Power Uprate - Power Ascension Testing2004-01-29029 January 2004 Supplemental Information Extended Power Uprate - Power Ascension Testing Project stage: Request ML0425201642004-01-30030 January 2004 E-mail Dated 1/30/04 RAI from Environmental Section on Waterford Unit 3 Project stage: RAI ML0425201672004-02-10010 February 2004 E-mail Dated 2/10/04 Waterford - Draft RAI from Human Performance, Piping Integrity and Electrical Groups Project stage: Draft RAI ML0425201702004-02-18018 February 2004 E-mail Dated 2/18/04 Re RAI from I&C - Waterford Project stage: RAI ML0405506052004-02-20020 February 2004 Westinghouse Request Withholding from Public Disclosure, Waterford 3, Extended Power Uprate, Appendix 1 - Safety Evaluation Report Compliance, MC1355 Project stage: Approval ML0425201712004-02-23023 February 2004 E-mail Dated 2/23/04 Waterford RAI Containment Systems Project stage: RAI ML0406310552004-02-26026 February 2004 Summary of Entergy Operations, Inc. Presentation of Extended Power Uprate Project stage: Other ML0426704852004-03-0202 March 2004 E-mail from D. Miller to K. Kalyanam Re RAI from J. Tsao Project stage: Other ML0426704892004-03-0202 March 2004 E-mail from B. Miller to N. Kalyanam RAI from SPLB-Angelo Stubbs Project stage: RAI W3F1-2004-0017, Supplement to Amendment Request NPF-38-249 Regarding Extended Power Uprate2004-03-0404 March 2004 Supplement to Amendment Request NPF-38-249 Regarding Extended Power Uprate Project stage: Supplement ML0406909622004-03-0909 March 2004 Extended Power Uprate Acceptance Review Project stage: Acceptance Review ML0407809952004-03-16016 March 2004 RAI, Proposed Revision to Facility Operation License and TSs - Extended Power Uprate Request Project stage: RAI ML0408506542004-03-24024 March 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI ML0412102452004-03-26026 March 2004 Request for Additional Information, Revision to Facility Operating License & Technical Specifications - Extended Power Uprate Request Project stage: RAI ML0409102392004-03-31031 March 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI ML0410005142004-04-0808 April 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI W3F1-2004-0029, Extended Power Uprate, Waterford, Unit 3 Supplement to Amendment Request2004-04-15015 April 2004 Extended Power Uprate, Waterford, Unit 3 Supplement to Amendment Request Project stage: Supplement ML0411301942004-04-20020 April 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI ML0412705672004-05-0404 May 2004 RAI, Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI W3F1-2004-0035, Supplemental to Amendment Request for Extended Power Uprate2004-05-0707 May 2004 Supplemental to Amendment Request for Extended Power Uprate Project stage: Supplement W3F1-2004-0028, License Amendment Request NPF-38-254, Reactor Coolant System Leakage Detection2004-05-0707 May 2004 License Amendment Request NPF-38-254, Reactor Coolant System Leakage Detection Project stage: Request W3F1-2004-0037, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-05-12012 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0413801452004-05-13013 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement W3F1-2004-0043, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-05-21021 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement W3F1-2004-0047, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-05-26026 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0417405772004-06-21021 June 2004 RAI, Revision to Facility Operating License and Technical Specifications - Extended Power Uprate Request, TAC MC1355 Project stage: RAI ML0420202942004-07-15015 July 2004 License Amendment Request NPF-38-256, Alternate Source Term Project stage: Request W3F1-2004-0061, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-07-28028 July 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0421100882004-07-29029 July 2004 Meeting with Entergy to Discuss Issues with Extended Power Uprate and Alternate Source Term Submittals Project stage: Request ML0422303352004-08-10010 August 2004 August 11, 12 and 13, 2004 Meeting with Westinghouse Re Waterford Main Steam Line Break, Feedwater Line Break and EPU Project stage: Meeting W3F1-2004-0068, Supplement to Amendment Request NPF-38-249 Extended Power Uprate2004-08-10010 August 2004 Supplement to Amendment Request NPF-38-249 Extended Power Uprate Project stage: Supplement W3F1-2004-0071, Supplement to Alternate Source Term Submittal2004-08-19019 August 2004 Supplement to Alternate Source Term Submittal Project stage: Request ML0423904892004-08-26026 August 2004 Meeting with Entergy to Discuss Issues with Extended Power Uprate and Alternate Source Term Submittals Project stage: Meeting W3F1-2004-0076, To Amendment Request NPF-38-256, Alternate Source Term2004-09-0101 September 2004 To Amendment Request NPF-38-256, Alternate Source Term Project stage: Other W3F1-2004-0078, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-09-14014 September 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0427505192004-09-29029 September 2004 RAI Extended Power Uprate Request and Alternate Source Term Request Project stage: RAI ML0427402482004-09-30030 September 2004 (3) Steam Elecric Station, 3, Draft EA and Finding of No Significant Impact Related to a Proposed License Amendment to Increase the Licensed Power Level (Tac. MC1355) Project stage: Draft Other W3F1-2004-0086, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-10-0808 October 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement W3F1-2004-0092, Supplement to Amendment Request NPF-38-249 Extended Power Uprate2004-10-0808 October 2004 Supplement to Amendment Request NPF-38-249 Extended Power Uprate Project stage: Supplement W3F1-2004-0085, Schedule Clarification for Amendment Request NPF-38-249, Extended Power Uprate2004-10-13013 October 2004 Schedule Clarification for Amendment Request NPF-38-249, Extended Power Uprate Project stage: Other W3F1-2004-0095, To Amendment Request NPF-38-256 Alternate Source Term2004-10-13013 October 2004 To Amendment Request NPF-38-256 Alternate Source Term Project stage: Other W3F1-2004-0101, To Amendment Request NPF-38-256, Alternate Source Term, Waterford Steam Electric Station, Unit 32004-10-19019 October 2004 To Amendment Request NPF-38-256, Alternate Source Term, Waterford Steam Electric Station, Unit 3 Project stage: Other ML0430102382004-10-21021 October 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0431006112004-10-26026 October 2004 RAI - Revision to Facility Operating License and Technical Specifications - Extended Power Uprate Request Project stage: RAI W3F1-2004-0089, Supplement to Amendment Request NPF-38-2492004-10-29029 October 2004 Supplement to Amendment Request NPF-38-249 Project stage: Supplement W3F1-2004-0107, Supplement to Amendment Request NPF-38-2492004-10-29029 October 2004 Supplement to Amendment Request NPF-38-249 Project stage: Supplement 2004-03-04
[Table View] |
Text
.y ym from SPLB - AngeloStubbs Page 1 From:
N. Kaly Kalyanam To:
Bryan Miller Date:
3/2/04 11:1OAM
Subject:
RAI from SPLB - Angelo Stubbs Bryan:
I am enclosing the draft RAI from Angelo Stubbs.
Please review the questions and let me know if you can respond to them within thirty days of receipt of the formal RAI.
Thanks Kaly oc No.
sa -3 e2 T A-C-N.
V1C 13Sa94
N. Kalv Kalvanam - Docl.wp~d Page 1 N. Kalv Kalvanam - Dod.wDd Paae 1 I OFFiCE OF NUCLEAR REACTOR REGULATION DRAFT REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST FOR EXTENDED POWER UPRATE WATERFORD STEAM ELECTRIC STATION, UNIT 3 DOCKET NOs: 50-382 (TAC NO. MC1355)
- 1.
Please explain how the Equipment and Floor Drainage System is impacted by the EPU.
- 2.
Section 2.5.5.3 of the licensee's November 13, 2003 license amendment request, addresses the impact of EPU on the Reactor Auxiliary Cooling Water Systems. In the evaluation section, it is stated that ' Under EPU conditions, the maximum heat load from containment during a LOCA is lower than the maximum heat load considered on the CCWS and ACCWS systems under pre-Uprate conditions. The containment heat load under EPU conditions was determined using a more detailed evaluation of the containment heat loads than was performed previously under Pre-EPU conditions."
A.
Provide the pre-EPU and post-EPU heat loads for the CCWS and ACCWS systems.
B Explain, in detail, the differences in the methods and assumptions use to calculate the pre-EPU and post-EPU heat loads. Identify what conservatism, if any, has been removed, and provide appropriate justification for the changes made in the way the heat load was calculated for post-EPU plant operation.
- 3.
Section 2.5.5.4 of the licensee's November 13, 2003 license amendment request, addresses the impact of EPU on the Ultimate Heat Sink. The EPU evaluation arrived at lower peak heat loads than those used in the current UHS analysis, due to lower maximum CCWS heat loads that resulted from a more detailed evaluation of post-accident heat loads. Please discuss how the UHS analyses were performed, and identify any differences in the analysis methods, assumptions or inputs between the pre-EPU evaluation and the post-Evaluation.
- 4.
Section 2.5.5.5 of the licensee's November 13, 2003 license amendment request, addresses the impact of EPU on the Emergency Feedwater System. In the Evaluation Section the licensee states "Although EPU will cause an increase in the decay heat, engineering evaluations for the EPU determined that no change to the EFW performance (flow rate and delivery pressure) is required." Please provide additional details on the analysis used to support the above statement. Explain how the increased heat load is accommodated by the EFW system without any change in the system performance requirements.
- 5.
In Section 2.5.5.5 it is also stated that " The increased demand for condensate requirements for cooldown as a result of EPU can be met with the current system configuration and operation." Please provide both the total inventory required by EFW for cooldown, and the total inventory available for use by the EFW system for the post-EPU plant.
- 6.
As a result of plant operation at the proposed extended power uprate (EPU) level, the decay heat load for any specific discharge fuel scenario will increase. In section 2.5.5.1 of the Waterford 3 EPU submittal, it is stated that for power uprate conditions the
- --.-. 1. - I I I -. - -. .- I __ -.I--- _;. __ -...
I--- --
_'. _, -...' . _
, I IN. Ka1v Kalvanam - Docl.wDd Paae 21l I N. KaIv Kalvanam - Dod.wDd Paae 21 maximum bulk pool temperature limit of 140OF for normal refueling outage will not be exceeded and that the maximum bulk pool temperature limit of 155 OF for full core offload will not be exceeded. However, a detailed discussion of the Spent Fuel Pool evaluations performed to support the above statements was not provided. Based on the plants current spent fuel pool analysis, the peak fuel pool temperature for the normal discharge case is 1 39.41F, and for the full core discharge is 151.60F. Please provide the following information for both pre-uprate, and post-uprate operation.
A.
Please provide for both pre-uprate, and post-uprate operation, the methodology and assumptions (i.e. number of fuel assemblies off loaded, hold time, number of previously discharged fuel assemblies in the SFP, ultimate heat sink temperature, etc.) used in the SFP thermal-hydraulic analysis for each scenario analyzed. Also, provide the spent fuel pool bulk temperature results for both the pre-EPU, and post-EPU plant, and identify any changes made to the SFP analysis for the EPU evaluation.
B.
In the event of loss of the Spent Fuel Pool Cooling System, what impact does the EPU have on the time for the SFP temperature to rise from the maximum bulk pool temperature limit of 140OF to boiling at 212 0F. Confirm that the time to boiloff the post-EPU plant is sufficient to allow mitigative actions, and that makeup water requirements are within the system capacity.
C.
The SFP heat loads and corresponding peak calculated temperatures during planned (normal) refueling outages under partial and full core off-load conditions, and unplanned (abnormal) full-core offload outages for both pre-urate, and post-uprate conditions.
- 7.
In section 2.5.8.1 of the EPU submittal, it is stated that "The fuel oil consumption rates were based on actual measured rates as opposed to vendor supplied rates determined when the EDGs were new. The consumption rates used in the evaluation were less than the vendor-supplied rates used in the Analysis of Record, but greater than the measured rates." Please provide the following information:
A.
The consumption rate assumed in the current Analysis of Record.
B.
The measured consumption rates, and conditions under which they were measured.
C.
The consumption rate assumed in the EPU evaluation, and the corresponding fuel oil requirements for post-DBA operation.
D.
A detailed discussion on how the consumption rates used for the EPU analysis was selected. Include discussions uncertainties associated with the measured data, and margins applied to the assumed consumption rate.
- 8.
In section 2.5.8.1 of the submittal, it is stated that " A time-dependent load profile was developed based on expected power requirements and run time of each component powered by the EDG under accident conditions. This evaluation considered the ECCS performance and containment design analyses, along with engineering judgement for long-term portion of the event and components not modeled in those analyses. Please identify the parts of the analysis were engineering judgement was used and provide the appropriate rationale.