Meeting with Entergy to Discuss Issues with Extended Power Uprate and Alternate Source Term Submittals
ML042390489
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/26/2004
From: Kalyanam N
NRC/NRR/DLPM/LPD4
To:
Kalyanam N, NRR/DLPM, 415-1480
Shared Package
ml042390499 List:
References
TAC MC1355
Download: ML042390489 (5)


Text

August 26, 2004 LICENSEE:

ENTERGY OPERATIONS, INC.

FACILITY:

WATERFORD STEAM ELECTRIC STATION, UNIT 3

SUBJECT:

SUMMARY

OF AUGUST 12, 2004, MEETING WITH ENTERGY OPERATIONS, INC. ON EXTENDED POWER UPRATE (EPU) AND ALTERNATE SOURCE TERM (AST) ISSUES (TAC NO. MC1355)

On August 12, 2004, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Entergy Operations, Inc. at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the schedules for completing the reviews of EPU and AST submittals, address the late October ACRS sub-committee meeting in regards to control room habitability, and any technical discussions that arose. There were no handouts from the licensee at the meeting.

As a result of the discussions, the following positions and/or decisions were taken.

1. From an initial look, the staff had only limited questions about the AST submittal dated August 15, 2004. The NRC staff intends to have one reviewer dedicated to evaluate control room habitability for Waterford 3 after August, and there will be a request for additional information (RAI) after a more detailed review.
2. The NRC staff will try to support the licensees target dates as long as it gets prompt and acceptable responses to the RAIs that are generated.
3. The licensee said that in the next AST supplement, which is expected to be submitted soon, it will link the EPU and AST applications, since AST is required for the control room habitability evaluation.
4. The licensee said that as long as we appear to be on a success path and there are no surprises as far as the EPU is considered, it can wait for the formal issue of the EPU amendment till just before the spring refueling.
5. It was agreed that the Advisory Committee on Reactor Safety (ACRS) sub-committee and full-committee meetings, currently scheduled for late-October and early-November, 2004, respectively, should not be changed.
6. In the ACRS sub-committee and full-committee meetings, the reviewer(s) can explain the status of reviews of the EPU and AST submittals.
7. The staff discussed with the licensee assumptions and inputs for the AST analyses they had submitted and how those assumptions and inputs related to the guidance in RG 1.183. The licensee also asked if there was any additional information or clarification we needed with regard to the latest EPU dose assessment RAI response for the EPU submittal. The staff stated the RAI response appeared complete.
8. The staff also told the licensee that they should make very clear in their supplementary submittals for the EPU what portions of the original EPU submittal and the new AST submittal they are relying on to show compliance with the appropriate regulations for the proposed power uprate, with respect to the dose offsite and in the control room as a result of design basis accidents.

A list of attendees is provided as Attachment 1.

There was one member of the public in attendance. Public Meeting Feedback forms were not received.

/RA/

N. Kalyanam, Project Manager Project Directorate IV-1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-382 Attachments: 1. List of Attendees cc w/atts: See next page CONTACT:

N. Kalyanam 301-415-1480 NRR/DLPM/PDIV-1 regard to the latest EPU dose assessment RAI response for the EPU submittal. The staff stated the RAI response appeared complete.

8. The staff also told the licensee that they should make very clear in their supplementary submittals for the EPU what portions of the original EPU submittal and the new AST submittal they are relying on to show compliance with the appropriate regulations for the proposed power uprate, with respect to the dose offsite and in the control room as a result of design basis accidents.

A list of attendees is provided as Attachment 1.

There was one member of the public in attendance. Public Meeting Feedback forms were not received.

/RA/

N. Kalyanam, Project Manager Project Directorate IV-1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-382 Attachments: 1. List of Attendees cc w/atts: See next page CONTACT:

N. Kalyanam 301-415-1480 NRR/DLPM/PDIV-1 DISTRIBUTION:

PUBLIC PDIV-1 Reading RidsNrrAdpt (BSheron)

RidsNrrDlpm (TMarsh/JLyons)

RidsNrrDlpmLpdiv (HBerkow)

RidsNrrLADBaxley RidsNrrLADJohnson RidsOgcRp KGrimes R. Dennig RCaruso M. Hart JDixon-Herrity LBrown TMensah RidsAcrsAcnwMailCenter RidsRgn4MailCenter(AHowell/BHenderson)

Package Accession No.ML042390499 Meeting Notice Accession No.ML042110088 Accession Number: ML04042390489

  • Per T Marsh deferal memo OFFICE PDIV-1/LA PDIV-1/PM PDIV-1/SC NAME DBaxley*

NKalyanam RGramm DATE N/A 8/24/04 8/24/04 OFFICIAL RECORD COPY

AUGUST 12, 2004, MEETING WITH ENTERGY OPERATIONS, INC.

ON EXTENDED POWER UPRATE AND ALTERNATE SOURCE TERM ISSUES LIST OF ATTENDEES NAME ORGANIZATION T. R. Leonard Entergy Operations, Inc.

P. Secard Entergy Operations, Inc.

D. B. Miller Entergy Operations, Inc.

J. Burford Entergy Operations, Inc.

J. Weil McGraw-Hill H. Berkow NRR/DLPM R. Gramm NRR/DLPM R. Dennig NRR/DSSA/SPSB R. Caruso ACRS M. Hart NRR/DSSA/SPSB L. Brown NRR/DSSA/SPSB N. Kalyanam NRR/DLPM

June 2004 Waterford Steam Electric Station, Unit 3 cc:

Mr. Michael E. Henry, State Liaison Officer Department of Environmental Quality Permits Division P.O. Box 4313 Baton Rouge, Louisiana 70821-4313 Vice President Operations Support Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Director Nuclear Safety Assurance Entergy Operations, Inc.

17265 River Road Killona, LA 70066-0751 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205 General Manager Plant Operations Waterford 3 SES Entergy Operations, Inc.

17265 River Road Killona, LA 70066-0751 Licensing Manager Entergy Operations, Inc.

17265 River Road Killona, LA 70066-0751 Winston & Strawn 1400 L Street, N.W.

Washington, DC 20005-3502 Resident Inspector/Waterford NPS P. O. Box 822 Killona, LA 70066-0751 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Parish President Council St. Charles Parish P. O. Box 302 Hahnville, LA 70057 Executive Vice President

& Chief Operating Officer Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Chairman Louisiana Public Services Commission P. O. Box 91154 Baton Rouge, LA 70825-1697