IAiiiohanFhadani - DRAFT request for extension of A mendmen"6i 109 ae 11 - I" - Oi6ei i From:
To:
Date:
Subject:
<dbuschbl @txu.com>
<mct~nrc.gov>
3/2/04 8:13AM DRAFT request for extension of Amendment 109 This is what we thought we would submit. It would be cleaned up a bit and the specific outage dates and duration would be made more general.
How's that look?
Denny
Forwarded by Dennis Buschbaum/ENERGY/TXU on 03/02/2004 07:11 AM---
Connie Wilkerson To:
Dennis Buschbaum/ENERGYITXU @TXUE 03/01/2004 10:58 cc:
Timothy Hope/ENERGY/TXU@TXUE, Fred Madden/EN ERGYITXU @TXUE AM
Subject:
Here is a copy of the DRAFT letter I had prepared last week asking for an extension of date for License Amendment No. 109.
THis will need to be revised accordingly by management for the right tone/justification, etc.
(See attached file: T04xxxclw.wpd).
F&\\TEM 15G-W}0000'1.TMP I- -..
i' O..
Page11 S o - 4z-xf-ga6 4t Mail Envelope Properties (40448880.EA1: 1: 7841)
Subject:
Creation Date:
From:
DRAFT7 request for extension of Amendment 109 3/2/04 8:08AM
<dbuschbl @txu.com>
Created By:
dbuschbl@txu.com Recipients nrc.gov owf4_po.OWFNDO MCT (Mohan Thadani)
Post Office owf4_po.OWFNDO Route nrc.gov Files MESSAGE T04xxxclw.wpd Mime.822 Options Expiration Date:
Priority:
Reply Requested:
Return Notification:
Concealed
Subject:
Security:
Size 1457 35756 52313 Date & Time 03/02/04 08:08AM None Standard No None No Standard
Mohan Thadani - To4xxxclw.wpd Page 1 CPSES-2004xxxxx Log # TXX-O4xxx March 1, 2004 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445 AND 50-446 IMPLEMENTATION OF LICENSE AMENDMENT NO. 109, INCREASING FLEXIBILITY IN MODE RESTRAINTS REF:
- 1. NRC letter from Mohan C. Thadani to M. R. Blevins "CPSES Units 1 and 2 - Issuance Of Amendments RE: Increasing Flexibility In Mode Restraints" (TAC NOS. MC0007 AND MC0008), dated January 23, 2004.
- 2.
TXU Energy letter logged TXX-03116 from C. L. Terry to NRC "License Amendment Request (LAR) 03 Revisions To Technical Specifications Regarding MODE Change Limitations Using the Consolidated Line Item Improvement Process" dated July 21, 2003 Gentlemen:
The purpose of this letter is to request an extension to the date that is currently specified for implementing CPSES License Amendment No. 109 (Reference 1).
TXU Generation Company LP (TXU Energy) submitted License Amendment Request (LAR) 03-06 (Reference 2) which requested an amendment to the CPSES Unit 1 Operating License (NPF-87) and CPSES Unit 2 Operating License (NPF-89) based on Industry/Technical Specification Task Force (TSTF) Traveler number TSTF-359 "Increase Flexibility in Mode Restraints." In the cover letter of the LAR, TXU Energy had requested that the amendment be issued by January, 2004 and implemented within 60 days of issuance.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
- Comanche Peak Diablo Canyon
- Palo Verde
- South Texas Project
- Wolf Creek
I Muohan Thadani - T04xxxcclw.wpd Page 21Z I Mohan Thadani - TO4xxxclw.wpd Page 2
License Amendment No. 109 was issued by the NRC on January 23, 2004 and is currently required to be implemented by March 23, 2004. However, after receipt of the amendment, TXU Energy has determined that full implementation of the amendment's provisions in revised Station procedures, processes and related licensing basis documents may not be readily achievable or prudent to implement by the specified implementation date.
The reasons for requesting an implementation date extension are as follows:
- 1.
TXU Energy is currently involved in final preparations for starting CPSES Unit 1 Refueling Outage IRFOIO which is scheduled to begin March 27, 2004. The available personnel resources needed to complete the relatively large number of procedure/process revisions and training required to implement Amendment No. 109 are already heavily committed to outage preparation work.
- 2.
The procedures and processes that are required to be revised and implemented for Amendment No. 109 involve Operations procedures for controlling MODE changes during Outages and Station procedures, processes and tools used for assessing risks based on the availability of systems/equipment and plant conditions. TXU Energy prefers not to implement such a major change in these types of procedues/processes so close to the begining of a Unit Refueling Outage.
- 3.
IRFO10 involves a greater scope of work that usual and is scheduled for a 36 day duration.
Accordingly, TXU Energy respectfully requests that the required date for implementing License Amendment No. 109 be extended to June 30,2004.
If you have any questions, please contact Mr. Denny Buschbaum at (254) 897-xxxx.
. -T-4 ",, --., -
- I I -I-
- - I
. . - I
-. I.
I - -
w -
I. -
- I I I ". I-I I I
. I -- 11 I
IMohan Thadani - T04xxxctw.wpd Page 31 I Mohan Thadani - TO4xxxclw.wpd Page 3
TXX-04005 Page 3 of 2 Sincerely, TXU Generation Company LP By:
TXU Generation Management Company LLC, Its General Partner Mike Blevins Senior Vice President and Principal Nuclear Officer By:
Fred W. Madden Nuclear Licensing Manager CLW/clw c -
B. S. Mallett, Region IV W. D. Johnson, Region IV M. C. Thadani, NRR Resident Inspectors, CPSES
Mohan Thadani - Mime.822 Page 1, Received: from igate.nrc.gov by nrcgwia.nrc.gov; Tue, 02 Mar 2004 08:13:33 -0500 Received: from mdcshrsmtppOl.bxu.com (mailhost2.txu.com [206.227.137.52])
by smtp-gateway ESMTPcoe id i22DD3cc022456 for <mct nrc.gov>; Tue, 2 Mar 2004 08:13:04 -0500 (EST)
Received: from CPTXUDSE202.cpses.tu.com (unverified) by mdcshrsmtppOl.txu.com (Content Technologies SMTPRS 4.3.12) with ESMTP id
<T6816d48e69cee3893442c @ mdcshrsmtppOl.txu.com> for <mct@ nrc.gov>;
Tue, 2 Mar 2004 07:13:47 -0600 Received: from CPTXUDSE215.cpses.tu.com ([172.31.223.215])
by CPTXUDSE202.cpses.tu.com (Lotus Domino Release 5.0.9a) with ESMTP id 2004030207130732:188; Tue, 2 Mar 2004 07:13:07 -0600
Subject:
DRAFT request for extension of Amendment 109 To: mct~nrc.gov X-Mailer: Lotus Notes Release 5.0.9a January 7, 2002 Message-ID: <OF1 2429D01.62AC1 6CE-ON86256E4B.00480715-86256E4B.0048A74C @ cpses.tu.com>
From: dbuschbl @txu.com Date: Tue, 2 Mar 2004 07:08:43 -0600 MIME-Version: 1.0 X-MIMETrack: Serialize by Router on CPTXUDSE215/ServerfrXU(Release 5.0.9a IJanuary 7, 2002) at 03/0212004 07:08:44 AM, Itemize by SMTP Server on CPTXUDSE202IServer/TXU(Release 5.0.9a Panuary 7,2002) at 03/02/2004 07:13:07 AM, Serialize by Router on CPTXUDSE202/ServerITXU(Release 5.0.9a JJanuary 7, 2002) at 03/02/2004 07:13:08 AM Content-type: multipart/mixed; Boundary="O.-...=09BBE4D8DFDB81858f9e8a93df938690918cO9BBE4D8DFDB8185" Content-Disposition: inline
--O__=09BBE4D8DFDB81858f9e8a93df938690918cO9BBE4D8DFDB8185 Content-type: text/plain; charset=us-ascii This is what we thought we would submit. It would be cleaned up a bit and the specific outage dates and duration would be made more general.
How's that look?
Denny
Forwarded by Dennis Buschbaurl/ENERGY/TXU on 03/02/2004 07:11 AM ----
Connie Wilkerson To:
Dennis Buschbaum/ENERGYITXU@TXUE 03/01/2004 10:58 cc:
Timothy Hope/ENERGY/TXU@TXUE, Fred Madden/ENERGY/TXU@TXUE AM
Subject:
Here is a copy of the DRAFT letter I had prepared last week asking for an extension of date for License Amendment No. 109.
THis will need to be revised accordingly by management for the right tonerjustification, etc.
IMohdn Thadani - Mime.822 Page 24 (See attached file: T04xxxclw.wpd).
-O__=09BBE4D8DFDB81858f9e8a93df938690918cO9BBE4D8DFDB8185 Content-type: application/octet-stream; name="TO4xxxclw.wpd' Content-Disposition: attachment; filename='TO4xxxclw.wpd Content-Transfer-Encoding: base64 Click to view Base64 Encoded File T04xxxclw.wpd