Meeting with Entergy to Discuss Issues with Extended Power Uprate and Alternate Source Term Submittals
ML042110088
Person / Time
Site: Waterford 
(NPF-038)
Issue date: 07/29/2004
From: Kalyanam N
NRC/NRR/DLPM/LPD4
To: Gramm R
NRC/NRR/DLPM/LPD4
Kalyanam N,NRR/DLPM,415-1480
References
Download: ML042110088 (6)


Text

July 29, 2004 MEMORANDUM TO: Robert A. Gramm, Chief, Section 1 Project Directorate IV Division of Licensing Project Management FROM:

N. Kalyanam, Project Manager, Section 1/RA/

Project Directorate IV Division of Licensing Project Management

SUBJECT:

FORTHCOMING MEETING WITH ENTERGY OPERATIONS, INC.

(ENTERGY), WATERFORD STEAM ELECTRIC STATION, UNIT 3 (WATERFORD 3)

DATE & TIME:

Thursday, August 12, 2004 9:00 a.m. to 3:00 p.m.

LOCATION:

U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room 0-8B6 Rockville, Maryland PURPOSE:

Meet with NRC management to discuss the issues with Extended Power Uprate and Alternate Source Term submittals.

CATEGORY 1:

This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC Entergy M. Hart, NRR T. Leonardr R. Gramm, NRR J. Burford N. Kalyanam, NRR P. Sicard et. al.

B. Miller Docket No. 50-382

Attachment:

Agenda (Accession No. ML042110088) cc w/att: See next page MEETING CONTACTS:

N. Kalyanam, NRR T. Alexion, NRR 301-415-1480 301-415-1326 nxk@nrc.gov twa@nrc.gov

July 29, 2004 MEMORANDUM TO: Robert A. Gramm, Chief, Section 1 Project Directorate IV Division of Licensing Project Management FROM:

N. Kalyanam, Project Manager, Section 1/RA/

Project Directorate IV Division of Licensing Project Management

SUBJECT:

FORTHCOMING MEETING WITH ENTERGY OPERATIONS, INC.

(ENTERGY), WATERFORD STEAM ELECTRIC STATION, UNIT 3 (WATERFORD 3)

DATE & TIME:

Thursday, August 12, 2004 9:00 a.m. to 3:00 p.m.

LOCATION:

U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room 0-8B6 Rockville, Maryland PURPOSE:

Meet with NRC management to discuss the issues with Extended Power Uprate and Alternate Source Term submittals.

CATEGORY 1:

This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC Entergy M. Hart, NRR T. Leonardr R. Gramm, NRR J. Burford N. Kalyanam, NRR P. Sicard et. al.

B. Miller Docket No. 50-382

Attachment:

Agenda (Accession No.ML042110088) cc w/att: See next page MEETING CONTACTS:

N. Kalyanam, NRR T. Alexion, NRR 301-415-1480 301-415-1326 nxk@nrc.gov twa@nrc.gov DISTRIBUTION: See attached page Accession Number: ML042110088 OFFICE PDIV-1/LA PDIV-1/PM PDIV-1/SC NAME DBaxley NKalyanam RGramm DATE 4/ /04 7/28/04 7/28/04 OFFICIAL RECORD COPY

DISTRIBUTION FOR FORTHCOMING MEETING WITH ENTERGY ON AUGUST 12, 2004.

Dated: July 29, 2004 Hardcopy:

PUBLIC PDIV-1 Reading Receptionist OWFN/TWFN E-Mail:

RidsNrrAdpt (BSheron)

RidsNrrDlpm (TMarsh/JLyons)

RidsNrrDlpmLpdiv (HBerkow)

RidsNrrDlpmLpdiv1 (RGramm)

RidsNrrLADBaxley RidsNrrLADJohnson KGrimes RidsOpaMail R. Dennig S. LaVie M. Hart JDixon-Herrity Chu-Yu Liang J. Uhle TMensah RidsOgcRp RidsRgn4MailCenter(AHowell/BHenderson)

RidsAcrsAcnwMailCenter PMNS

AGENDA MEETING WITH ENTERGY OPERATIONS, INC.

WATERFORD STEAM ELECTRIC STATION, UNIT 3 TO DISCUSS THE ISSUES WITH EXTENDED POWER UPRATE SUBMITTAL AND ALTERNATE SOURCE TERM SUBMITTAL AUGUST 12, 2004 Introduction and meeting objective discuss the possibility of dedicating a reviewer to the Alternate Source Term (AST) amendment request in order to achieve NRC approval before next refueling outage in Spring 2005.

discuss how best to address the late October ACRS sub-committee meeting in regards to Control Room habitability.

discuss the NRC schedule for AST approval and Extended Power Uprate approval.

Public comment

June 2004 Waterford Steam Electric Station, Unit 3 cc:

Mr. Michael E. Henry, State Liaison Officer Department of Environmental Quality Permits Division P.O. Box 4313 Baton Rouge, Louisiana 70821-4313 Vice President Operations Support Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Director Nuclear Safety Assurance Entergy Operations, Inc.

17265 River Road Killona, LA 70066-0751 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205 General Manager Plant Operations Waterford 3 SES Entergy Operations, Inc.

17265 River Road Killona, LA 70066-0751 Licensing Manager Entergy Operations, Inc.

17265 River Road Killona, LA 70066-0751 Winston & Strawn 1400 L Street, N.W.

Washington, DC 20005-3502 Resident Inspector/Waterford NPS P. O. Box 822 Killona, LA 70066-0751 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Parish President Council St. Charles Parish P. O. Box 302 Hahnville, LA 70057 Executive Vice President

& Chief Operating Officer Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Chairman Louisiana Public Services Commission P. O. Box 91154 Baton Rouge, LA 70825-1697