Letter Sequence RAI |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML040300802, ML040631055, ML042520157, ML042670485, ML050870511, ML051090111, ML052290107, ML052800176, W3F1-2004-0076, To Amendment Request NPF-38-256, Alternate Source Term, W3F1-2004-0085, Schedule Clarification for Amendment Request NPF-38-249, Extended Power Uprate, W3F1-2004-0095, To Amendment Request NPF-38-256 Alternate Source Term, W3F1-2004-0101, To Amendment Request NPF-38-256, Alternate Source Term, Waterford Steam Electric Station, Unit 3
|
MONTHYEARML0425201572004-01-14014 January 2004 E-mail to T. Alexion Dated 1/14/04 Waterford - Extended Power Uprate Project stage: Other ML0401405152004-01-14014 January 2004 Meeting with Entergy, Waterford Steam Electric Station, Unit 3 Extended Power Uprate Amendment Request Dated 11/13/2003 Project stage: Meeting ML0403302602004-01-28028 January 2004 1/28/04 Waterford 3 - RAI Revision to Facility Operating License & TS - Extended Power Uprate Request. TAC MC1355 Project stage: RAI ML0403008022004-01-28028 January 2004 FRN -Notice of Consideration of Issuance of Amendment for Extended Power Uprate and Opportunity for Hearing Project stage: Other W3F1-2004-0004, Supplemental Information Extended Power Uprate - Power Ascension Testing2004-01-29029 January 2004 Supplemental Information Extended Power Uprate - Power Ascension Testing Project stage: Request ML0425201642004-01-30030 January 2004 E-mail Dated 1/30/04 RAI from Environmental Section on Waterford Unit 3 Project stage: RAI ML0425201672004-02-10010 February 2004 E-mail Dated 2/10/04 Waterford - Draft RAI from Human Performance, Piping Integrity and Electrical Groups Project stage: Draft RAI ML0425201702004-02-18018 February 2004 E-mail Dated 2/18/04 Re RAI from I&C - Waterford Project stage: RAI ML0405506052004-02-20020 February 2004 Westinghouse Request Withholding from Public Disclosure, Waterford 3, Extended Power Uprate, Appendix 1 - Safety Evaluation Report Compliance, MC1355 Project stage: Approval ML0425201712004-02-23023 February 2004 E-mail Dated 2/23/04 Waterford RAI Containment Systems Project stage: RAI ML0406310552004-02-26026 February 2004 Summary of Entergy Operations, Inc. Presentation of Extended Power Uprate Project stage: Other ML0426704852004-03-0202 March 2004 E-mail from D. Miller to K. Kalyanam Re RAI from J. Tsao Project stage: Other ML0426704892004-03-0202 March 2004 E-mail from B. Miller to N. Kalyanam RAI from SPLB-Angelo Stubbs Project stage: RAI W3F1-2004-0017, Supplement to Amendment Request NPF-38-249 Regarding Extended Power Uprate2004-03-0404 March 2004 Supplement to Amendment Request NPF-38-249 Regarding Extended Power Uprate Project stage: Supplement ML0406909622004-03-0909 March 2004 Extended Power Uprate Acceptance Review Project stage: Acceptance Review ML0407809952004-03-16016 March 2004 RAI, Proposed Revision to Facility Operation License and TSs - Extended Power Uprate Request Project stage: RAI ML0408506542004-03-24024 March 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI ML0412102452004-03-26026 March 2004 Request for Additional Information, Revision to Facility Operating License & Technical Specifications - Extended Power Uprate Request Project stage: RAI ML0409102392004-03-31031 March 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI ML0410005142004-04-0808 April 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI W3F1-2004-0029, Extended Power Uprate, Waterford, Unit 3 Supplement to Amendment Request2004-04-15015 April 2004 Extended Power Uprate, Waterford, Unit 3 Supplement to Amendment Request Project stage: Supplement ML0411301942004-04-20020 April 2004 RAI Related to Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI ML0412705672004-05-0404 May 2004 RAI, Revision to Facility Operating License and TSs - Extended Power Uprate Request Project stage: RAI W3F1-2004-0035, Supplemental to Amendment Request for Extended Power Uprate2004-05-0707 May 2004 Supplemental to Amendment Request for Extended Power Uprate Project stage: Supplement W3F1-2004-0028, License Amendment Request NPF-38-254, Reactor Coolant System Leakage Detection2004-05-0707 May 2004 License Amendment Request NPF-38-254, Reactor Coolant System Leakage Detection Project stage: Request W3F1-2004-0037, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-05-12012 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0413801452004-05-13013 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement W3F1-2004-0043, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-05-21021 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement W3F1-2004-0047, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-05-26026 May 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0417405772004-06-21021 June 2004 RAI, Revision to Facility Operating License and Technical Specifications - Extended Power Uprate Request, TAC MC1355 Project stage: RAI ML0420202942004-07-15015 July 2004 License Amendment Request NPF-38-256, Alternate Source Term Project stage: Request W3F1-2004-0061, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-07-28028 July 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0421100882004-07-29029 July 2004 Meeting with Entergy to Discuss Issues with Extended Power Uprate and Alternate Source Term Submittals Project stage: Request ML0422303352004-08-10010 August 2004 August 11, 12 and 13, 2004 Meeting with Westinghouse Re Waterford Main Steam Line Break, Feedwater Line Break and EPU Project stage: Meeting W3F1-2004-0068, Supplement to Amendment Request NPF-38-249 Extended Power Uprate2004-08-10010 August 2004 Supplement to Amendment Request NPF-38-249 Extended Power Uprate Project stage: Supplement W3F1-2004-0071, Supplement to Alternate Source Term Submittal2004-08-19019 August 2004 Supplement to Alternate Source Term Submittal Project stage: Request ML0423904892004-08-26026 August 2004 Meeting with Entergy to Discuss Issues with Extended Power Uprate and Alternate Source Term Submittals Project stage: Meeting W3F1-2004-0076, To Amendment Request NPF-38-256, Alternate Source Term2004-09-0101 September 2004 To Amendment Request NPF-38-256, Alternate Source Term Project stage: Other W3F1-2004-0078, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-09-14014 September 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0427505192004-09-29029 September 2004 RAI Extended Power Uprate Request and Alternate Source Term Request Project stage: RAI ML0427402482004-09-30030 September 2004 (3) Steam Elecric Station, 3, Draft EA and Finding of No Significant Impact Related to a Proposed License Amendment to Increase the Licensed Power Level (Tac. MC1355) Project stage: Draft Other W3F1-2004-0086, Supplement to Amendment Request NPF-38-249, Extended Power Uprate2004-10-0808 October 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement W3F1-2004-0092, Supplement to Amendment Request NPF-38-249 Extended Power Uprate2004-10-0808 October 2004 Supplement to Amendment Request NPF-38-249 Extended Power Uprate Project stage: Supplement W3F1-2004-0085, Schedule Clarification for Amendment Request NPF-38-249, Extended Power Uprate2004-10-13013 October 2004 Schedule Clarification for Amendment Request NPF-38-249, Extended Power Uprate Project stage: Other W3F1-2004-0095, To Amendment Request NPF-38-256 Alternate Source Term2004-10-13013 October 2004 To Amendment Request NPF-38-256 Alternate Source Term Project stage: Other W3F1-2004-0101, To Amendment Request NPF-38-256, Alternate Source Term, Waterford Steam Electric Station, Unit 32004-10-19019 October 2004 To Amendment Request NPF-38-256, Alternate Source Term, Waterford Steam Electric Station, Unit 3 Project stage: Other ML0430102382004-10-21021 October 2004 Supplement to Amendment Request NPF-38-249, Extended Power Uprate Project stage: Supplement ML0431006112004-10-26026 October 2004 RAI - Revision to Facility Operating License and Technical Specifications - Extended Power Uprate Request Project stage: RAI W3F1-2004-0089, Supplement to Amendment Request NPF-38-2492004-10-29029 October 2004 Supplement to Amendment Request NPF-38-249 Project stage: Supplement W3F1-2004-0107, Supplement to Amendment Request NPF-38-2492004-10-29029 October 2004 Supplement to Amendment Request NPF-38-249 Project stage: Supplement 2004-03-04
[Table View] |
Text
October 26, 2004 Mr. Joseph E. Venable Vice President Operations Entergy Operations, Inc.
17265 River Road Killona, LA 70066-0751
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 (WATERFORD 3) -
REQUEST FOR ADDITIONAL INFORMATION RELATED TO REVISION TO FACILITY OPERATING LICENSE AND TECHNICAL SPECIFICATIONS -
EXTENDED POWER UPRATE REQUEST (TAC NO. MC1355)
Dear Mr. Venable:
By application dated November 13, 2003, and supplemented by letters dated January 29, March 4, April 15, May 7, May 12, May 13, May 21, May 26, July 14, July 15, July 28, August 10, August 19, August 25, September 1, September 14, October 8 (2 letters),
October 13, October 18, and October 19, 2004, Entergy Operations, Inc., requested changes to the Facility Operating License and Technical Specifications for the Waterford Steam Electric Station, Unit 3, which would allow an increase in the rated thermal power from 3,441 megawatts thermal (MWt) to 3,716 MWt.
After reviewing your request, the Nuclear Regulatory Commission staff has determined that additional information is required in the area of transient testing to complete the review. We discussed this information with your staff by telephone and they agreed to provide the additional information requested in the enclosure within 15 days of receipt of this letter.
If you have any questions, please call me at (301) 415-1480.
Sincerely,
/RA/
N. Kalyanam, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-382
Enclosure:
Request for Additional Information cc w/encl: See next page
October 26, 2004 Mr. Joseph E. Venable Vice President Operations Entergy Operations, Inc.
17265 River Road Killona, LA 70066-0751
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 (WATERFORD 3) -
REQUEST FOR ADDITIONAL INFORMATION RELATED TO REVISION TO FACILITY OPERATING LICENSE AND TECHNICAL SPECIFICATIONS -
EXTENDED POWER UPRATE REQUEST (TAC NO. MC1355)
Dear Mr. Venable:
By application dated November 13, 2003, and supplemented by letters dated January 29, March 4, April 15, May 7, May 12, May 13, May 21, May 26, July 14, July 15, July 28, August 10, August 19, August 25, September 1, September 14, October 8 (2 letters),
October 13, October 18, and October 19, 2004, Entergy Operations, Inc., requested changes to the Facility Operating License and Technical Specifications for the Waterford Steam Electric Station, Unit 3, which would allow an increase in the rated thermal power from 3,441 megawatts thermal (MWt) to 3,716 MWt.
After reviewing your request, the Nuclear Regulatory Commission staff has determined that additional information is required in the area of transient testing to complete the review. We discussed this information with your staff by telephone and they agreed to provide the additional information requested in the enclosure within 15 days of receipt of this letter.
If you have any questions, please call me at (301) 415-1480.
Sincerely,
/RA/
N. Kalyanam, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-382
Enclosure:
Request for Additional Information cc w/encl: See next page DISTRIBUTION PUBLIC PDIV-1 r/f RidsOgcRp RidsAcrsAcnwMailCenter RidsNrrDlpmLpdiv1 (DJaffe)
RidsNrrPMNKalyanam RidsNrrLADJohnson RidsRgn4MailCenter (AHowell)
JTatum/AStubbs RidsNrrDlpmDpr RidsNrrDeDpr RidsNrrDssaDpr RidsNrrLADJohnson Accession No.: ML043100611
- RAI input from the staff without any major change OFFICE PDIV-1/PM PDIV-1/LA DSSA/SPlB/A LPM-Power Uprate PDIV-1/SC(A)
NAME NKalyanam DJohnson JTatum/AStubbs*
JStang DJaffe for MWebb DATE 10/21/04 10/21/04 10/15/04 10/24/04 10/26/04 OFFICIAL COPY
ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION ENTERGY OPERATIONS, INC. (ENTERGY)
WATERFORD STEAM ELECTRIC STATION, UNIT 3 (WATERFORD 3)
DOCKET NO. 50-382 In general, the NRC staff does not review and approve the application of computer codes and analyses that are credited for evaluating balance-of-plant performance and primary/secondary interactions. Consequently, the startup test program is relied upon as a quality check to:
a) confirm that analyses and any modifications and adjustments that are necessary for a proposed extended power uprate (EPU) have been completed properly, and b) benchmark the analyses against the actual integrated performance of the plant, thereby assuring conservative results. This is consistent with the requirements stated in Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, which states that design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate calculational methods, or by the performance of a suitable testing program; and requires that design changes be subject to design control measures commensurate with those applied to the original plant design (which includes startup testing).
In order to implement the proposed EPU at Waterford 3, the main steam system will operate at a lower pressure and higher mass flow rate, with corresponding operating conditions for the main feedwater system. In order to accommodate these revised operating conditions, the following changes are necessary:
a.
The reactor power cutback system will be put in service at 65 percent power (instead of the current 70 percent), and the reactor trip on turbine trip setpoint will be reduced to 65 percent, to compensate for the relative reduction in the capacity of the steam bypass control system (SBCS).
b.
Changes to the controllers and/or setpoints of the atmospheric dump valves (ADVs) are being made in order to maintain adequate margin between the actuation setpoints for the SBCS and the ADVs, providing assurance that the ADVs will not actuate prematurely (the SBCS is relied upon to prevent unnecessary challenges to the ADVs).
c.
A new high pressure main turbine rotor with all reaction blading is being installed, potentially affecting the inertia of the main turbine and overshoot during a turbine overspeed transient, such as during a loss-of-load.
d.
Modifications to various control systems and setpoints will be required to ensure that the plant will be maintained within desired operating bands during normal operations and during minor load changes and load rejection events.
Entergys test program primarily includes steady-state testing with some minor load changes, and no large-scale transient testing is proposed. Sufficient information has not been provided to demonstrate that, in the absence of large-scale transient testing, the integrated plant response during transient conditions will be as expected. Entergy is, therefore, requested to either: a. provide additional information that explains in detail how the proposed EPU startup ENCLOSURE test program, in conjunction with the original Waterford 3 startup test results and applicable industry experience, assure the plant will respond as expected during postulated transient conditions following implementation of the proposed EPU, given the revised operating conditions that will exist and plant changes that are being made; or b. describe transient testing that will be included in the startup test program in order to provide this assurance, and explain in detail how the proposed transient testing will accomplish this.
July 2003 Waterford Steam Electric Station, Unit 3 cc:
Mr. Michael E. Henry, State Liaison Officer Department of Environmental Quality Permits Division P.O. Box 4313 Baton Rouge, Louisiana 70821-4313 Vice President, Operations Support Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Director Nuclear Safety Assurance Entergy Operations, Inc.
17265 River Road Killona, LA 70066-0751 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205 General Manager Plant Operations Waterford 3 SES Entergy Operations, Inc.
17265 River Road Killona, LA 70066-0751 Licensing Manager Entergy Operations, Inc.
17265 River Road Killona, LA 70066-0751 Winston & Strawn 1400 L Street, N.W.
Washington, DC 20005-3502 Resident Inspector/Waterford NPS P. O. Box 822 Killona, LA 70066-0751 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011 Parish President Council St. Charles Parish P. O. Box 302 Hahnville, LA 70057 Executive Vice President
& Chief Operating Officer Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Chairman Louisiana Public Services Commission P. O. Box 91154 Baton Rouge, LA 70825-1697