Summary of Entergy Operations, Inc. Presentation of Extended Power Uprate
ML040631055
Person / Time
Site: Waterford Entergy icon.png
Issue date: 02/26/2004
From: Kalyanam N
NRC/NRR/DLPM/LPD4
To:
Kalyanam N, NRR/DLPM, 415-1480
References
TAC MC1355
Download: ML040631055 (6)


Text

February 26, 2004 FACILITY: Waterford Steam Electric Station, Unit 3 (Waterford 3)

LICENSEE: Entergy Operations, Inc.

SUBJECT:

SUMMARY

OF FEBRUARY 5, 2004, ENTERGY OPERATIONS, INC. (EOI)

PRESENTATION ON EXTENDED POWER UPRATE AT WATERFORD 3 (TAC NO. MC1355)

Entergy Operations, Inc. was at the NRC offices in Rockville, Maryland on February 5, 2004, to make a presentation on the extended power uprate amendment request dated November 13, 2003, and to provide clarifications as needed and answer any questions that arose during the initial review of the submittal. An attendance list is provided in the enclosure.

The licensee made the presentation from 10:00 a.m. to 11:50 a.m. The slides used during the meeting are available in ADAMS under accession number ML040560396. In the afternoon session, questions were raised by the NRC staff reviewers from the Reactor Systems Branch, the Plant Systems Branch, the Materials and Chemical Engineering Branch, and the Mechanical and Civil Engineering Branch. There was no public meeting feedback.

Pursuant to "Commission Policy Statement on Staff Meetings Open to the Public," 59 Federal Register 48340, dated September 20, 1994, the meeting notice was issued on January 14, 2004 (ML040140515).

/RA/

N. Kalyanam, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-382

Enclosure:

List of Attendees cc w/encl: See next page

February 26, 2004 FACILITY: Waterford Steam Electric Station, Unit 3 (Waterford 3)

LICENSEE: Entergy Operations, Inc.

SUBJECT:

SUMMARY

OF FEBRUARY 5, 2004, ENTERGY OPERATIONS, INC. (EOI)

PRESENTATION ON EXTENDED POWER UPRATE AT WATERFORD 3 (TAC NO. MC1355)

Entergy Operations, Inc. was at the NRC offices in Rockville, Maryland on February 5, 2004, to make a presentation on the extended power uprate amendment request dated November 13, 2003, and to provide clarifications as needed and answer any questions that arose during the initial review of the submittal. An attendance list is provided in the enclosure.

The licensee made the presentation from 10:00 a.m. to 11:50 a.m. The slides used during the meeting are available in ADAMS under accession number ML040560396. In the afternoon session, questions were raised by the NRC staff reviewers from the Reactor Systems Branch, the Plant Systems Branch, the Materials and Chemical Engineering Branch, and the Mechanical and Civil Engineering Branch. There was no public meeting feedback.

Pursuant to "Commission Policy Statement on Staff Meetings Open to the Public," 59 Federal Register 48340, dated September 20, 1994, the meeting notice was issued on January 14, 2004 (ML040140515).

/RA/

N. Kalyanam, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-382

Enclosure:

List of Attendees cc w/encl: See next page DISTRIBUTION: See Next Page Adams Accession No. ML040631055 OFFICE PDIV-1/PM PDIV-1/LA PDIV1/SC NAME NKalyanam DJohnson RGramm DATE 2/26/04 2/26/04 2/26/04 OFFICIAL RECORD COPY

DISTRIBUTION FOR MEETING

SUMMARY

DATED February 26, 2004:

PUBLIC PD IV-1 Reading File RidsNrrDlpm (ELeeds/TMarsh)

RidsNrrDlpmLpdiv (HBerkow)

RidsNrrDlpmLpdiv1 (RGramm)

RidsNrrLADJohnson RidsOgcRp RidsAcrsAcnwMailCenter DJackson, EDO RidsRgn4MailCenter (AHowell)

JAlbright JTsao SDennis Chu-Yu Liang RDavis KDesai HLi LBrown WLyon JBongarra JCai AStubbs PClifford JWu TScarbrough RLobel JMedoff FOrr

LIST OF ATTENDEES MEETING WITH ENTERGY OPERATIONS, INC.

FEBRUARY 5, 2004 ENTERGY OPERATIONS, INC.

T. Brennan D. Viener T. Leonard D. Madere B. Miller P. Sicard D. Whiddon WESTINGHOUSE R. Morrison S. OHearn J. Cleary D. Baisley G. Hess OTHER G. Wrobel (Rochester Gas & Electric)

NRC J. Tsao S. Dennis C. Liang R. Davis K. Desai H. Li L. Brown W. Lyon J. Bongarra J. Wu T. Scarbrough R. Lobel J. Medoff F. Orr P. Clifford A. Stubbs J. Cai N. Kalyanam Enclosure 1

Waterford Steam Electric Station, Unit 3 cc:

Mr. Michael E. Henry, State Liaison Officer Regional Administrator, Region IV Department of Environmental Quality U.S. Nuclear Regulatory Commission Permits Division 611 Ryan Plaza Drive, Suite 1000 P.O. Box 4313 Arlington, TX 76011 Baton Rouge, Louisiana 70821-4313 Parish President Council Vice President, Operations Support St. Charles Parish Entergy Operations, Inc. P. O. Box 302 P. O. Box 31995 Hahnville, LA 70057 Jackson, MS 39286-1995 Executive Vice President Director & Chief Operating Officer Nuclear Safety Assurance Entergy Operations, Inc.

Entergy Operations, Inc. P. O. Box 31995 17265 River Road Jackson, MS 39286-1995 Killona, LA 70066-0751 Chairman Wise, Carter, Child & Caraway Louisiana Public Services Commission P. O. Box 651 P. O. Box 91154 Jackson, MS 39205 Baton Rouge, LA 70825-1697 General Manager Plant Operations Mr. Joseph E. Venable Waterford 3 SES Vice President Operations Entergy Operations, Inc. Entergy Operations, Inc.

17265 River Road 17265 River Road Killona, LA 70066-0751 Killona, LA 70066-0751 Licensing Manager Entergy Operations, Inc.

17265 River Road Killona, LA 70066-0751 Winston & Strawn 1400 L Street, N.W.

Washington, DC 20005-3502 Resident Inspector/Waterford NPS P. O. Box 822 Killona, LA 70066-0751 July 2003