ML042030152

From kanterella
Jump to navigation Jump to search
Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Licensee Performance and Planned Activities as Part of the Manual Chapter 0350 Process at the Davis-Besse Nuclear Power Station
ML042030152
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/20/2004
From: Christine Lipa
NRC/RGN-III/DRP/RPB4
To:
References
Download: ML042030152 (5)


Text

July 20, 2004 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF THE JULY 13, 2004, PUBLIC MEETING TO DISCUSS LICENSEE PERFORMANCE AND PLANNED ACTIVITIES AS PART OF THE MANUAL CHAPTER 0350 PROCESS AT THE DAVIS-BESSE NUCLEAR POWER STATION On July 13, 2004, the Nuclear Regulatory Commission (NRC) held a public meeting at the Oak Harbor High School in Oak Harbor, Ohio. The meeting was between the NRC Davis-Besse Oversight Panel and FirstEnergy Nuclear Operating Company (FENOC) to discuss licensee performance and planned activities as part of the Manual Chapter 0350 process at the Davis-Besse Nuclear Power Station. The letter of notification, meeting notice, NRC presentation, and licensee presentation can be found in ADAMS as ML041680321, ML041680292, ML041960317, and ML042020130, respectively. The transcript of the meeting will be made publicly available in ADAMS and on the NRCs Davis-Besse web page when it is available. A list of NRC and licensee meeting participants can be found in the attached Enclosure. Agenda topics included plant performance, discussion of the status of the licensees improvement initiatives, performance monitoring and independent assessments; and a discussion of site assessment, mid-cycle outage and oversight perspective.

These documents and many others related to the reactor vessel head degradation can also be found on the NRCs website at http://www.nrc.gov/reactors/operating/ops-experience/vessel-head-degradation.html.

/RA/

Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

As Stated See Attached Distribution

DOCUMENT NAME: C:\ORPCheckout\FileNET\ML042030152.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME RSmith/dtp CLipa DATE 07/20/04 07/20/04 OFFICIAL RECORD COPY

FirstEnergy Nuclear Operating Company cc w/encl: The Honorable Dennis Kucinich G. Leidich, President - FENOC J. Hagan, Senior Vice President Engineering and Services, FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, Attorney, FirstEnergy Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Board of County Commissioners of Lucas County C. Koebel, President, Ottawa County Board of Commissioners D. Lochbaum, Union Of Concerned Scientists J. Riccio, Greenpeace P. Gunter, N.I.R.S.

C. Emahiser, Ottawa County Sheriff J. P. Greer, Director, Ottawa County Emergency Management Agency H. Barlos, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff B. Halsey, Director, Lucas County Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable John Weber The Honorable Lowell C. Krumnow The Honorable Joseph Verkin The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown The Honorable Jacqueline Bird INPO

FirstEnergy Nuclear Operating Company ADAMS Distribution:

DFT DWW Project Director, NRR Project Mgr., NRR RidsNrrDipmlipb JLC1 GEG HBC RML2 SRI Davis-Besse DRPIII DRSIII PLB1 JRK1 DB0350

Enclosure Meeting Participants NRC J. Grobe, Chairman, Davis-Besse Oversight Panel C. Lipa, Branch Chief, DRP, RIII, Davis-Besse J. Hopkins, Project Manager, NRR C. Thomas, Senior Resident Inspector, Davis-Besse J. Rutkowski, Resident Inspector, Davis-Besse V. Mitlying, Public Affairs, RIII FirstEnergy Nuclear Operating Company M. Bezilla, Site Vice President R. Hansen, Vice President, Nuclear Oversight B. Allen, Plant Manager K. Ostrowski, Manager, Nuclear Operations