Press Release-lll-04-041: NRC to Meet with Detroit Firm on Apparent Transportation and Storage ViolationsML041910138 |
Person / Time |
---|
Issue date: |
07/09/2004 |
---|
From: |
Office of Public Affairs Region II |
---|
To: |
|
---|
References |
---|
Press Release-III-04-041 |
Download: ML041910138 (2) |
|
|
---|
Category:Press Release
MONTHYEARML23166A1082023-04-0303 April 2023 News Release-II-23-004: NRC Proposes $70,000 Fine to Urenco USA Uranium Enrichment Facility ML23166A0932023-03-30030 March 2023 News Release-II-23-003: NRC Names New Resident Inspector at Plant Vogtle ML23166A0682023-03-21021 March 2023 News Release-III-23-006: NRC Names New Resident Inspector at Byron Nuclear Generating Station ML23166A0182023-03-0707 March 2023 News Release-III-23-005: NRC Names New Senior Resident Inspector at Byron Nuclear Power Plant ML23052A1072023-02-14014 February 2023 News Release-III-23-004: NRC Names New Senior Resident Inspector at Perry Nuclear Power Station ML23052A1032023-02-14014 February 2023 News Release-II-23-002: NRC Names New Resident Inspector at Browns Ferry Nuclear Plant ML23052A1062023-02-0101 February 2023 News Release-III-23-003: NRC Names New Senior Resident Inspector at Dresden Nuclear Power Plant ML23052A1052023-01-26026 January 2023 News Release-III-23-002: NRC Names New Senior Resident Inspector at LaSalle Nuclear Power Plant ML23052A1042023-01-11011 January 2023 News Release-III-23-001: NRC Names New Senior Resident Inspector at Dresden Nuclear Power Plant ML23052A1022023-01-0505 January 2023 News Release-II-23-001: NRC Announces Resident Inspectors at McGuire Nuclear Station ML22346A0582022-11-21021 November 2022 News Release-II-22-028: NRC Names New Resident Inspector at Watts Bar Nuclear Power Plant ML22305A5492022-10-17017 October 2022 News Release-II-22-027: NRC Conducts Special Inspection at Nuclear Fuel Services Facility ML22305A5482022-10-13013 October 2022 News Release-II-22-026: NRC Names New Senior Resident Inspector at Harris Nuclear Power Plant ML22305A5502022-10-13013 October 2022 News Release-III-22-024: NRC Names New Inspector at Fermi Nuclear Power Plant ML22273A1282022-09-30030 September 2022 News Release-II-22-025: NRC Monitoring Hurricane Ian ML22270A0822022-09-14014 September 2022 News Release-II-22-024: NRC Schedules Pre-Decisional Enforcement Conference with BWXT ML22231A2002022-08-17017 August 2022 News Release-II-22-023: NRC Names Senior Resident Inspector at BWXT Nuclear Fuel Facility ML22223A1262022-08-11011 August 2022 News Release-II-22-022: NRC Names New Resident Inspector at Sequoyah Nuclear Power Plant ML22223A1252022-08-10010 August 2022 News Release-II-22-021: NRC Launches Special Inspection at Farley Nuclear Power Plant ML22215A2122022-08-0303 August 2022 News Release-II-22-020: NRC Announces Resident Inspectors at Robinson Nuclear Power Plant ML22199A0592022-07-0707 July 2022 News Release-II-22-018: NRC Names New Resident Inspector at Brunswick Nuclear Power Plant ML22199A0602022-07-0707 July 2022 News Release-II-22-019: NRC Names New Senior Resident Inspector at Vogtle Nuclear Power Plant ML22199A0662022-06-28028 June 2022 News Release-III-22-020: NRC Names New Resident Inspector at Clinton Nuclear Power Plant Press Release-II-22-017, NRC Names New Senior Resident Inspector at Surry Nuclear Power Plant2022-06-23023 June 2022 Press Release-II-22-017: NRC Names New Senior Resident Inspector at Surry Nuclear Power Plant ML22199A0652022-06-22022 June 2022 News Release-III-22-019: NRC Names New Resident Inspector at Dresden Nuclear Power Station ML22199A0642022-06-17017 June 2022 News Release-III-22-018: NRC Proposes $16,000 Civil Penalty to Mistras Group, Inc ML22199A0632022-06-16016 June 2022 News Release-III-22-017: NRC to Conduct Open House to Discuss 2021 Performance of Point Beach Nuclear Power Plant ML22199A0622022-06-15015 June 2022 News Release-III-22-016: NRC to Hold Public Meeting to Discuss 2021 Performance of Davis-Besse Nuclear Power Plant ML22153A1302022-05-24024 May 2022 News Release-III-22-013: NRC to Hold Public Meeting to Discuss 2021 Performance of Donald C. Cook Nuclear Power Plant ML22153A1312022-05-24024 May 2022 News Release-III-22-014: NRC to Hold Webinar to Discuss 2021 Performance of Dresden and Quad Cities Nuclear Power Plants ML22153A1292022-05-20020 May 2022 News Release-III-22-012: NRC to Hold Public Meeting to Discuss 2021 Performance of Byron and Braidwood Nuclear Power Plants ML22153A1282022-05-17017 May 2022 News Release-III-22-011: NRC to Conduct Pre-Decisional Enforcement Conference to Discuss Niowave Inc ML22153A1272022-05-13013 May 2022 News Release-II-22-016: NRC Schedules Public Meeting to Discuss Safety Performance of Westinghouse Columbia Fuel Facility Press Release-III-22-009, NRC to Hold Public Meeting to Discuss 2021 Performance of Perry Nuclear Power Plant2022-05-10010 May 2022 Press Release-III-22-009: NRC to Hold Public Meeting to Discuss 2021 Performance of Perry Nuclear Power Plant Press Release-III-22-010, NRC to Hold Public Meeting to Discuss 2021 Performance of Clinton and LaSalle Nuclear Power Plants2022-05-10010 May 2022 Press Release-III-22-010: NRC to Hold Public Meeting to Discuss 2021 Performance of Clinton and LaSalle Nuclear Power Plants Press Release-III-22-008, NRC to Hold Public Meeting to Discuss 2021 Performance of Fermi Nuclear Power Plant2022-05-0909 May 2022 Press Release-III-22-008: NRC to Hold Public Meeting to Discuss 2021 Performance of Fermi Nuclear Power Plant Press Release-II-22-015, NRC Schedules Public Meeting to Discuss V.C. Summer Nuclear Power Plant Performance2022-04-28028 April 2022 Press Release-II-22-015: NRC Schedules Public Meeting to Discuss V.C. Summer Nuclear Power Plant Performance Press Release-II-22-014, NRC Schedules Virtual Meeting to Discuss Performance of Framatome Facility2022-04-27027 April 2022 Press Release-II-22-014: NRC Schedules Virtual Meeting to Discuss Performance of Framatome Facility Press Release-II-22-013, NRC Schedules Virtual Meeting to Discuss 2021 Safety Performance of St. Lucie and Turkey Point Nuclear Power Plants& 8204;2022-04-26026 April 2022 Press Release-II-22-013: NRC Schedules Virtual Meeting to Discuss 2021 Safety Performance of St. Lucie and Turkey Point Nuclear Power Plants& 8204; Press Release-III-22-007, NRC to Hold Webinar to Discuss 2021 Performance for Monticello and Prairie Island Nuclear Generating Plants2022-04-26026 April 2022 Press Release-III-22-007: NRC to Hold Webinar to Discuss 2021 Performance for Monticello and Prairie Island Nuclear Generating Plants Press Release-II-22-012, NRC to Hold Virtual Meeting to Discuss Brunswick and Shearon Harris Nuclear Power Plant Performance2022-04-20020 April 2022 Press Release-II-22-012: NRC to Hold Virtual Meeting to Discuss Brunswick and Shearon Harris Nuclear Power Plant Performance ML22112A0192022-04-20020 April 2022 News Release-II-22-012: NRC to Hold Virtual Meeting to Discuss Brunswick and Shearon Harris Nuclear Power Plant Performance ML22112A0212022-04-19019 April 2022 News Release-III-22-005: NRC to Conduct Open House to Discuss 2021 Performance of Palisades Nuclear Plant Press Release-II-22-011, NRC Hosts Virtual Meeting to Discuss Safety Performance at Vogtle Nuclear Power Plant2022-04-14014 April 2022 Press Release-II-22-011: NRC Hosts Virtual Meeting to Discuss Safety Performance at Vogtle Nuclear Power Plant Press Release-II-22-010, NRC Schedules Virtual Meeting to Discuss Safety Performance of North Anna and Surry Nuclear Power Plants2022-04-13013 April 2022 Press Release-II-22-010: NRC Schedules Virtual Meeting to Discuss Safety Performance of North Anna and Surry Nuclear Power Plants ML22102A2932022-04-0707 April 2022 News Release-II-22-007: NRC Schedules Virtual Public Meeting to Discuss H.B. Robinson Nuclear Power Plant 2021 Safety Performance ML22102A2952022-04-0707 April 2022 News Release-II-22-009: NRC Schedules Virtual Meeting to Discuss Performance of Honeywell Facility ML22097A1292022-04-0505 April 2022 News Release-II-22-006: NRC Schedules Virtual Public Meeting to Discuss Three TVA Nuclear Power Plants 2021 Safety Performance ML22097A1282022-03-30030 March 2022 News Release-II-22-005: NRC to Hold Virtual Public Meeting to Discuss Farley and Hatch Nuclear Power Plant Safety Performance Press Release-II-22-004, NRC Begins Special Inspection at Urenco USA Facility2022-03-21021 March 2022 Press Release-II-22-004: NRC Begins Special Inspection at Urenco USA Facility 2023-04-03
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION 2443 Warrenville Road Lisle IL 60532 Web Site: http://www.nrc.gov E-mail: opa3@nrc.gov No. III-04-041 July 8, 2004 CONTACT: Jan Strasma (630) 829-9663 Viktoria Mitlyng (630) 829-9662 NRC TO MEET WITH DETROIT FIRM ON APPARENT TRANSPORTATION AND STORAGE VIOLATIONS The Nuclear Regulatory Commission staff will meet on Friday, July 16, with representatives of Imaging Subsurface, Inc., Detroit, Michigan, to discuss three apparent violations of NRC requirements for the safe transportation and storage of gauges containing sealed radiation sources.
The meeting, called a predecisional enforcement conference, will be held at 9 a.m. CDT at the NRC Region III Office, 2443 Warrenville Road, Lisle, Illinois. The meeting is open to public observation, and NRC officials will be available before the conclusion of the meeting to respond to questions and comments from the public.
Imaging Subsurface uses nuclear gauges containing sealed radiation sources to test soil conditions at road and other construction sites.
An NRC inspection in April found three apparent violations: failing to adequately secure a gauge while it was being transported by truck, failing to have required shipping documents readily available while the gauge was being transported, and failing to lock a second gauge or its container while in storage. None of the apparent violations resulted in the loss of a gauge or a direct safety hazard. The company took steps to correct the violations before the NRC inspection was completed.
These apparent violations are similar to those identified in a 2003 inspection, said Marc Dapas, Director of the Region III Division of Nuclear Materials Safety. They are of concern to the NRC because they indicate ineffective management of the companys radiation safety program regarding proper and timely corrective actions for the violations found in the previous inspection.
The decision to hold a predecisional enforcement conference does not mean that a determination has been made that a violation has occurred or that enforcement action will be taken.
The purpose of the conference is to discuss apparent violations, their causes and safety significance; to provide the licensee an opportunity to point out any errors that may have been made in the NRC inspection report; and to enable the company to outline its proposed corrective actions.
No decision on the apparent violations or any contemplated enforcement action, such as a fine, will be made at the conference.
If the NRC subsequently concludes that significant enforcement action is warranted, the NRC will post the action on the agencys enforcement web page:
http://www.nrc.gov/what-we-do/regulatory/enforcement/current.html.