Apr. 17, 2003 Page 1 of 1 MANUAL HARD COPY DISTRIBUTION DOCUMENT TRANSMITTAL 2003-19628 SER INFORMATION:

GER H*R S EMPL#:28401 CA#: 0363 Address: NUCSAt Phone# 2 3 TRANSMITTAL INFORMATION:

TO: GCnnSOCHRZSE M 04/17/2003 LOCATION: DOCUMENT CONTROL DESK "ROM: NUCLEAR RECORDS DOCUMENT CONTROL CENTER ANUCSA-2)

"-'THE FOLLOWING CHANGES HAVE OCCURRED TO THE HARDCOPY OR ELECTRONIC MANUAL ASSIGNED TO YOU:

126 - 126 - CONTROL ROOM (CR) COMMUNICATOR REMOVE MANUAL TABLE OF CONTENTS DATE: 02/26/2003 ADD MANUAL TABLE OF CONTENTS DATE: 04/16/2003 CATEGORY: PROCEDURES TYPE: EP ID: EP-PS-126 REMOVE: REV:17 ADD: REV: 18 Remove All Forms in REMOVE: PCAF 2002-1441 REV: N/A Tab C UPDATES FOR HARD COPY MANUALS WILL BE DISTRIBUTED WITHIN 5 DAYS IN ACCORDANCE WITH DEPARTMENT PROCEDURES. PLEASE MAKE ALL CHANGES AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX UPON RECEIPT OF HARD COPY. FOR ELECTRONIC MANUAL USERS, ELECTRONICALLY REVIEW THE APPROPRIATE DOCUMENTS AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX.

,W

PROCEDURE COVER SHEET PPL SUSQUEHANNA, LLC NUCLEAR DEPARTMENT PROCEDURE EMERGENCY PLAN COMMUNICATOR: EP-PS-1 26 I Emergency-Plan-Position-Specific Instruction Revision 18 Page 1 of 3 QUALITY CLASSIFICATION: APPROVAL CLASSIFICATION:

( ) QA Program (X) Non-QA Program ( ) Plant/' ' t, ) Non-Plant

( X) Instruction t EFFECTIVE DATE: A, PERIODIC REVIEW FREQUENCY: - 2 Years PERIODIC REVIEWIDUE DATE: Qi0i 54ir RECOMMENDED REVIEWS: aJ All

(  ! ,4 Procedure Owner Nuclear Emergency Planning Responsible Supervisor: Primary Operations Coordinator Responsible FUM: Supv.-Nuclear Emergency Planning Responsible Approver: Primary TSC Emergency Director FORM NDAP-QA-0002-1, Rev. 3, Page 1 of 1

EP-PS-1 26 Revision 18 Page 2 of 3 EMERGENCY PLAN COMMUNICATOR: Emergency Plan-Position Specific Procedure WHEN: Emergency plan is activated HOW NOTIFIED: Assigned while on duty REPORT TO: Shift Supervisor/ED WHERE TO REPORT: Control Room OVERALL DUTY:

Communicate information on emergency to specified personnel, agencies, and organizations, until the Technical Support Center (TSC) takes over communications.

MAJOR TASKS: TAB: REVISION:

Using the 'Control Room Communicator's TAB A 23 Flowchart," make initial notifications to off-site agencies and emergency personnel unless directed by the Shift Manager to implement Tab C.

Pass on information and documentation when TAB B 3 your communications job is finished, due to shift turnover, transfer of control to the TSC, or termination.

Perform Security Threat or Event TAB F 1 communications as directed by Emergency Director Perform additional notifications for Unusual TAB G 0 Event if NERO is not activated.

EP-PS-126 Revision 18 Page 3 of 3 SUPPORTING INFORMATION: TAB:

Emergency Telephone Instructions TAB 1 Emergency Organization TAB 2 Logkeeping TAB 3 Communication Information TAB 4 Emergency Forms TAB 5

  • Emergency Notification Report
  • Emergency Notification Logsheet Brief Non-Technical Descriptions of EAL TAB 6 Emergency Classification TAB 7

REFERENCES:

NUREG-0654, Planning Standards and Evaluation Criteria NUREG-0696, Functional Criteria for Emergency Response Facilities NUREG-0731, Guidelines for Utility Management Structure and Technical Resources, September 1980 SSES Emergency Plan NDAP-00-0316, Station Communications NDAP-QA-0300, Conduct of Operations OP-AD-003, Shift Routine - Log taking Letter dated February 25, 2002, from Samuel J. Collins, Director, Office of Nuclear Reactor Regulations, to Robert G. Byram, Senior Vice President and Chief Nuclear Officer.

TAB F EP-PS-1 26-F Revision 1 Page 1 of 2 MAJOR TASK:

Perform Site Specific Security Threat or Event emergency communications as directed by the Emergency Director.

SPECIFIC TASKS: HOW:

1. Commence logging communication 1a. Use Tab 5 Log Sheet actions.
2. Transmit Emergency Notification 2a. Dial 191 conference bridge on Report for EAL and Site Evacuation. CTN extension OR Use Tab 4 backup phone numbers.

2b.

Contact:

(1) Pennsylvania EMA (2) Columbia County EMA (3) Luzeme County EMA

3. If directed by the Emergency 3a. For evacuation, Ensure 'Page Director. Merge" button is depressed and Make a page announcement twice:

"Attention All Personnel: A security emergency has been declared. All non-essential personnel evacuate the site. All NERO responders report to the Emergency Operations Facility."

4. When a site accountability is ordered 4a. Ensure the "Page Merge" button is by the Emergency Director. depressed.

TAB F EP-PS-1 26-F Revision 1 Page 2 of 2 SPECIFIC TASKS" HOW:

4b. Go to Panel 0C695:

(1) Turn siren tone generator switch to 'pulsed."

(2) Pull out evacuation alarm switch.

(3) Turn evacuation alarm switch to

.plant alarm."

(4) Push in evacuation alarm switch.

(5) Wait 30 seconds.

(6) Pull out evacuation alarm switch.

(7) Turn evacuation alarm switch to

.off."

(8) Push in evacuation alarm switch.

4c. Make a page announcement twice:

Attention All Personnel: A site accountability is ordered. All personnel report to the nearest accountability area."

5. When Tasks 3 and 4 are completed. 5a. Enter Communication Flowchart step C3.

TAB G EP-PS-1 26-G Revision 0 Page 1 of 1 MAJOR TASK:

Perform additional notifications for an Unusual Event if NERO is not activated.

SPECIFIC TASKS: HOW:

1. When directed by the Shift Manager, 1a. Contact the ASCC and request Security Perform Key Manager Notification. to initiate Key Manager Notifications.
2. Within two hours of declaration, 2a. Transmit the Emergency Classification to Perform additional notifications. offsite agencies:

Institute of Nuclear Power (INPO)

Pennsylvania Rural Electric Cooperative American Nuclear Insurers (ANI)

PPL Insurance Group NOTE:

Phone Numbers are on the Control Room Communications Flowchart.

( (

Tab 2 EP-PS-1 26-2 EMERGENCY ORGANIZATION CONTROL ROOM EMERGENCY DIRECTOR (SHIFT MANAGER)

I 'lI EMERGENCY PLAN SHIFT TECHNICAL OPERATORS COMMUNICATOR ADVISOR (STA)

EP-AD-000-406, Revision 15, Page 1 of 3

( (C (

Tab 2 EP-PS-1 26-2 TSC ORGANIZATION

  • EMERGENCY I

DIRECTOR

. I I I

  • Operations Admin *Security *Rad Prot Coordinator Coordinator Coordinator Coordinator

. . I I I I HPN

  • TSC*Severe Accident *Damage Communicator Shift Manager Communicators Management Control Team C m coCoordinator Coord.

TSC Dose Calculator l Maintl&

Coordinators -H *HP Specialist

  • TSC Radio *Tech Support Communicator Coordinator -f;4an
  • Denotes minimum staffing. r *Chemistry MHP os I *OSC Coordinator I Coordinator Rev. 41, 03/03 Lead Tech l Support Engineer Susquehanna Steam Electric Station Units 1 and 2 Emergency Plan TSC ORGANIZATION *Tech Support Engineers FIGURE 6 2 EP-AD-000-406, Revision 15, Page 2 of 3

( (h (

Tab 2 EP-PS-1 26-2 EOF ORGANIZATION I I I I ENGINEER. DOSE LIAISON SUPPORT ASSESSMENT SUPPORT *EOF SUPPORT SUPERVISOR SUPERVISOR SUPERVISOR SUPERVISOR l NUCLEAR DOSE COUNTY I FUELS ASSESSMENT LIAISONS COMMUt ENGINEER STAFFER(S)

IELECTRICAL I TEA M NEP I SUPPORT DIRECDTORM ENGINEERDIETRP

  • MECHANICAL SUPPORT ADAD ENGINEER MONITORINGASS
  • SYSTEMS LEAD ENVIRONMENTAL SC ENGINEER SAMPLING TEAM SC

EP-AD-000-406, Revision 15, Page 3 of 3

Tab 4 EP-PS-126-4 EMERGENCY PLAN COMMUNICATOR GENERAL INFORMATION ACRONYM TABLE ASCC Alternate Security Control Center MOC Media Operations Center CCEMA Columbia County Emergency NERO Nuclear Emergency Response Management Agency Organization CTN Centrex Telephone Network NRC Nuclear Regulatory Commission DEPIBRP Department of Env. Protection! PEMA Pennsylvania Emergency Bureau of Radiation Protection Management Agency ENS Emergency Notification System PIM Public Information Manager EOF Emergency Operations Facility SCC Security Control Center ETN Electronic Tandem Network TPD Transmission Power Dispatcher LCEMA Luzerne County Emergency TSC Technical Support Center Management Agency I.-

TELEPHONE INFORMATION

1. Alternate Security Control Center (ASCC) Dial 8-254-4918 (primary)

Dial 8-254-3115 (backup)

2. Offsite Agencies (PEMA, LCEMA, CCEMA, Within 15 minutes, use extension 4915 and dial and the MOC Communicator) "191" to access the conference line. Transmit the Emergency Notification Report.

NOTE: If the conference capability is not available, use the following back-up phone numbers:

BACKUP TELEPHONE NUMBERS If calling from a 4xxx extension, dial the backup numbers as follows:

PEMA: 4960, 4961 or 8-1-717-651-2148 LCEMA: 4906, 4907, or 8-1-800-821-3715 CCEMA: 4955,4956, or 8-1-570-389-5720 EP-AD-000-328, Revision 13, Page 1 of 2 -

Tab 4 EP-PS-1 26-4 EMERGENCY PLAN COMMUNICATOR TELEPHONE INFORMATION If calling from a 3xxx extension, dial the backup numbers as follows:

PEMA: 8-353-4960, 8-353-4961, or 8-1-717-651-2148 LCEMA: 8-353-4906, 8-353-4907, or 8-1-800-821-3715 CCEMA: 8-353-4955, 8-353-4956, or 8-1-570-389-5734

3. Transmission Power Dispatcher Use the TPD Hotline OR Dial 8-1-484-634-4090 Give the classification.
4. NRC Use the ENS telephone OR 1-301-816-5100 1-301-951-0550 (backup)

EP-AD-000-328, Revision 13, Page 2 of 2