Revised Notice of Public Meeting (Regulatory Conference) with American Electric Power Co to Discuss Preliminary Yellow Finding Involving Essential Service Water Debris Intrusion Event That Occurred at D. C. Cook Plant on 08/29/2001ML021910519 |
Person / Time |
---|
Site: |
Cook |
---|
Issue date: |
07/10/2002 |
---|
From: |
Passehl D NRC/RGN-III/DRP/RPB6 |
---|
To: |
|
---|
References |
---|
EA-01-286 |
Download: ML021910519 (2) |
|
Similar Documents at Cook |
---|
Category:Inspection Report
MONTHYEARIR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 IR 05000315/20224202022-10-19019 October 2022 Cover Letter - Donald C. Cook Nuclear Plant Units 1 and 2 - Security Baseline Inspection Report 05000315/2022420 and 05000316/2022420 IR 05000315/20224012022-09-21021 September 2022 Security Baseline Inspection Report 05000315 2022401 05000316 2022401 Independent Spent Fuel Storage Security Inspection Report 07200072 2022401 IR 05000315/20223012022-08-31031 August 2022 NRC Initial License Examination Report 05000315/2022301; 05000316/2022301 IR 05000315/20220052022-08-24024 August 2022 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022005 and 05000316/2022005) IR 05000315/20220022022-08-0808 August 2022 Integrated Inspection Report 05000315/2022002 and 05000316/2022002 IR 05000315/20224022022-07-0505 July 2022 Material Control and Accounting Program Inspection Report 05000315/2022402 and 05000316/2022402 ML22165A2012022-06-14014 June 2022 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2022001 and 05000316/2022001 IR 05000315/20220012022-05-10010 May 2022 Integrated Inspection Report 05000315/2022001 and 05000316/2022001 ML22129A2052022-05-10010 May 2022 Integrated Inspection Report 05000315/2022001 and 05000316/2022001 IR 05000315/20220102022-04-0505 April 2022 Triennial Fire Protection Inspection Report 05000315/2022010 and 05000316/2022010 ML22084A5812022-03-25025 March 2022 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000315/2022011 05000316/2022011 IR 05000315/20210062022-03-0202 March 2022 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021006 and 05000316/2021006) IR 05000315/20210042022-02-0707 February 2022 Integrated Inspection Report 05000315/2021004 and 05000316/2021004 and Exercise of Enforcement Discretion IR 05000315/20210132021-12-0606 December 2021 Inspection Report 05000315/2021013 and 05000316/2021013 IR 05000315/20214032021-11-17017 November 2021 Security Baseline Inspection Report 05000315/2021403 and 05000316/2021403 IR 05000315/20210112021-11-15015 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000315/2021011 and 05000316/2021011 IR 05000315/20210032021-10-26026 October 2021 Integrated Inspection Report 05000315/2021003; 05000316/2021003; and 07200072/2021001 IR 05000315/20214012021-10-21021 October 2021 Cyber Security Inspection Report 05000315/2021401 and 05000316/2021401 IR 05000315/20215012021-10-0606 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2021501 and 05000316/2021501 IR 05000315/20210102021-09-0707 September 2021 Biennial Problem Identification and Resolution Inspection Report 05000315/2021010 and 05000316/2021010 IR 05000315/20210052021-09-0101 September 2021 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021005 and 05000316/2021005) IR 05000315/20210122021-08-0202 August 2021 Donald Cook Nuclear Plant - NRC Inspection Report 05000315/2021012 and 05000316/2021012 IR 05000315/20210022021-07-22022 July 2021 Integrated Inspection Report 05000315/2021002 and 05000316/2021002 ML21158A1732021-06-0909 June 2021 Review of the Fall 2017 Steam Generator Tube Inspections Report IR 05000315/20214022021-06-0909 June 2021 Donald D. C. Cook Nuclear Plant - Security Baseline Inspection Report 05000315/2021402 and 05000316/2021402 IR 05000315/20210012021-04-28028 April 2021 Integrated Inspection Report 05000315/2021001 and 05000316/2021001 IR 05000315/20200062021-03-0404 March 2021 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020006 and 05000316/2020006) IR 05000315/20200042021-02-0808 February 2021 Integrated Inspection Report 05000315/2020004 and 05000316/2020004 IR 05000315/20204032020-12-16016 December 2020 Security Baseline Inspection Report 05000315/2020403 and 05000316/2020403 IR 05000315/20204022020-11-0404 November 2020 Security Baseline Inspection Report 05000315/2020402 and 05000316/2020402 IR 05000315/20200032020-10-28028 October 2020 Integrated Inspection Report 05000315/2020003 and 05000316/2020003 IR 05000315/20203012020-10-19019 October 2020 NRC Initial License Examination Report 05000315/2020301; 05000316/2020301 IR 05000315/20200112020-09-17017 September 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 IR 05000315/20200052020-09-0101 September 2020 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020005 and 05000316/2020005) IR 05000315/20200022020-08-10010 August 2020 Integrated Inspection Report 05000315/2020002 and 05000316/2020002 2024-01-31
[Table view] Category:Meeting Notice
MONTHYEARPMNS20231429, Meeting in Support of License Amendment Review Regarding Neutron Flux Channels2023-12-27027 December 2023 Meeting in Support of License Amendment Review Regarding Neutron Flux Channels PMNS20230842, Pre-Application Meeting Regarding Potential License Amendment Request Related to Operating Power Sources for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 22023-07-28028 July 2023 Pre-Application Meeting Regarding Potential License Amendment Request Related to Operating Power Sources for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23159A1432023-06-13013 June 2023 Notice of Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Donald C. Cook Nuclear Plant for Performance for 2022 Calendar Year PMNS20221232, Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 22022-11-29029 November 2022 Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 PMNS20221117, Pre-Application Meeting Regarding Neutron Flux Channels2022-11-0303 November 2022 Pre-Application Meeting Regarding Neutron Flux Channels ML22132A2562022-05-16016 May 2022 Notice of Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Donald C. Cook Nuclear Power Plant for Performance for 2021 Calendar Year PMNS20211596, Pre-Application Meeting Regarding Regarding Final Response to Generic Letter 2004-02 for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 22022-01-0707 January 2022 Pre-Application Meeting Regarding Regarding Final Response to Generic Letter 2004-02 for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 PMNS20211496, Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Quality Assurance Program for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 22021-11-22022 November 2021 Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Quality Assurance Program for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 PMNS20211167, Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Licensing Basis of Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 to Support Increased Damping Levels for Seismic Analysis of Piping2021-09-0808 September 2021 Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Licensing Basis of Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 to Support Increased Damping Levels for Seismic Analysis of Piping PMNS20210907, Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 22021-07-15015 July 2021 Pre-Application Meeting Regarding Potential License Amendment Request Related to Revising the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21154A1122021-06-0202 June 2021 Notice of Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 for Performance for 2020 Calendar Year PMNS20210248, Pre-Application Meeting Regarding Containment Water Level Channels2021-03-18018 March 2021 Pre-Application Meeting Regarding Containment Water Level Channels PMNS20201331, Pre-Application Meeting Regarding Type a Test Interval Extension2020-11-17017 November 2020 Pre-Application Meeting Regarding Type a Test Interval Extension PMNS20201176, Pre-Application Meeting Regarding Potential N-729 Relief Request2020-10-0101 October 2020 Pre-Application Meeting Regarding Potential N-729 Relief Request ML20189A4242020-07-0707 July 2020 7/21/2020 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of Donald C. Cook Nuclear Plant Performance for the 2019 Calendar Year ML19183A1202019-07-0202 July 2019 7/23/2019 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Donald C. Cook Nuclear Power Plant Performance for the 2018 Calendar Year ML18169A1262018-06-15015 June 2018 8/21/2018 Notice of Significant Public Meeting to Discuss Nrc'S End-Of-Cycle Assessment of the Donald C. Cook Nuclear Power Plant, Units 1 and 2 Performance for the 2017 Calendar Year ML17257A3762017-09-14014 September 2017 Public Meeting Notice of NRC Region III 2017 Operator Licensing Workshop ML17181A2352017-06-30030 June 2017 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Donald C. Cook Power Plant Performance for the 2016 Calendar Year ML16216A3502016-08-0303 August 2016 Notice of Meeting to Discuss 2015 End-of-Cycle Performance Assessment at Donald C. Cook Nuclear Power Plant ML16216A3752016-08-0303 August 2016 8/22/2016 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Donald C. Cook Nuclear Power Plant Performance for the 2015 Calendar Year ML15231A8022015-08-19019 August 2015 August 31, 2015, Notice of Meeting for D.C. Cook 2014 End-of-Cycle ML15183A4842015-07-0101 July 2015 Ltr. 07/01/15 Davis-Besse U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4792015-07-0101 July 2015 Ltr. 07/01/15 D.C. Cook U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting)(Drm) ML15183A4782015-07-0101 July 2015 Ltr. 07/01/15 Duane Arnold U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4722015-07-0101 July 2015 Ltr. 07/01/2015 Fermi U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4632015-07-0101 July 2015 Ltr. 07/01/15 Monticello U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4452015-07-0101 July 2015 Ltr. 07/01/15 Perry U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A3862015-07-0101 July 2015 Ltr. 07/01/15 Prairie Island U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15182A4412015-07-0101 July 2015 Notice and Agenda - 2015 Operator Licensing Workshop ML14168A1022014-06-16016 June 2014 Notice of Meeting with Indiana Michigan Power Company to Present the Licensee the Results of NRC End-of-Cycle Assessment Regarding Donald C. Cook Nuclear Power Plant, Unit 1 and Unit 2 ML14168A1862014-06-13013 June 2014 07/9-10/2014 Meeting Notice with the Public - 2014 Operator Licensing Workshop ML14169A4862014-06-13013 June 2014 D. Ccook Operator License Workshop Invitation ML13161A3802013-06-12012 June 2013 Meeting Notice with Indiana Michigan Power Company (I&M) Concerning Donald C. Cook Nuclear Plant, Unit 1 ML13122A2162013-05-0202 May 2013 DC Cook Meeting Notice for EOC Public Meeting 5-30-2013 ML13122A2122013-05-0202 May 2013 DC Cook Open House to Discuss 2012 EOC Performance Assessment ML12138A3312012-05-17017 May 2012 05/31/2012, Notice of Significant Licensee Meeting (non-public) Regarding Operator Licensing Workshop and Meeting ML12137A4862012-05-15015 May 2012 Notice of Meeting with Indiana Michigan Power Company to Discuss NRC Activities, Nuclear Power Issues, and 2011 End-of-Cycle Performance Assessment for D.C. Cook Nuclear Power Plant, Units 1 and 2 ML12137A3972012-05-15015 May 2012 DC Cook Units 1 and 2 Public Meeting/Open House to Discuss NRC Activities, Nuclear Power Issues, and 2011 End-of-Cycle Performance Assessment ML12132A4432012-05-11011 May 2012 5/11/2012, Notice of Closed Meeting to Conduct a Closed Mediation Session as Part of the Nrc'S Post-Investigation Alternative Dispute Resolution Program Related to an Apparent Willful Violation of Fitness-for-Duty Requirements ML1113903342011-05-18018 May 2011 Notice of Meeting to Discuss NRC End-Of-Cycle Assessment of D.C. Cook Plant Performance for 2010 Calendar Year and the Agency'S Reactor Oversight Process with the Public ML1113903252011-05-18018 May 2011 Notice of Public Meeting/Open House to Discuss NRC Activities, Nuclear Power Issues, and 2010 End-Of-Cycle Performance Assessment for D.C. Cook Nuclear Power Plant ML11115A0012011-04-26026 April 2011 Notice of Forthcoming Meeting with Indiana Michigan Power Company to Discuss Pre-Application Issues Related to the Future Amendment to Transition to NFPA 805, Performance-Based Fire Protection ML1104000792011-02-0808 February 2011 Notice of Public Meeting with D. C. Cook to Provide Representatives with an Opportunity to Present Selected Topics in Advance of the Emergency Exercises ML1013301362010-05-12012 May 2010 Notice of Meeting to Discuss NRC End-of-Cycle Assessment of DC Cook Station Performance for the 2009 Calendar Year and the Agency'S Reactor Oversight Process with the Public ML0930200572009-10-26026 October 2009 Revised Notice of Significant Licensee Meeting with Indiana Michigan Power Company to Allow Licensee to Present Information on the 09/20/2008, Unit 1 Turbine Event to the Region III Staff and Discuss Unit 1 Recovery Efforts ML0928706922009-10-15015 October 2009 D.C. Cook Notice of Significant Licensee Meeting - Presentation of Unit 1 Turbine Event ML0912709852009-05-0606 May 2009 Public Meeting/Open House to Review 2008 End-Cycle Performance Assessment for D.C. Cook Nuclear Power Plants ML0912709932009-05-0606 May 2009 Notice of Meeting Notice to Discuss NRC End-of-Cycle Assessment of D.C. Cook Station Performance for the 2008 Calendar Year and the Agency'S Reactor Oversight Process with the Public ML0808602542008-03-26026 March 2008 Notice of Meeting with Indiana Michigan Power Company to Present the Licensee the Results of NRC End-of-Cycle Assessment 2023-07-28
[Table view] |
Text
July 10, 2002 NOTICE OF SIGNIFICANT LICENSEE MEETING THIS MEETING IS OPEN TO PUBLIC ATTENDANCE (Updated to Include Video Conference Location)
EA-01-286 Name of Licensee: American Electric Power Company Name of Facility: D. C. Cook Nuclear Power Station Docket No: 50-315; 50-316 Date and Time of Meeting: July 25, 2002 at 9:00 a.m. (CDT)
Location of Meeting: U. S. Nuclear Regulatory Commission Region III 801 Warrenville Road, Suite 255 Lisle, IL 60532-4351 Video Conference Location: U. S. Nuclear Regulatory Commission NRC One White Flint North 11555 Rockville Pike Room O-3 B4 Rockville, MD Purpose of Meeting: Regulatory Conference to discuss a preliminary Yellow finding involving the essential service water debris intrusion event that occurred at the D. C. Cook Nuclear Power Plant on August 29, 2001. A Yellow finding is described as having substantial safety significance. The ADAMS accession number of the associated inspection report is ML021610713.
CATEGORY 1: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
NRC Attendees:
J. Dyer, Regional Administrator G. Grant, Director, Division of Reactor Projects D. Passehl, Acting Chief, Branch 6, Division of Reactor Projects B. Kemker, Senior Resident Inspector, D. C. Cook Others as designated Licensee Attendees:
A. Bakken III, Senior Vice President, Nuclear Generation Group J. Pollock, Site Vice President Others as designated
Notice of Significant Licensee Meeting NOTE: Attendance at this meeting by NRC personnel at Region III, other than those listed above, should be made known to me by telephone at 630-829-9872 or e-mail at dxp@nrc.gov by COB July 19, 2002. Attendance at this meeting by NRC personnel at One White Flint North, should be made known to Mr. John Stang, Jr. at 301-415-1345 or e-mail at jfs2@nrc.gov by COB July 19, 2002.
Approved by: /RA by Steven Orth Acting for/
David G. Passehl, Acting Chief Branch 6 Division of Reactor Project DOCUMENT NAME:C:\ORPCheckout\FileNET\ML021910519.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII C RIII RIII RIII NAME SOrth HClayton DPassehl DATE 7/10/02 7/10/02 7/10/02
Notice of Significant Licensee Meeting Distribution:
B. W. Sheron, Associate Director for Projects Licensing and Technical Review, NRR J. Zwolinski, Director, Division of Licensing and Project Management, NRR G. Tracy, Chief, Division of Inspection Program Management, IOLB, NRR H. Nieh, Region III Coordinator, OEDO S. Bajwa, Project Directorate, Division of Licensing and Project Management, NRR J. Stang, Project Manager, Project Directorate, Division of Licensing and Project Management, NRR F. Congel, Director, Office of Enforcement D. Dambly, Assistant General Counsel for Materials and Enforcement, OGC G. E. Grant, Director, Division of Reactor Projects, RIII S. A. Reynolds, Deputy Director, Division of Reactor Projects, RIII J. A. Grobe, Director, Division of Reactor Safety, RIII R. J. Caniano, Deputy Director, Division of Reactor Safety, RIII H. B. Clayton, Team Leader, Enforcement / Investigation Staff, RIII D. Passehl, Acting Branch Chief, Branch 6, RIII B. Kemker, SRI, D. C. Cook DRS Branch Chiefs (RNG, DEH, JMJ3, KXR)
R. M. Lickus, Regional State Liaison Officer, RIII PMNS RIII Public Affairs (RJS2, VTM)
J. Kweiser, ORA P. Buckley, ORA OEMAIL (E-Mail)