IR 05000315/2020003
| ML20302A422 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 10/28/2020 |
| From: | Nestor Feliz-Adorno Reactor Projects Region 3 Branch 4 |
| To: | Gebbie J Indiana Michigan Power Co |
| References | |
| IR 2020003 | |
| Download: ML20302A422 (13) | |
Text
October 28, 2020
SUBJECT:
DONALD C. COOK NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000315/2020003 AND 05000316/2020003
Dear Mr. Gebbie:
On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Donald C. Cook Nuclear Plant. On October 8, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Néstor J. Féliz Adorno, Chief Branch 4 Division of Reactor Projects
Docket Nos. 05000315 and 05000316 License Nos. DPR-58 and DPR-74
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000315 and 05000316
License Numbers:
Report Numbers:
05000315/2020003 and 05000316/2020003
Enterprise Identifier: I-2020-003-0024
Licensee:
Indiana Michigan Power Company
Facility:
Donald C. Cook Nuclear Plant
Location:
Bridgman, Michigan
Inspection Dates:
July 01, 2020 to September 30, 2020
Inspectors:
J. Bozga, Senior Reactor Inspector
J. Mancuso, Resident Inspector
J. Neurauter, Senior Reactor Inspector
P. Zurawski, Senior Resident Inspector
Approved By:
Néstor J. Féliz Adorno, Chief
Branch 4
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at the Donald C. Cook Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 and Unit 2 began the inspection period at rated thermal power. On September 16, 2020, Unit 1 was shutdown for a scheduled refueling outage and remained shutdown through the end of the inspection period. Unit 2 had an unplanned shutdown on September 4, 2020, due to a failed pressurizer relief valve. After correction of the issue, the unit was returned to rated thermal power on September 9, 2020, where it remained for the rest of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities, and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated readiness for seasonal extreme weather (summer hot temperature conditions) for the following systems, July 2 through July 9, 2020:
Impending Severe Weather Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems below from impending severe weather [Midwest Derecho High Winds] on August 10, 2020:
- Circulating Water
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1 CD EDG with Unit 1 AB EDG inoperable on July 7, 2020
- (2) Unit 2 AB EDG with Unit 2 CD EDG inoperable on July 27, 2020
- (3) Unit 2 control room instrument distribution alternate power source with main power source inoperable on July 28, 2020
- (4) Unit 1 west charging pump with Unit 1 east charging pump inoperable on July 30, 2020
- (5) Unit 2 west motor-driven auxiliary feedwater pump (MDAFWP) with Unit 2 east MDAFWP inoperable for maintenance on August 5, 2020
- (6) Unit 1 component cooling water (CCW) heat exchanger on September 24, 2020
71111.07A - Heat Sink Performance
Annual Review (IP Section 03.01) (1 Sample)
The inspectors evaluated readiness and performance of:
- (1) Unit 1 east and west CCW heat exchanger inspection on August 17, 2020
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (3 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:
- (1) Reserve auxiliary transformer maintenance the week of July 6, 2020 (2)2AB EDG maintenance the week of July 20, 2020 (3)2CD EDG maintenance the week of July 27, 2020
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Scheduled Unit 1 work (reserve auxiliary transformer and EDG) for the week of July 6, 2020 (2)2AB EDG due to room ventilation supply fan and day tank enclosure fan motor fire on July 13, 2020
- (3) Scheduled Unit 2 work (2CD EDG, emergency service water, safety injection pump)for the week of July 27, 2020
- (4) Maintenance Rule (a)(1) - Unit 2 non-essential service water (NESW) System on July 21, 2020
- (5) Maintenance Rule (a)(1) - Unit 2 Nuclear Instrument NI-01 on July 24, 2020
- (6) Unit 1 east essential service water (ESW) backwash air fitting - unplanned limiting condition for operation on August 7, 2020
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Action Request (AR) 2020-5522 & 5534; Increase of leaks on 1AB EDG jacket water and 1-HE-47-ABS EDG aftercooler leaking from two bolts on July 13, 2020
- (2) AR 2020-5502; Unverified assumption - calculation 2-E-N-ELCP-120-002 on July 13, 2020
- (4) AR 2020-6007; Thru wall leak at equalizing line on Unit 1 East centrifugal charging pump on August 1, 2020
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Engineering Change 0000057627; Replace 2-HV-DGX-3 Motor on July 27, 2020
- (2) Unit 1 ESW temporary configuration change for broken airline on August 7, 2020
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:
(1)2-IMO-312; Unit 2 residual heat removal (RHR) heat exchanger on July 1, 2020
- (2) Unit 1 CO2 fire suppression system following maintenance on July 1, 2020 (3)1-HV-CLV-1A; Unit 1 lower containment vent unit on July 2, 2020
- (4) Unit 2 west containment spray system test on July 20, 2020 (5)2-OHP-4040-208-051N; Unit 2 north safety injection (SI) pump surveillance on July 31, 2020
- (6) Unit 2 CD EDG after maintenance on August 3, 2020
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Sample 1 Partial)
- (1) The inspectors evaluated activities during a forced outage for Unit 2 due to a failed pressurizer spray valve from September 4 to September 7, 2020.
(2)
(Partial)
The inspectors evaluated Unit 1 Refueling Outage activities from September 15 to September 30, 2020. The refueling outage remained ongoing as of the end of the inspection period.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
(1)2CD EDG operability surveillance on July 27, 2020
- (2) Unit 1 north SI pump on July 29, 2020
- (4) Unit 1 Train B reactor protection system and engineered safety feature reactor trip breaker and solid-state protection system automatic trip and logics test on August 17, 2020
Inservice Testing (IP Section 03.01) (1 Sample)
- (1) Unit 2 west containment spray system test on July 20, 2020
71114.06 - Drill Evaluation
Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)
The inspectors evaluated:
- (1) An emergency planning drill on August 25,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===
- (1) Unit 1 (January 1, 2019 through December 31, 2019)
- (2) Unit 2 (January 1, 2019 through December 31, 2019)
IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)
- (1) Unit 1 (January 1, 2019 through December 31, 2019)
- (2) Unit 2 (January 1, 2019 through December 31, 2019)
IE04: Unplanned Scrams with Complications Sample (IP Section 02.03) (2 Samples)
- (1) Unit 1 (January 1, 2019 through December 31, 2019)
- (2) Unit 2 (January 1, 2019 through December 31, 2019)
MS05: Safety System Functional Failures Sample (IP Section 02.04) (2 Samples)
- (1) Unit 1 (January 1, 2019 through December 31, 2019)
- (2) Unit 2 (January 1, 2019 through December 31, 2019)
MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)
- (1) Unit 1 (July 1, 2019 through June 30, 2020)
- (2) Unit 2 (July 1, 2019 through June 30, 2020)
MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)
- (1) Unit 1 (July 1, 2019 through June 30, 2020)
- (2) Unit 2 (July 1, 2019 through June 30, 2020)
MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)
- (1) Unit 1 (July 1, 2019 through June 30, 2020)
- (2) Unit 2 (July 1, 2019 through June 30, 2020)
71152 - Problem Identification and Resolution
Annual Follow-Up of Selected Issues (IP Section 02.03) (2 Samples 1 Partial)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
(1)
(Partial)
AR 2020-4198; Design Basis Non-Conformance of Containment Penetrations CPN-16 & 47 (RHR Normal Cooldown Flow Path, Supply & Return) on July 1, 2020
- (2) AR 2020-5344; Unexpected Control Rod Motion (Unit 1) - Power Range N-32 Spiked High on July 6, 2020
- (3) AR 2020-6007; Thru-Wall Leak at Equalizing Line on Unit 1 East Centrifugal Charging Pump on August 1,
INSPECTION RESULTS
Observation: Active Leak at Unit 1 East Charging Pump (1-PP-50E) Discharge Side Flange Equalization Line 71152 The inspectors performed a detailed review of AR 2020-6007; "Leak at Equalizing Line of U1 E CCP. For the Problem Identification and Resolution Annual Sample, the inspectors focused on assessment of the licensee's corrective actions taken to date and those planned from this point forward. The licensee performed a repair to the leak at the equalization line for the Unit 1 East Charging Pump (1-PP-50E). The inspectors reviewed the work order associated with this repair as well as the post repair non-destructive examination information.
The inspectors concluded that the licensee's actions taken in accordance with their corrective action program were reasonable given the overall safety significance of the issue. Based on the inspector's review, no concerns were identified.
Observation: Unexpected Control Rod Motion 71152 The inspectors performed a detailed review of AR 2020-6603, U-1 control rod stepped in one-half step and AR-2020-5344, "Unexpected Control Rod Motion in Unit 1." On July 3, 2020, AR 2020-5344 identified unexpected control rod motion in Unit 1 by control bank D unexpectedly moving inward 0.5 steps. Immediate operational action was taken, and the appropriate procedures were entered. Operators noted a temperature error from a power mismatch (momentary spike) had occurred which appeared to originate from nuclear instrumentation N-42. On August 24, 2020, AR 2020-6603 identified a similar occurrence of an unexpected one-half step on the control rods with an associated spike on nuclear instrumentation N-42. For this Problem Identification and Resolution Annual Sample, the inspectors focused on assessment of the licensee's corrective actions taken to date and those planned from this point forward. The licensee evaluated the occurrences, determined that power range indications were related to end of core life behavior and established end of core life procedural guidance. The inspectors concluded that the licensee's actions taken in accordance with their corrective action program were reasonable given the overall safety significance of the issue. Based on the inspector's review, no concerns were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 8, 2020, the inspectors presented the integrated inspection results to Mr. J. Gebbie, Senior Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Procedures
2-OHP-4022-
001-010
Severe Weather
PMP-5055-SWM-
001
Severe Weather Guidelines
Procedures
1-OHL-5030-
SOM-005
Unit 1 Tours - Unit 1 Auxiliary Tour
1-OHP-4021-003-
001
Letdown, Charging, and Seal Water Operations
1-OHP-4030-156-
017E
East Motor Driven Auxiliary Feedwater System Test
71111.07A Procedures
2-EHP-8913-
001-02
Heat Exchange Inspection
Work Orders
2-EHP-8913-
001-002
Unit 1 West Component Cooling Water Heat Exchanger
(1-HE-15W)
55509691-06
Unit 1 East Component Cooling Water Heat Exchanger
(1-HE-15E)
55510487-08
West Component Cooling Water Heat Exchanger
Procedures
2-OHP-4030-232-
27AB
AB Diesel Generator Operability Test (Train B)
2
2-OHP-4030-232-
27CD
CD Diesel Generator Operability Test (Train A)
Work Orders
55522389-01
CD Diesel Generator
55532220-01
Unit 1 Reserve Auxiliary Transformer TR101CD
Corrective Action
Documents
AR 2020-5542
2-HV-DGS-2 Found Not Running During EDG Surveillance
AR 2020-5542
2-HV-DGS-2 Found Not Running During EDG Surveillance
AR 2020-5545
AR 2020-5545
Engineering
Changes
2-HV-DGX-3 Motor Replacement
Miscellaneous
Cook Unit 1 & 2 Online Risk Cycle 115, Week 05
07/27/2020
Risk Profile for the Week of July 27, 2020
Risk Profile for the Week of July 7, 2020
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Cook Unit 1 & 2 Online Risk Cycle 115, Week 02
07/06/2020
Cook Nuclear Plant Key Maintenance and Testing Schedule
07/06/2020
Work Orders
55549208
Fire U2 AB Room
07/13/2020
55549287
AB EDG Room Vent Abnormal Vent Alarm Came in During
Extended EDG Run
07/14/2020
55550267
1-WRV-761 Unit 1 East ESW Strainer Outlet Valve
08/07/2020
Calculations
2-E-N-ELCP-120-
20VAC Control Room Instrumentation Distribution (CRID)
Loading and Voltage Drop Analysis - Unit 2
Corrective Action
Documents
AR 2020-5502
Track Unverified Assumption - Calculation 2-E-N-ELCP-120-
2
AR 2020-5522
Increase of Leaks on 1AB EDG Jacket Water
AR 2020-5860
Dirty EDG Sub-Panel Air Supply Screens
AR 2020-6007
Thru Wall Leak at Equalizing Line on Unit 1 East Centrifugal
Charging Pump
AR-2020-5534
1-HE-47-ABS EDG Aftercooler Leaking from Two Bolts
Engineering
Changes
0000055545-TP-
2
Unit 2 Control Room Instrumentation Diagram Steady State
Circuit Current Recording
Miscellaneous
DIT-B-00197-09
Design Information Transmittal - Area Temperature and
Relative Humidity for Selected Plant Areas Outside
Containment
2/16/2000
Engineering
Changes
Replace 2-HV-DGX-3 Motor
07/22/2020
Procedures
2-MHP-5021-
2-146
Emergency Diesel Generator System Mechanical
Maintenance
2-OHP-4030-208-
053A
HE-17E Outlet Flow Control Valve 2-IRV-310 Stroke Test -
RHR in Service
2-OHP-4030-209-
007W
West Containment Spray System Test
Work Orders
55530794-02
East RHR Heat Exchanger 2-IMO-312
55535313-21
1-HV-CLV-1A-MTR, Containment Lower Compartment Quad
- 1 Vent Unit Exhaust Fan HV-CLV-1A Motor
06/30/2020
Procedures
1-IHP-4030-001B
Train 'B' Solid State Protection System (SSPS) Automatic Trip and Actuation Logic Operational Test (TADOT,
Actuation Logic Test and Master Relay Test) and Reactor
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Trip Breaker Operational Test (TADOT)
2-OHP-4030-208-
051N
North Safety Injection Pump System Test
2-OHP-4030-209-
007W
West Containment Spray System Test
2-OHP-4030-232-
27D
2CD Diesel Generator Operability Test (Train A)
07/26/2020
PMP-2291-WMP-
001
PMP-2291-WMP-001
Work Orders
55543997-01
Unit 1 - Perform Procedure 1-IHP-4030-111-01B
08/12/2020
55546678-01
West Containment Spray System Test
07/20/2020
55546679-01
2-OHP-4030-208-051N; North Safety Injection Pump System
Test
07/28/2020
55549335-01
PMP-2291-WMP-001, 4kV Bus Loss of Voltage and 4kV Bus
Degraded Voltage Relay test
07/15/2020
Miscellaneous
August 25, 2020 Emergency Planning Drill Scenario
71151
Miscellaneous
Operational Narrative Logs (January 1, 2019 through
December 31, 2019)
Corrective Action
Documents
AR 2020-4198
AR 2020-4198; Design Basis Non-Conformance of
Containment Penetrations CPN-16 & 47
AR 2020-5344
Unexpected Control Rod Motion in Unit 1
AR 2020-6007
Leak at Equalizing Line of U1 E CCP
07/29/2020
AR 2020-6043
WOs Requested for 2 to 1 Fillet Welds on CCP Balance
Line
07/30/2020
AR 2020-6603
U1 Control Rods Stepped in One Half Step
Miscellaneous
20-5344 White
Paper
Reactor Engineering (Verteramo) White Paper (2020-5344)
Work Orders
55549905-01
1-PP-50E Repair Leak at Equalizing Line on U1 CCP
07/29/2020
55549905-02
1-PP-50E Perform Leak Inspection (PMT)
07/30/2020