ULNRC-04681, May 2002 Monthly Operating Report for Callaway Plant, Unit 1

From kanterella
(Redirected from ML021750152)
Jump to navigation Jump to search
May 2002 Monthly Operating Report for Callaway Plant, Unit 1
ML021750152
Person / Time
Site: Callaway Ameren icon.png
Issue date: 06/13/2002
From: Witt W
Union Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ULNRC-04681
Download: ML021750152 (4)


Text

Union Electric PO Box 620 Fulton, MO 65251 Callaway Plant June 13, 2002 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 ULNRC-04681 SAmeren UFGentlemen:

DOCKET NUMBER 50-483 UNION ELECTRIC CO.

CALLAWAY PLANT UNIT 1 FACILITY OPERATING LICENSE NPF-30 MONTHLY OPERATING REPORT MAY/2002 The enclosed Monthly Operating Report for May/2002 is submitted pursuant to Section 5.6.4 of the Callaway Unit 1 Technical Specifications.

Warren A. Witt Manager, Callaway Plant WAW/JER/slk Enclosure a subsidiary of Ameren Corporation

ULNRC04681 June 13, 2002 Page 2 cc: Mr. Ellis W. Merschoff Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Jack Donohew (2 copies)

Licensing Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 7El Washington, DC 20555-2738 Manager, Electric Department Missouri Public Service Commission PO Box 360 Jefferson City, MO 65102 Mr. Thomas A. Baxter Shaw, Pittman, Potts, & Trowbridge 2300 N. Street N.W.

Washington, DC 20037

Enclosure ULNRC04681 June 13, 2002 DOCKET NO.: 50-483 UNIT NAME: CALLAWAY UNIT I COMPLETED BY: J. E. Ready TELEPHONE: 573/676-8617 FAX: 573/676-4202 REPORTING PERIOD: May/2002

1. DESIGN ELECTRICAL RATING (MWe-Net): 1171
2. MAX. DEPEND. CAPACITY (MWe-Net): 1125 THIS MONTH YR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744 3,303 137,266 744 3,257 135,407
4. HOURS GENERATOR ON-LINE 0.0 0.0 0.0
5. REACTOR RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED (MWH) 823,474 3,678,063 148,835,581 6.

Page 1 of 2

Enclosure ULNRC04681 June 13, 2002 UNIT SHUTDOWNS DOCKET NO.: 50-483 UNIT NAME: CALLAWAY UNIT 1 COMPLETED BY: J. E. Ready TELEPHONE: 573/676-8617 FAX: 573/676-4202 REPORT May/2002 TYPE METHOD OF F: FORCED DURATION SHUTTING DOWN CORRECTIVE NO. DATE S: SCHEDULED (HOURS) REASON THE REACTOR ACTIONS/COMMENT.

SUMMARY

The Callaway Plant did not have a shutdown during the month of May REASON METHOD A: EQUIPMENT FAILURE (EXPLAIN) 1: MANUAL B: MAINT. OR TEST 2: MANUAL SCRAM C: REFUELING 3: AUTOMATIC SCRAM D: REGULATORY RESTRICTION 4. CONTINUATION E: OPERATOR TRAINING / LICENSE EXAMINATION 5: OTHER (EXPLAIN)

F: ADMINISTRATIVE G: OPERATIONAL ERROR (EXPLAIN)

H: OTHER (EXPLAIN)

Page 2 of 2