AmerenUE Callaway Plant PO Box 620 Fulton, MIO 65251 April 4, 2003 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 wameren UF ULNRC04833 Ladies & Gentlemen:
DOCKET NUMBER 50-483 UNION ELECTRIC CO.
CALLAWAY PLANT UNIT 1 FACILITY OPERATING LICENSE NPF-30 MONTHLY OPERATING REPORT MARCH/2003 The enclosed Monthly Operating Report for March/2003 is submitted pursuant to Section 5.6.4 of the Callaway Unit 1 Technical Specifications.
Warren A. Witt Manager, Callaway Plant WAW/JER/slk Enclosure 9; j t- )
a subsidiary ofAmeren Corporation
ULNRC04833 April 4, 2003 Page 2 cc: Mr. Ellis W. Merschoff Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Jack Donohew (2 copies)
Licensing Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 7E1 Washington, DC 20555-2738 Manager, Electric Department Missouri Public Service Commission PO Box 360 Jefferson City, MO 65102
Enclosure ULNRC04833 April 4, 2003 DOCKET NO.:
UNITNAME:
COMPLETED BY:
TELEPHONE:
FAX:
50-483 CALLAWAY UNIT I J. E. Ready 573/676-8617 573/676-4202 REPORTING PERIOD:
MARCH/2003
- 1.
DESIGN ELECTRICAL RATING (MWe-Net): 1171
- 2.
MAX. DEPEND. CAPACITY (MWe-Net): 1125 THIS MONTH YR TO DATE CUMULATIVE 3.
4.
5.
6.
NUMBER OF HOURS REACTOR WAS CRITICAL HOURS GENERATOR ON-LINE REACTOR RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED (MWH) 513 510 0.0 584,814 1,929 1,926 0.0 2,242,524 1 43,446 141,522 0.0 155,786,620 Page 1 of 2
Enclosure ULNRC04833 April 4, 2003 UNIT SHUTDOWNS DOCKET NO.:
UNIT NAME:
COMPLETED BY:
TELEPHONE:
FAX:
50-483 CALLAWAY UNIT 1 J. E. Ready 573/676-8617 573/676-4202 REPORT:MARCH/2003 TYPE F: FORCED NO.
DATE S: SCHEDULED 301 03-22-03 S
DURATION (HOURS) 234 METHOD OF SHUTTING DOWN REASON THE REACTOR B
1 CORRECTIVE ACTIONS!
COMMENTS
SUMMARY
The Callaway Plant was shut down on March 22, 2003 to replace a Pressurizer Safety Valve, that was experiencing leakage past the seat.
REASON A: EQUIPMENT FAILURE (EXPLAIN)
B: MAINT. OR TEST C: REFUELING D: REGULATORY RESTRICTION E: OPERATOR TRAINING / LICENSE EXAMINATION F: ADMINISTRATIVE G: OPERATIONAL ERROR (EXPLAIN)
H: OTHER (EXPLAIN)
METHOD 1: MANUAL 2: MANUAL SCRAM 3: AUTOMATIC SCRAM
- 4. CONTINUATION 5: OTHER (EXPLAIN)
Page 2 of 2