February 2005 Monthly Operating Report for Callaway Plant Unit 1
ML050890316
Person / Time
Site: Callaway Ameren icon.png
Issue date: 03/11/2005
From: Keith Young
AmerenUE, Union Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ULNRC05131
Download: ML050890316 (4)


Text

AmerenUE Callaway Plant P0 Box 620 Fulton, MIO 65251 March 11, 2005 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 ULNRC05131 Ladies & Gentlemen:

WAmeren UE DOCKET NUMBER 50-483 UNION ELECTRIC CO.

CALLAWAY PLANT UNIT 1 FACILITY OPERATING LICENSE NPF-30 MONTHLY OPERATING REPORT February 2005 The enclosed Monthly Operating Report for February 2005 is submitted pursuant to Section 5.6.4 of the Callaway Unit 1 Technical Specifications.

4ta OeJo~

Keith D. Young Manager, Regulatory Affairs KDY/JWH/slk Enclosure

9k1 a subsidiary oflAmeren Corporation

ULNRC05131 March 11, 2005 Page 2 cc: Mr. Bruce S. Mallett Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Jack Donohew (2 copies)

Licensing Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 7E1 Washington, DC 20555-2738 Missouri Public Service Commission Governor Office Building 200 Madison Street P.O. Box 360 Jefferson City, MO 65102-0360

Enclosure ULNRC05 131 March 11, 2005 DOCKET NO.:

UNIT NAME:

COMPLETED BY:

TELEPHONE:

FAX:

50-483 CALLAWAY UNIT I J. Hiller 573/676-4259 573/676-4202 REPORTING PERIOD:

February 2005

1.

DESIGN ELECTRICAL RATING (MWe-Net): 1171

2.

MAX. DEPEND. CAPACITY (MWe-Net): 1125 THIS MONTH YR TO DATE CUMULATIVE

3.

NUMBER OF HOURS REACTOR WAS CRITICAL

4.

HOURS GENERATOR ON-LINE

5.

REACTOR RESERVE SHUTDOWN HOURS

6.

NET ELECTRICAL ENERGY GENERATED (MWH) 672 672 0.0 787,769 1387.27 1369.77 0.0 1,588,550 1 58,265.84 156,220.79 0.0 172,674,767 Page 1 of2

Enclosure ULNRC05131 March 11, 2005 UNIT SHUTDOWNS DOCKET NO.:

UNIT NAME:

COMPLETED BY:

TELEPHONE:

FAX:

50-483 CALLAWAY UNIT I J. Hiller 573/6764259 573/676-4202 REPORT: February 2005 TYPE F: FORCED NO.

DATE S: SCHEDULED DURATION (HOURS)

METHOD OF SHUTTING DOWN REASON THE REACTOR CORRECTIVE ACTIONS/

COM ME ENTS

SUMMARY

Callaway Plant operated at approximately 100% power for the month of February.

REASON A: EQUIPMENT FAILURE (EXPLAIN)

B: MAINT. OR TEST C: REFUELING D: REGULATORY RESTRICTION E: OPERATOR TRAINING / LICENSE EXAMINATION F: ADMINISTRATIVE G: OPERATIONAL ERROR (EXPLAIN)

H: OTHER (EXPLAIN)

M ETHOD 1: MANUAL 2: MANUAL SCRAM 3: AUTOMATIC SCRAM

4. CONTINUATION 5: OTHER (EXPLAIN)

Page 2 of 2