j AmerenUE Callaway Plant PO Box 620 Fulton, MIO 65251 November 10, 2003 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 WAmeenr UE ULNRC04916 Ladies & Gentlemen:
DOCKET NUMBER 50-483 UNION ELECTRIC CO.
CALLAWAY PLANT UNIT 1 FACILITY OPERATING LICENSE NPF-30 MONTHLY OPERATING REPORT OCTOBER/2003 The enclosed Monthly Operating Report for October/2003 is submitted pursuant to Section 5.6.4 of the Callaway Unit 1 Technical Specifications.
Maa u ng Manager, Regulatory Affairs KDY/JER/slk Enclosure a subsidiary of Ameren Corporation
ULNRC04916 November 10, 2003 Page 2 cc: Mr. Bruce S. Mallett Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Jack Donohew (2 copies)
Licensing Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 7EI Washington, DC 20555-2738 Manager, Electric Department Missouri Public Service Commission PO Box 360 Jefferson City, MO 65102
ULNRC04916 Enclosure November 10, 2003 DOCKET NO.:
UNIT NAME:
COMPLETED BY:
TELEPHONE:
FAX:
50-483 CALLAWAY UNIT I J. E. Ready 573/676-8617 573/676-4202 REPORTING PERIOD:
October/2003 I.
DESIGN ELECTRICAL RATING (MWe-Net): 1171
- 2.
MAX. DEPEND. CAPACITY (MWe-Net): 1125 THIS MONTH YR TO DATE CUMULATIVE 3.
4.
5.
6.
NUMBER OF HOURS REACTOR WAS CRITICAL HOURS GENERATOR ON-LINE REACTOR RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED (MWH) 679.5 663.5 0.0 749,941 6,965 6,934 0.0 7,992,340 148,482 146,530 0.0 161,536,436 Page 1 of 2
ULNRC04916 Enclosure November 10, 2003 UNIT SHUTDOWNS DOCKET NO.:
UNIT NAME:
COMPLETED BY:
TELEPHONE:
FAX:
50483 CALLAWAY UNIT I J. E. Ready 573/676-8617 573/676-4202 REPORT: October/2003 TYPE F: FORCED NO.
DATE S: SCHEDULED 303 10/21/2003 F
DURATION (HOURS) 81.5 METHOD OF CORRECTIVE SHUTTING DOWN ACTIONS/
REASON THE REACTOR COMMENTS A
I
SUMMARY
On October 21. 2003. the Callaway Plant was shut down to repair a 120 V inverter.
The inverter was repaired and the plant was returned to service on October 24, 2003.
The September. 2003 Monthly Operating Report listed the cumulative reactor critical hours as 148.522.5. The correct number for cumulative reactor critical hours in September is 147,802.5 REASON A: EQUIPMENT FAILURE (EXPLAIN)
B: MAINT. OR TEST C: REFUELING D: REGULATORY RESTRICTION E: OPERATOR TRAINING / LICENSE EXAMINATION F: ADMINISTRATIVE G: OPERATIONAL ERROR (EXPLAIN)
H: OTHER (EXPLAIN)
METHOD 1: MANUAL 2: MANUAL SCRAM 3: AUTOMATIC SCRAM
- 4. CONTINUATION 5: OTHER (EXPLAIN)