ML020950884

From kanterella
Jump to navigation Jump to search
IR 05000335/2002-006, St. Lucie Nuclear Power Plant, Inspection on 03/14/2002-04/03/2002 Related to Fire Protection Unresolved Item 50-335, 389/98-201-09
ML020950884
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 04/05/2002
From:
NRC/RGN-II
To: Stall J
Florida Power & Light Co
References
EA-02-033 IR-02-006
Download: ML020950884 (22)


See also: IR 05000335/2002006

Text

April 5, 2002

EA-02-033

Florida Power and Light Company

ATTN: Mr. J. A. Stall, Senior Vice President

Nuclear and Chief Nuclear Officer

P. O. Box 14000

Juno Beach, FL 33408-0420

SUBJECT: ST. LUCIE NUCLEAR POWER PLANT - NRC INSPECTION

REPORT 50-335/02-06; PRELIMINARY WHITE FINDING

Dear Mr. Stall:

On April 3, 2002, the NRC completed an in-office open item review for your St. Lucie facility.

The attached enclosure presents the results of that review, which was discussed on April 4,

2002, with Mr. D. Jernigan, St. Lucie Plant Vice President and other members of your staff.

This review was an in-office examination of an unresolved item (URI) which was identified in

NRC Inspection Report 50-335, 389/98-201 and forwarded to Florida Power and Light

Company on July 9, 1998. The URI was: URI 50-335, 389/98-201-09, Fire Mitigation System

Does Not Meet Plant Licensing Basis Requirements/Commitments or Minimum Industry Codes

and Standards for System Design and Testing. The URI included four fire protection program

issues concerning the design and testing of requirements of (1) fire protection systems, (2)

water suppression systems, (3) Halon 1301 fire suppression system, and (4) standpipe and fire

hose system. Issues 1 and 2 were resolved and documented in NRC Inspection Report 50-

335, 389/01-03. Issue 4 was resolved and documented in NRC inspection Report 50-335,

389/98-14. Issue 3 was unresolved pending further NRC review of the adequacy of the St.

Lucie Unit 1 Halon system.

Based on the results of this review, the inspector identified a finding involving failure to have an

installed fixed fire suppression system in an Alternative Shutdown Area. This finding was

assessed using the applicable significance determination process (SDP) and preliminarily

determined to be White (i.e., an issue with low to moderate safety significance, which may

require additional NRC inspections.) This issue was also determined to be an apparent

violation of Section III.G.3 of 10 CFR Part 50, Appendix R requirements. The apparent violation

is being considered for escalated enforcement action in accordance with the "General

Statement of Policy and Procedure for NRC Enforcement Actions - May 1, 2000" (Enforcement

Policy), NUREG-1600.

The NRC acknowledges that compensatory measures were implemented in response to the

URI, which included stationing a fire watch in the affected area. In addition, this matter was

entered into your corrective action program.

FPL 2

Before the NRC makes a final decision on this matter, we are providing you an opportunity to

request a regulatory conference where you would be able to provide your perspectives on the

significance of the finding, the bases for your position, and whether you agree with the apparent

violation. If you choose to request a regulatory conference, we encourage you to submit your

evaluation and any differences with the NRCs evaluation at least one week prior to the

conference in an effort to make the conference more efficient and effective. If a regulatory

conference is requested, it will be held in the NRC Headquarters office in Rockville, Maryland

and open for public observation. The NRC will also issue a press release to announce the

regulatory conference.

Please contact Mr. Randall A. Musser at (404) 562-4540 within seven days of the date of this

letter to notify the NRC of your intentions. If we have not heard from you within 10 days, we will

continue with our significance determination and associated enforcement processes on the

finding and you will be advised by separate correspondence of the results of our deliberations

on this matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for the finding at this time. In addition, please be advised that the characterization of the

apparent violation described in the enclosure may change as a result of further NRC review.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs Document system

(ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

If you have any questions regarding this letter, please contact me at 404-562-4500.

Sincerely,

/RA/

Victor M. McCree, Deputy Director

Division of Reactor Projects

Docket No. 50-335

License No. DPR-67

Enclosure: Inspection Report No. 50-335/02-06

w/Attachment (Phase 3 SDP Analysis)

cc w/encl: (See page 3)

FPL 3

cc w/encl: J. Kammel

D. E. Jernigan Radiological Emergency

Site Vice President Planning Administrator

St. Lucie Nuclear Plant Department of Public Safety

Florida Power & Light Company Electronic Mail Distribution

Electronic Mail Distribution

Douglas Anderson

R. G. West County Administrator

Acting Plant General Manager St. Lucie County

St. Lucie Nuclear Plant 2300 Virginia Avenue

Electronic Mail Distribution Ft. Pierce, FL 34982

T. L. Patterson

Licensing Manager

St. Lucie Nuclear Plant

Electronic Mail Distribution

Don Mothena, Manager

Nuclear Plant Support Services

Florida Power & Light Company

Electronic Mail Distribution

Mark Dryden

Administrative Support & Special Projects

Florida Power & Light Company

Electronic Mail Distribution

Rajiv S. Kundalkar

Vice President - Nuclear Engineering

Florida Power & Light Company

Electronic Mail Distribution

M. S. Ross, Attorney

Florida Power & Light Company

Electronic Mail Distribution

William A. Passetti

Bureau of Radiation Control

Department of Health

Electronic Mail Distribution

Craig Fugate, Director

Division of Emergency Preparedness

Department of Community Affairs

Electronic Mail Distribution

FPL 4

Distribution w/encl:

B. Moroney, NRR

RIDSNRRDIPMLIPB

PUBLIC

OFFICE RII:DRP RII:DRP RII:DRP RII:DRP RII:DRS RII:DNMS RII:EICS

SIGNATURE RMusser HChristensen/for Rbernard for/ltr only LWert

NAME TRoss RMusser COgle VMcCree WRogers LWert SSparks

DATE 4/ /2002 3/29/02 4/5/02 4/ /2002 4/5/02 4/5/02 4/ /2002

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICE RII:EICS NRC:NRR NRC:NRR NRC:NRR NRC:OE

SIGNATURE Cevans defer to

NAME CEvans HBerkow JHannon MJohnson DNelson

DATE 4/ /2002 4/ /2002 4/ /2002 4/ /2002 4/ /2002 4/ /2002 4/ /2002

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICIAL RECORD COPY DOCUMENT NAME: C:\ORPCheckout\FileNET\ML020950884.wpd

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No: 50-335

License No: DPR-67

Report No: 50-335/02-06

Licensee: Florida Power & Light Company (FPL)

Facility: St. Lucie Nuclear Plant, Unit 1

Location: 6351 South Ocean Drive

Jensen Beach, FL 34957

Dates: March 14 - April 3, 2002

Inspector: S. Ninh, Senior Project Engineer

Approved by: Randall A. Musser, Acting Chief

Reactor Projects Branch 3

Division of Reactor Projects

Enclosure

2

SUMMARY OF FINDINGS

IR 05000335-02-06 on 03/14-4/3/02, Florida Power & Light Company, St. Lucie Plant Unit 1.

Region-based follow up review of fire protection Unresolved Item 50-335, 389/98-201-09.

This in-office review was conducted by a regional senior project engineer. The inspector

identified one preliminary White finding with an apparent violation. The significance of an issue

is indicated by it color (green, white, yellow, red) using IMC 0609 Significance Determination

Process (SDP). Findings for which the SDP does not apply are indicated by No Color or by

the severity level of the applicable violation. The NRCs program for overseeing the safe

operation of commercial nuclear power reactors is described at its Reactor Oversight Process

website at http://www.nrc.gov/NRR/OVERSIGHT/index.html.

A. Inspector Identified Findings

Cornerstone: Mitigating Systems

To Be Determined. An apparent violation of Section III.G.3 of 10 CFR 50, Appendix R

was identified for failure to have an installed fixed fire suppression system in an

Alternative Shutdown Area. The licensees Cable Spreading Room (CSR) is designated

as an area requiring Alternative Shutdown capability. The St Lucie Unit 1 CSR Halon

1301 fire suppression system would not be able to extinguish a deep-seated fire

involving cable insulation and jacket material.

This finding appears to have a low to moderate safety significance because a

completely failed Halon system would result in a change in core damage frequency

(CDF) of 4.9E-6. (Section 1R05).

B. Licensee Identified Violations

None

3

1. REACTOR SAFETY

Cornerstone: Mitigating Systems

1R05 Fire Protection

.1 (Closed) Unresolved Item (URI) 50-335, 389/98-201-09: Fire Mitigation System Does

not Meet Plant Licensing Basis Requirements/Commitments or Minimum Industry Codes

and Standards for System Design and Testing.

a. Inspection Scope

The inspector reviewed the adequacy of the St. Lucie Unit 1 Cable Spreading Room

(CSR) Halon 1301 fire suppression system issue associated with the above URI. The

inspector also reviewed the St. Lucie Unit 1 Final Safety Analysis Report. The inspector

evaluated the licensees compliance with the requirements of 10 CFR 50.48(a)(1)(i),

Criterion 3 of Appendix A to Part 50, 10 CFR 50.48(b), and Section III.G.3 of 10 CFR

Part 50, Appendix R.

b. Findings

An apparent violation of Section III.G.3 of 10 CFR 50, Appendix R was identified for

failure to have an installed fixed fire suppression system in an Alternative Shutdown

Area (To Be Determined). The licensees CSR is designated as an area requiring

Alternative Shutdown capability. The St Lucie Unit 1 CSR Halon 1301 fire suppression

system would not be able to extinguish a deep-seated fire involving cable insulation and

jacket material.

The URI was identified during a Nuclear Regulatory (NRC) Fire Protection Functional

Inspection at the St. Lucie Plant in March and April, 1998. The URI included four fire

protection program issues concerning the design and testing of requirements of (1) fire

protection systems, (2) water suppression systems, (3) Halon 1301 fire suppression

system, and (4) standpipe and fire hose system. Issues 1 and 2 were resolved and

documented in NRC Inspection Report 50-335, 389/01-03. Issue 4 was resolved and

documented in NRC inspection Report 50-335, 389/98-14. Issue 3 was identified

concerning a design deficiency of the Halon 1301 fire suppression system installed in

the Unit 1 CSR. The inspector questioned the minimum required concentration and the

minimum soak time requirements. The licensee could not produce design-basis tests

for the concentrations and soak times of the system or demonstrate operability to the

inspectors. The inspector determined this system to be limited in its ability to mitigate a

fire since the system was not designed to extinguish the expected hazard (i.e., a deep-

seated cable fire). Issue 3 was unresolved pending further NRC review of the

adequacy of the St. Lucie Unit 1 Halon system.

Region II requested the Office of Nuclear Reactor Regulation (NRR) to evaluate this

issue in two Task Interface Agreements (TIAs), TIA 99-001, dated January 26, 1999,

and TIA 2000-04, dated May 8, 2000, to determine the design adequacy of the Halon

system for the Unit 1 CSR. NRR completed its review of the TIAs and documented their

4

conclusions by memoranda dated November 29, 1999 (TIA 99-01), August 4, 2000 (TIA 2000-04), and August 30, 2000 (TIA 2000-04). Additionally, several conference calls

with the licensee, Region II and NRR staff were conducted to discuss this issue in 2000

and 2001. The licensee provided additional information related to the CSR smoke and

thermal detection systems and the vendors performance tests of the Halon system for

NRC review.

Risk Assessment

This issue affected the mitigating systems cornerstone due to a design deficiency of a

fire defense-in-depth element, therefore, it was assessed in accordance with the NRC

Reactor Oversight Processs Significance Determination Process (SDP) as described in

NRC Inspection Manual Chapter 0609, Appendix F. The Phase III risk evaluation is

attached. This finding appears to have a low to moderate safety significance because a

completely failed Halon system would result in a change in core damage frequency

(CDF) of 4.9E-6. This finding is preliminarily characterized as a White finding in

accordance with the Fire Protection SDP. The issue was entered into the licensees

corrective action program as CR 98-0131, and the licensee has implemented

compensatory measures in the affected areas.

Apparent Violation

10 CFR 50.48(a)(1)(i) requires that each operating nuclear power plant have a fire

protection plan that satisfies Criterion 3 of Appendix A to Part 50.

Criterion 3 of Appendix A to Part 50 states that fire detection and fighting systems of

appropriate capacity and capability shall be provided and designed to minimize the

adverse effects of fires on structures, systems and components important to safety.

10 CFR 50.48(b) provides that Appendix R to Part 50 establishes fire protection features

required to satisfy Criterion 3.

Section III.G.3 of 10 CFR Part 50, Appendix R, requires that fire areas which require

Alternative Shutdown have fire detection and a fixed fire suppression system installed in

the area.

Contrary to the above, the licensee does not have an installed fixed fire suppression

system in an Alternative Shutdown Area. The licensees Cable Spreading Room (CSR)

is designated as an area requiring Alternative Shutdown capability. In 1986, the

licensee installed a Halon 1301 fire protection suppression system in the CSR. In order

to suppress a fire for special hazards such as a Halon fire suppression system, it must

be capable of extinguishing a fire. The licensees Halon 1301 system is designed to

achieve a minimum 5-7% halon concentration and minimum soak time of 10 minutes,

while a minimum 10% halon concentration and minimum soak time of 10 minutes is

necessary to extinguish a fire in a CSR. This failure to comply with Section III.G.3 of 10 CFR Part 50, Appendix R is identified as an apparent violation (AV) 50-335/02-06-01,

Failure to Have an Installed Fixed Fire Suppression System in an Alternative Shutdown

Area.

5

4OA6 Management Meeting

Exit Meeting Summary

Mr. R. Musser, Acting Chief, Reactor Projects Branch 3, Region II presented results to

Mr. D. Jernigan, Site Vice President and other members of the licensee staff via

telephone on April 4, 2002.

KEY POINTS OF CONTACT

Licensee

D. Jernigan, Site Vice President, St. Lucie

NRC

T. Ross, Senior Resident Inspector, St. Lucie

L. Wert, Acting Chief, Fuel Facilities Branch, Region II

ITEMS OPENED AND CLOSED

Opened

50-335/02-06-01 AV Failure to Have an Installed Fixed Fire Suppression

System in an Alternative Shutdown Area.

Closed

50-335, 389/98-201-09 URI Fire Mitigation System Does not Meet Plant

Licensing Basis Requirements/Commitments or

Minimum Industry Codes and Standards for

System Design and Testing.

Attachment

Phase 3 SDP Analysis: St. Lucie CSR Halon System Deficiency

1. Performance Deficiency

The St. Lucie Unit 1 Cable Spreading Room (CSR) [Fire Zone 57] Halon 1301 fire

suppression system did not meet regulatory or National Fire Code minimum

requirements for concentration and hold time to extinguish a deep-seated fire involving

cable insulation and jacket material. This condition has existed since 1986 and was

identified as Unresolved Item (URI) 50-335, 389/98-201-09 in NRC Inspection Report

50-335, 389/98-201, dated July 9, 1998, i.e. greater than 3 years.

2. Fire Scenario

The fire loading for combustibles in the St. Lucie Unit 1 CSR is over 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />, with the

primary combustibles being electrical cables located above numerous potential ignition

sources. The potential ignition sources include the pressurizer heater transformers,

power programmer cabinets, 480V load centers, DC distribution panels, and reactor trip

switchgear. Other potential ignition sources, such as a power cable failure in a tray, or

other electrical originated failures (in distribution panels, circuit boards, electrical wiring,

internal cable fault, electrical circuit fault in switchgear cabinets, etc.) leading to ignition

of the in-situ combustibles (cables), are considered in the fire scenario. Although

creditable, outside ignition sources such as hot work (welding) or transient sources were

not factored into this analysis due to the large number of potential in-situ ignition

sources in the area.

One credible fire scenario is based on postulating that a fire develops from any one of

the potential in-situ electrical ignition sources, if undetected and unsuppressed, would

grow to a rate of heat release of 600 kW and ignite the cable insulation of electrical

cables resulting in deep-seated fires. The St. Lucie Unit 1 CSR Halon system is

actuated by a cross-zoned thermal detection system. The cross-zoned thermal

detection system requires two independent detectors, spaced some distance apart, to

reach their preset actuation temperature to initiate operation of the Halon system. After

the Halon system control panel has been activated, all the permissive circuits must be

completed to start the 30-second release delay alarm (for evacuation) followed by

system discharge. The permissive circuits include electrical confirmation that 3 HVAC

fans have stopped, 3 electrically-melted fusible links have operated and their associated

fire dampers closed, one motor-operated damper has cycled closed, and 5 fire doors

are verified closed. If any one of these permissive circuits does not confirm its operation

(e.g., electrical melting of the fusible link in fire damper FPPR-25-117 fails), the Halon

system will not automatically discharge its gaseous inventory.

The CSR area also has a fire detection system equipped with ionization smoke

detectors that only alarms in the Main Control Room (MCR). The Halon system was

designed to maintain a concentration of 5 to 7 percent for a minimum of 10 minutes for

extinguishing fires. However, the NFPA Standard 12A states that "deep-seated fires

usually require much higher concentrations than 10 percent and much longer soaking

times than 10 minutes." Thus, a fully developed deep-seated fire in the CSR fire zone

57 would overpower the suppressive capability of the Halon fire suppression system

resulting in damage to electrical cables performing safe shutdown functions and loss of

plant control from the MCR. In the event of an uncontrollable fire in the cable spreading

room, alternate shutdown of the plant outside the MCR would be required from the hot

shutdown control panel room in the Electrical Equipment Room1B which is located

adjacent to the cable spreading room.

In this fire scenario, it is assumed that a fire starts from a specific ignition source (e.g.,

pressurizer heater transformers, power programmer cabinets, etc.) and has sufficient

flame spread (i.e., flame height and radius) to ignite a cable tray closest to the ignition

source. Deep-seated fires (which are the concern of the finding related to the Halon

system design concentration and soak time at St. Lucie Unit 1 CSR) can be either

severe or non-severe (i.e. depending on whether fire damage is limited to the

component of fire origin). Severe fires are defined as fires that have grown beyond the

incipient stage and have the potential to damage structures, systems or components

(SSCs) beyond the SSC in which the fire originates. However, all severe fires, as

defined above, involving cables routed in cable trays are expected to result in a deep-

seated fire due to the combustible characteristics of cable insulation (i.e., the fire burns

internally as opposed to a surface fire). Based on the SPLB fire hazards analysis (see

attachment), it is postulated that a credible fire propagation pathway exists in the power

programmer cabinets, 480 V reactor auxiliary common MCC 1AB, vital AC supply

panels, and DC bus 1AB-1. The failure of 480V reactor auxiliary common MCC 1AB,

vital AC supply panels, and DC bus 1AB-1 would cause preheating of cables leading to

cable failure, thus initiating a secondary fire in the cable trays. Three different cases of

cable tray fire were postulated to bound the fire scenario: (1) a cable tray fire with

mechanical ventilation on (i.e., HVAC system was not shut down during the fire), (2) a

cable tray fire with exhaust fan on only (i.e., smoke purge during suppression), and (3) a

cable tray fire with mechanical ventilation off. In modeling the fire growth and damage

potential, Case 2 was considered to be the better representation of actual conditions in

the CSR. In the event of a fire, supply fan(s) in the CSR should shut down automatically

and the ventilation is limited only by the exhaust flow rate from the CSR.

The CFAST (Consolidated Model of Fire Growth and Smoke Transport) computer code

was used to model the fire growth of cable tray fire that is, by definition, considered to

be a deep-seated fire. The cable trays were assumed to ignite at the bottom of the

lowest tray which means that the entire cable tray will burn to produce a larger peak

heat release rate (HRR). For this analysis, the HRR for cable tray fires will be

approximated as slow fire growth rate. Results from the CFAST simulation of the

three ventilation conditions in the CSR show that there is sufficient oxygen available in

the CSR, even without mechanical ventilation and the door closed, such that a

significant fire can be sustained for some period of time. The upper gas layer

temperature with mechanical ventilation on (supply and exhaust) and with exhaust fan

on only, can lead to a flashover. Flashover is a phenomenon, which defines the point in

a compartment fire where all combustibles in the compartment are involved and flames

appear to fill the entire volume. During a fire, the exhaust fan will remove smoke from

the hot gas layer and raise the elevation of the layer interface. This exhaust will allow

the fire to burn at a higher intensity since more fresh air will be entrained into the fire

from the lower layer. Due to high temperatures of the upper gas layer, it is possible that

the exhaust fan could fail during the fire. In the case of cable tray fire with exhaust fan

on only (Case 2), the CFAST results show that the time to flashover ranges from 23

minutes to 29 minutes depending on the tray surface area.

During normal operations, the doors from CSR to other areas are closed. As such,

there are no large openings available (according to the licensee) to allow air into the

CSR to feed the fire. This will result in the fire becoming ventilation limited such that it

will burn at a lower intensity with a greater production of toxic smoke. The peak HRR is

ultimately determined by the amount of fresh air available to the fire. However, the CSR

is not perfectly sealed, gaps around the door and small cracks around the CSR will allow

the passage of air from the outside. Flashover occurs when all of the combustible

materials located in the compartment are involved and the fire is ventilation limited.

Backdraft is a phenomenon that results when a relatively well-sealed compartment is

ventilated near the floor level after the fire has been burning for an extended period of

time (i.e., hours) and almost all of the oxygen has been consumed, the compartment

accumulates a large quantity of non-combusted fuel-rich gases and the compartment

temperatures have increased significantly due to a smoldering fire in a semi-quiescent

state. The sudden addition of air (containing oxygen) results in the ignition of the fuel-

rich gases in a detonation or deflagration (i.e., backdraft occurs). The CFAST modeling

appears to indicate that flashover can occur without additional ventilation. If this is the

case, a backdraft cannot occur regardless of the fire brigade actions and the likelihood

that the fire would be allowed to develop for hours is small. Since there is sufficient

ventilation in the compartment for flashover, the fire brigades actions are not relevant to

the issue.

The effects of CSR fire were modeled using the HRR from the PE/PVC cable jacket

insulation with various cable tray exposed surface areas. Temperatures and products of

combustion in the CSR could result in damage to the entire CSR and all in-situ

combustibles therein. Without prompt automatic/manual fire suppression, hazardous

conditions are expected to occur in a relatively short period of time, i.e., about 23

minutes, in the CSR.

Non-IEEE-383 qualified cables were installed in the St. Lucie 1 CSR during its original

construction. These cables installed in the CSR cable trays were coated with Flamastic

fire-retardant coatings in order to offset the rapid flame spread of the thermoplastic

cables in the event of fire. However, Flamastic cable-coating is combustible, i.e., it does

not fire-proof the cables as initially thought. Table III of the Sandia National

Laboratories (SNL) report, A Preliminary Report on Fire Protection Research Program

Fire Retardant Coatings Tests, SAND 78-0518, 1978 provides the following data points:

(a) Test 13, non-IEEE-383 cable without cable coating had a burning duration of 36

minutes and an affected length of 70 inches.

(b) Test 9, IEEE-383 cable without cable coating had a burning duration of 13 minutes

and an affected length of 27 inches.

(c) Test 3, Same cable as Test 9 with Flamastic coating had a burning duration of 7

minutes and an affected length of 40 inches.

The Sandia cable test program did not test non-IEEE-383 cables with Flamastic

coatings (which were installed in St. Lucie 1 CSR cable trays). The cable trays in the

Sandia tests were only tested in the horizontal configuration which is not the worst case

configuration for cable tray fires. (Vertical cable tray configurations provide a more

challenging configuration, in that heat from the burning cables in the lower trays will

expose the cables above, causing the exposed cables to offgas and support more rapid

combustion. St. Lucie 1 CSR has both vertical and horizontal cable tray arrays.) Based

on this limited test data, it can be conjectured that the non-IEEE-383 qualified cables

with Flamastic coating in the St. Lucie 1 CSR, will perform better than Test #13 (Non-

IEEE 383 cables without coating) but not as well as Test#9 (IEEE-383 cables) or Test

  1. 3 (IEEE-383 cables with Flamastic coating). It is also assumed that any post-1980

modifications at St. Lucie 1 included the installation of IEEE-383 qualified cables, such

that the current as-installed plant configuration has both IEEE-383 qualified and non-

qualified cables with Flamastic coatings. Based on this information, even though non-

IEEE-383 qualified cables had been installed in the St. Lucie 1 CSR, no penalty has

been assessed in the analysis. Likewise, no credit for the Flamastic coatings was

assessed in the analysis.

Based on the results of the fire modeling, SPLB fire protection staff concluded that a fire

in the CSR would have a significant impact on the CSR. Depending on the ventilation

condition and exposed surface areas involved, it is possible for the room to flashover

and this could result in failure of the CSR structure.

3. Assumptions

(a) Fire Barrier - The licensee had replaced the Thermo-Lag 330 fire barrier wall

separating the Unit 1 cable spreading room and the Electrical Equipment Room 1B, with

a sheet metal and ceramic fibre barrier (See NRC Inspection Report 50-335/99-08,

January 31, 2000). As a result of the modification, the barrier can be considered to be

in the normal operating state. Therefore, in the event that both equipment trains in the

CSR are affected by fire, the remote hot shutdown panel in Electrical Equipment Room

1B could be used to achieve safe shutdown of the plant.

(b) Fire Detection and Manual Fire Suppression - The Unit 1 CSR is equipped with a

cross-zoned thermal detection system, which activates the Halon system. The cross-

zoned thermal detection system has two independent detectors per ceiling bay, spaced

some distance apart and preset to reach their actuation temperature to initiate the

discharge of the Halon system. The CSR area is also equipped with a detection system

of ionization smoke detectors that provide alarm conditions in the Main Control Room

(MCR). The 1998 Fire Protection Functional Inspection (FPFI) found a number of

problems with the Fire Alarm Control Panel (FACP) annunciator located in the MCR,

most notably the audible levels in the MCR (Section F7.4.1 of FPFI report). The

licensee had initiated a Condition Report, CR98-0453, to correct this problem. With this

condition corrected, alarms from the ionization fire detection system would result in the

dispatch of an operator to investigate the CSR, and plant-specific procedures (1-ONP-

100.01) would be implemented to notify the fire brigade for fire-fighting response. The

time taken for operator response to the fire alarm and arriving at the CSR area should

be reasonably rapid since the CSR is located directly below the MCR.

Based on previous four fire drills, all (five) members of the fire brigade arrived at the

CSR area in about 10 minutes after the MCR personnel sounds the alarm. The arrival

time of the assembled fire brigade in 10 minutes may not include the time from fire

ignition to the time that the alarm is sounded by MCR operators. This unaccounted time

begins when the fire must ignite (time = 0), grow and generate products of combustion

in sufficient quantity to initiate the local spot detector, the spot detector then sends an

alarm to the Local Fire Alarm Control Panel (LFACP) which in turn transmits an alarm to

the main FACP in the MCR. The operator must then acknowledge the alarm and

determine the location of the fire. By normal procedures, a member of the operations

staff would be dispatched to investigate the origin of the alarm. Upon confirmation of

the fire, the operations staff will then determine if the fire brigade should be activated. In

IPEEE reviews, the IPEEE Senior Review Team considered that the time from the start

of the fire until fire brigade arrival was a minimum of 30 minutes across industry-wide

experience. Consistent with the Reactor Oversight Process, a fire brigade rating of

normal operating state is attributed to the fire brigade response capability in order to

evaluate the significance of the degraded halon system.

The fire-induced core damage frequency (CDF) equation for the CSR area can be

defined as follows:

FCDF = Fi * Sf * P1 * P2 * P3

where Fi = Fire ignition frequency of ignition source

Sf = Severity factor for a challenging fire

P1 = Failure probability of Halon system

P2 = Failure probability of manual suppression by fire brigade

P3 = Conditional core damage probability, or failure probability of operator to

operate remote hot shutdown panel in Electrical Equipment Room 1B

This fire-induced CDF equation does not account for geometry factors for a large fire to

damage the critical equipment. Geometry factors are not recognized as an accepted

partitioning method for fire events. The use of geometry factors was proposed in some

early fire PRAs. However, this approach was rejected by NRC reviewers during the

IPEEE review process. Most fires that have challenged the safe shutdown capability of

a plant have not been characterized as large (Nureg/CR-6738), and also, the definition

of severe fires in the EPRI Fire PRA Implementation Guide include more than large

fires.

4: Fire Ignition Frequencies

The various ignition sources in the CSR area and their associated fire ignition frequency

estimates, as provided on the Ignition Source Data Sheet (ISDS) for the St. Lucie Unit 1

CSR, are shown below:

Ignition Source Fire Ignition Frequency

1. Transformers 1.09E-3

2. Electrical Cabinets 3.20E-3

3. Ventilation Systems 3.39E-4

4. Cable Runs 7.65E-4

5. Fire Protection Panels 1.75E-4

The ignition frequency estimate of 1.09E-3/yr for transformers represents the total

contribution from 10 transformers in the CSR. However, only two of the 10 transformers

are high voltage, dry-type transformers. The other transformers are small and low

voltage transformers, and are not located near to the combustible loads. In the case of

high voltage, dry-type transformers, vendor-specific information from ABB Power T& D

Co., indicated that only two transformer fires involving the VPE and VPI dry-type

transformers have occurred during 100,453 service years. This provides an estimate of

2.0E-5/yr for the fire ignition frequency of transformers in the CSR. This component-

specific fire ignition frequency estimate, rather than the IPEEE generic estimate of

1.09E-3/yr for transformers in the CSR, was used in the risk analysis because the

estimate of 2.0E-5/yr reflects realistic operational experience of the transformers.

The ignition frequency of 3.2E-3/yr for electrical cabinets represents the total

contribution from all electrical cabinets including the reactor trip switchgear (240V AC,

with solid bottom tray and solid cover above), 125 V DC bus, battery chargers, 480V

motor control centers, and programmer cabinets. It was conservatively estimated that

there are at least 80 electrical cabinets in the CSR. As identified in the CSR layout

drawing, the only electrical cabinet housing medium voltage electrical equipment is the

480V Motor Control Center 1AB cabinet. The licensees fire hazard analysis showed

that MCCs have concentrated combustible loading of 830,000 BTUs. The remaining

electrical cabinets located in the CSR contain low voltage electrical equipment, and

each appear to have low combustible loadings (i.e., the volume fraction of cable

insulation and non-metal combustibles is estimated to be 10 percent or less). Based on

these considerations, the evaluation of risk impacts from electrical cabinets is divided

into two scenarios, beginning with: (1) 480V MCC 1AB cabinet, and (2) remaining low

voltage electrical cabinets. Therefore, the ignition frequencies for the 480V MCC 1AB

cabinet and remaining low voltage electrical cabinets used in the risk analysis were

estimated as follows:

(1) 480V MCC 1AB cabinet: (1/80)x (3.2E-3) = 4.0E-5 events/yr

(2) Low voltage electrical cabinets: (79/80)x(3.2E-3) = 3.16E-3 events/yr

The ignition frequency estimate of 1.75E-4/yr for the fire protection panels represents

the total contribution from two supervisory electrical cabinets containing relays and

annunciator lights alarming the fire zones affected by fire.

5: Conditional Core Damage Probability (CCDP)

In the various fire scenarios considered (i.e., each scenario initiated by a different

ignition source), the conditional core damage probability was estimated to be 3.0E-4

(using licensees PRA model) if there is one equipment train available to perform

mitigating functions. In the event that both equipment trains in the CSR are affected by

fire, the CCDP would be dominated by operator actions to achieve safe shutdown at the

remote hot shutdown (HSD) panel at the Electrical Equipment Room 1B.

In the licensees IPEEE study, the human error probability (HEP) of failing to control the

plant safe shutdown at the HSD control panel was estimated to be 0.1. In the deep

seated fire scenario, performance shaping factors (PSFs) for the HEP of operator

failure to start the HVAC fan to prevent heat and smoke buildup before operating safe

shutdown equipment must be considered. Using the ASP human error worksheet, the

total PSF value for the nominal HEP of the action to start the HVAC fan was determined

to be 300 based on the multiplication of each PSF (i.e., nominal time = 1, extreme stress

= 5, moderately complex = 2, low experience, or training = 3, available, but poor

procedures = 5, nominal ergonomics = 1, nominal fitness for duty = 1, poor work

processes = 2). Since the nominal HEP for a single action of starting the HVAC fan is

1E-3, the estimated HEP is 0.3 for the case of the available procedure having poor

instructions for achieving proper ventilation and smoke control. In a hostile, fire-induced

environment, an important PSF for consideration is the opacity effects of smoke on the

operator to manipulate the HSD control panel. If the smoke effects on the operators

vision to manipulate the HSD control panel and potential ineffectiveness of the HVAC

system after its restart (based on an inspection finding discussed in NRC IR 98-201) are

taken into account, an additional probability value of 0.1 should be included in the

overall estimation of the operator failure to achieve safe shutdown. Therefore, a

reasonable value of the HEP for operator failure to manually start the HVAC and

operate the HSD control panel was estimated to be 0.4 for the stated case. This

probability value is more conservative than the probability of 0.1 assumed in the

licensees analysis.

6. Integrated Assessment of Fire-Induced Core Damage Frequency

The fire-induced CDF estimate for fire in the CSR with a failed Halon system is

calculated as shown below:

Ignition Source Fi Sf P1 P2 P3 FCDF

1. Transformers 2.00E-5 1.00 1.0 0.5 4.0E-1 4.0E-6

2. 480V MCC 1AB Cabinet 4.00E-5 0.12 1.0 0.5 4.0E-1 9.6E-7

3. Low Voltage Electrical Cabinets 3.16E-3 0.12 1.0 0.5 3.0E-4 5.7E-8

4. Ventilation Systems 3.39E-4 0.08 1.0 0.5 3.0E-4 4.1E-9

5. Cable Runs 7.65E-4 0.01 1.0 0.5 4.0E-1 1.5E-6

6. Fire Protection Panels 1.75E-4 0.12 1.0 0.5 3.0E-4 3.2E-9

Total CDF 6.5E-6

(a) Severity Factors, Sf - A fire severity factor is a fractional value (between 0 and 1) that

is used to adjust fire frequency estimates to reflect some specific mitigating pattern of

behavior of the fire event. The severity factor is applied to reflect a split in challenging

versus non-challenging fires. In the absence of plant-specific information, the severity

factors for the electrical cabinets, ventilation systems, and fire protection panels were

based on the EPRI Fire PRA Implementation Guide (FPRAIG), December 1995 (Section

D.3). The FPRAIG severity factors ranged from 0.08 to 0.2, and engineering judgment

was used to determine these severity factors. The question of double counting was

raised concerning the use of severity factors and credit for manual suppression by the

fire brigade in this risk analysis. The severity factors used for the fire risk analysis of the

electrical cabinets, ventilation systems, and fire protection panels reflect the ratio of

severe fires to the total number of fires observed in each fire source group. The severity

factor approach used in the risk analysis model is to account for the probability of fire

growth, and the severity factors are independent of the credit for subsequent fire-

fighting efforts by the fire brigade.

The severity factor used for the pressurizer heater transformers in the risk analysis is

1.0 because it is assumed that the transformer fire would be a single-point source of

flames with height of at least 5 feet, and the distances from the top of the transformers

to the lowest cable trays were less than 5 feet. The use of the severity factor of 1.0 is a

conservative assumption because the reported transformer fires (based on vendor

historical information) were self-extinguished when the fires were not sustained after

ignition.

In the case of cable runs in the CSR, it is the analysts judgment that the severity factor

used in the risk analysis is 0.01 based on the assumption that one percent of self-ignited

cable tray fires may grow into a large fire if the original fire is undetected and

unsuppressed. Although cable self-ignition events have occurred in the past, none of

the self-ignited cable fires in the current operating U.S. plants have led to a large fire

(see NUREG/CR-6738). Furthermore, some of the cable trays in the CSR are vented

trays with solid covers, and the average fill of the cable trays near to the major ignition

sources (i.e., pressurizer heater transformers and programmer cabinets) is, at the most,

about 25 percent.

(b) Halon system failure probability, P1 - The failure probability of the Halon system to

extinguish a fully-developed fire in the CSR was assumed to be 1.0. The major in-situ

fire hazard in the CSR is of electrical origin. The major in-situ fuel loading in the CSR is

cable insulation and jacket (for both IEEE-383 and non-IEEE-383 qualified cables).

Electrical cable fires are deep-seated fires. St. Lucie Stations NFPA Code of Record

(COR) for the installation of the Halon system is NFPA 12A, Halon 1301 Fire

Extinguishing Systems, 1980 Edition. The code recommends a minimum of 10%

concentration Halon 1301, held in the enclosure for a minimum of 10 minutes (Section

A-2-4), or allows a different concentration and hold time that is approved by the

Authority Having Jurisdiction (AHJ). The NRC, i.e., the AHJ, had sponsored testing of

fire suppressant agent effectiveness, and established the minimum concentrations and

hold times for fire suppressant agents used to extinguish cable fires in nuclear power

plants. As documented in NUREG/CR -3656, Evaluation of Suppression Methods for

Electrical Cable Fires, October 1986, Table 8 shows that a minimum of 6%

concentration of Halon 1301 should be held for 15 minutes for IEEE-383 qualified cables

and 10 minutes for non-IEEE-383 qualified cables to result in no re-ignition from fully

developed, five-tray cable fires. At the lowest cable tray elevation, the CSR Halon 1301

system drops below 6% concentration after 4 minutes and continues to decrease to

approximately 4.5% at 15 minutes. Concentrations measured at the lowest levels of the

CSR (i.e., on the floor far below the cable fire hazard) are less than the minimum 6%

concentration at 15 minutes. Therefore, no credit was given to the Halon 1301

suppression system. Furthermore, research studies have shown that the ineffective

Halon 1301 agent which thermally decomposes will increase the generation of toxic

products of combustion (smoke). Most notably, halogen acid products, particularly

hydrogen fluoride, are generated. This condition will further hamper fire brigade

personnel in performing manual suppression activities, and affect operations personnel

in adjacent locations performing alternate shutdown.

(c) Manual Suppression by Fire Brigade, P2 - Historical records of fire brigade drills

performed for the CSR (on 11/14/85, 9/19/97, 3/6/98, and 3/8/98) have shown that all

required members of the fire brigade team arrived at the CSR in less than 10 minutes

after notification. Additionally, historical records of fire brigade response to fires in the

CSR due to capacitor failures in battery charger cabinets (on 12/6/83 and 11/14/85)

indicated that the two fires were successfully extinguished by operators investigating the

scene prior to the arrival of the full fire brigade in 6 minutes after notification from the

Control Room.

Based on the above considerations, together with the discussion in Section 3b, entitled:

Fire Detection and Manual Fire Suppression, and since the fire brigade response

capability was considered to be in the normal operating state (due to the Reactor

Oversight Process guidance to consider findings separately in significance evaluations

unless a common root cause exists), the failure probability of manual suppression by the

fire brigade associated with severe fires was estimated to be 0.5 in this risk analysis.

(d) Conditional Core Damage Probability, P3 - In the fire scenarios involving ignition of

the electrical cabinets, ventilation systems, and fire protection panels, an analysis was

performed to determine whether a redundant cable train would be affected by fire

damage from the specified ignition source. In this analysis, the critical radiant flux

distances were estimated for various peak fire intensities (e.g., 65 BTU/sec to 500

BTU/sec) using the single-point source equation on page 10.4-23 of the Fire-Induced

Vulnerability Evaluation (FIVE) Report. The critical radiant flux distance varies from 2.0

ft. for 65 BTU/sec to 5.6 ft. for 500 BTU/sec heat release rate and 0.5 BTU/s/ft2 for

unqualified cables. These critical heat flux distances were then compared to the

horizontal distances between the redundant trains of cable trays with the specific ignition

source directly below its nearest cable tray. Based on review of layout drawings of the

cable tray configurations and ignition source locations, and information on measured

distances provided by the licensee, the minimum horizontal distance between redundant

cable trains was estimated to be 6 ft (for the low voltage electrical cabinets such as 125

VDC Bus 1AB-1, 1AB Battery Charger, 1AB DC Switchgear, and Vital AC Supply

cabinets), while the maximum distance between A and B trains is about 19 ft (for the

pressurizer heater transformers). Based on observations of low combustible loadings of

the low voltage electrical cabinets (i.e., the volume fraction of cable insulation and non-

metal combustibles is estimated to be 10 percent or less) and the minimum distance

separation of redundant cable trains being greater than the critical radiant heat flux

distances with conservative heat release rates, it is reasonable to assume that one

equipment train would be available to perform mitigating functions if any of the low

voltage electrical cabinets were to ignite. Therefore, the CCDP estimate of 3.0E-4 was

used in the risk analysis of the fire scenarios involving the low voltage electrical

cabinets. Similar arguments can be made to use the CCDP estimate of 3.0E-4 for

analyzing the fire scenarios involving the ventilation systems and fire protection panels.

The air handling units, HVA-4 and HVA-5, located in the CSR contained less than 4 lb.

of plastic filter material and wiring insulation and a few ounces of grease associated with

the fan and motor. The air handling units are about 3 ft. below the nearest cable trays,

and the distance between redundant cable trains appear to be greater than 6 ft. The

two fire protection panels are small enclosed metal boxes with small indicator lights that

show the location of specific detectors in the alarm mode. Each fire protection panel

contains about 10 lb of plastic/insulation, and are located about 3 ft horizontally and 4 ft

vertically from the nearest cable tray.

In the case of the transformers and cable runs, it is assumed that a fire from these

sources would result in a deep-seated fire and the operators would have to gain access

to the remote HSD panel to achieve safe shutdown of the plant. Based on the ASP

Human Reliability Analysis method, the operator failure to operate the HSD control

panel was estimated to be at least 0.4, and this probability was used in the risk analysis

as the CCDP estimate. The risk impact of spurious actuations from hot shorts is

subsumed in this CCDP estimate of 0.4.

In the case of 480V Motor Control Center 1AB cabinet, the licensees fire hazard

analysis showed that MCCs have concentrated combustible loading of 830,000 BTUs.

This 830,000 BTU combustible loading can result in a fire of peak fire intensity of 332

BTU/sec (using the equation on page E-8, Fire PRA Implementation Guide). The critical

radiant flux distance for this fire peak intensity was estimated to be 4.7 ft. Although the

minimum separation distance between redundant cable trays for the nearest cable tray

above the 480V MCC 1AB cabinet is about 6 ft., it is assumed that a fire from the 480V

MCC 1AB could damage both redundant cable trains as a bounding analysis. Therefore,

the CCDP estimate of 0.4 was used in the risk analysis of a fire from the 480V MCC

1AB.

7: Incremental Fire-Induced CDF

The baseline CDF (conforming case) for the cable spreading room without a degraded

Halon system is calculated by assuming the Halon system failure probability of 0.05, and

the manual suppression failure probability of 0.1. These values were used for the non-

degraded Halon system and manual suppression capability because the values were

considered to be appropriate for the entire population of fires (including deep-seated

fires) arising from an ignition source. It is expected that failure probabilities for these fire

protection systems and features would be much higher if a severity factor was used

since the severity factor represents the case where only severe fires are considered.

Severe fires are defined as fires that have grown beyond the incipient stage and would

have the potential to damage structures, systems or components (SSCs) beyond the

SSC in which the fire originates. Severe fire events are a subset of the entire population

of fires.

Deep-seated fires (which are the concern of the finding related to the Halon system

design concentration and soak time at St. Lucie Unit 1 CSR) can be either severe or

non-severe (i.e. depending on whether fire damage is limited to the component of fire

origin). Based on data from currently available databases of fire events, it is presently

not feasible to partition the deep-seated fire events from the non-deep-seated fire

events to develop a deep-seated fire factor to adjust the fire ignition frequency similar

to that done for severe fires. However, all severe fires, as defined above, involving

cables routed in cable trays are expected to result in a deep-seated fire due to the

combustible characteristics of cable insulation (i.e., the fire burns internally as opposed

to a surface fire). Additionally, an accurate determination of the effectiveness of a code

compliant Halon system on a severe fire is beyond the current state-of-the-art methods.

The basis for using the failure probability value of 0.05 for the non-degraded Halon

system in the conforming case of this analysis is found in EPRIs Fire-Induced

Vulnerability Evaluation (FIVE) guidance (page 10.3-7). This probability value is the

accepted value used by the community of fire risk analysis practitioners for a non-

degraded Halon system. The basis for using the probability of 0.1 for failure of manual

suppression in this conforming-case analysis is, as discussed above, that the value of

0.1 is appropriate for the entire population of fires. The fire protection SDP

methodology, which uses the entire population of fires as the basis to derive an ignition

frequency, also uses the probability value of 0.1, in general, for the failure probability of

nondegraded manual suppression capability.

Based on the preceding discussions, the baseline CDF for the St. Lucie Unit 1CSR

without a degraded Halon system is calculated as shown below:

Ignition Source Fi P1 P2 P3 FCDF

1. Transformers 2.00E-5 0.05 0.1 4.0E-1 4.0E-8

2. 480V MCC 1AB Cabinet 4.00E-5 0.05 0.1 4.0E-1 8.0E-8

3. Low Voltage Electrical Cabinets 3.16E-3 0.05 0.1 3.0E-4 4.7E-9

4. Ventilation Systems 3.39E-4 0.05 0.1 3.0E-4 5.1E-10

5. Cable Runs 7.65E-4 0.05 0.1 4.0E-1 1.5E-6

6. Fire Protection Panels 1.75E-4 0.05 0.1 3.0E-4 2.6E-10

Baseline CDF 1.6E-6

The incremental CDF change due to a failed Halon system in the CSR would be:

6.5E-6 - 1.6E-6 = 4.9E-6

CONCLUSION: The change in CDF due to a completely failed Halon system is 4.9E-6.

Therefore, the significance characterization of this issue is WHITE.