MONTHYEARLIC-99-0096, Monthly Operating Rept for Sept 1999 for Fcs,Unit 1.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fcs,Unit 1.With LIC-99-0084, Monthly Operating Rept for Aug 1999 for Fort Calhoun Station.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fort Calhoun Station.With ML20210R1961999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fcs,Unit 1 LIC-99-0065, Monthly Operating Rept for June 1999 for Fort Calhoun Station,Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fort Calhoun Station,Unit 1.With ML20210R2081999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Fcs,Unit 1 LIC-99-0053, Monthly Operating Rept for May 1999 for Fort Calhoun Station,Unit 11999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fort Calhoun Station,Unit 1 LIC-99-0047, Monthly Operating Rept for Apr 1999 for Fort Calhoun Station Unit 1.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fort Calhoun Station Unit 1.With LIC-99-0034, Monthly Operating Rept for Mar 1999 for Fcs,Unit 1.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fcs,Unit 1.With LIC-99-0025, Monthly Operating Rept for Feb 1999 for Fort Calhoun Station,Unit 1.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fort Calhoun Station,Unit 1.With LIC-99-0003, Monthly Operating Rept for Dec 1998 for Fort Calhoun Station.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fort Calhoun Station.With LIC-98-0172, Monthly Operating Rept for Nov 1998 for Fort Calhoun Station,Unit 1.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fort Calhoun Station,Unit 1.With LIC-98-0154, Monthly Operating Rept for Oct 1998 for Fort Calhoun Station,Unit 1.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fort Calhoun Station,Unit 1.With LIC-98-0136, Monthly Operating Rept for Sept 1998 for Fort Calhoun Station,Unit 1.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fort Calhoun Station,Unit 1.With LIC-98-0122, Monthly Operating Rept for Aug 1998 for Fort Calhoun Station Unit 1.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fort Calhoun Station Unit 1.With LIC-98-0105, Monthly Operating Rept for July 1998 for Fort Calhoun Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fort Calhoun Station LIC-98-0092, Monthly Operating Rept for June 1998 for Fort Calhoun Station,Unit 11998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fort Calhoun Station,Unit 1 LIC-98-0078, Monthly Operating Rept for May 1998 for Fort Calhoun Station Unit 11998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fort Calhoun Station Unit 1 LIC-98-0070, Monthly Operating Rept for Apr 1998 for Ft Calhoun Station1998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Ft Calhoun Station LIC-98-0058, Monthly Operating Rept for Mar 1998 for Fcs,Unit 11998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fcs,Unit 1 LIC-98-0035, Monthly Operating Rept for Feb 1998 for Fcs,Unit 11998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fcs,Unit 1 LIC-98-0016, Monthly Operating Rept for Jan 1998 for Fort Calhoun Station1998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fort Calhoun Station LIC-98-0002, Monthly Operating Rept for Dec 1997 for Fcs,Unit 11997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fcs,Unit 1 LIC-97-0191, Monthly Operating Rept for Nov 1997 for Fcs,Unit 11997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fcs,Unit 1 LIC-97-0179, Monthly Operating Rept for Oct 1997 for Fcs,Unit 11997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Fcs,Unit 1 LIC-97-0163, Monthly Operating Rept for Sept 1997 for Fcs,Unit 11997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Fcs,Unit 1 LIC-97-0149, Monthly Operating Rept for Aug 1997 for Fort Calhoun Station Unit 11997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Fort Calhoun Station Unit 1 LIC-97-0137, Monthly Operating Rept for Jul 1997 for Fort Calhoun Station1997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Fort Calhoun Station LIC-97-0115, Monthly Operating Rept for June 1997 for Fort Calhoun Station,Unit 11997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Fort Calhoun Station,Unit 1 ML20148L9291997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Fort Calhoun Station Unit 1 LIC-97-0081, Monthly Operating Rept for April 1997 for FCS1997-04-30030 April 1997 Monthly Operating Rept for April 1997 for FCS LIC-97-0054, Monthly Operating Rept for Mar 1997 for Fort Calhoun Station Unit 11997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Fort Calhoun Station Unit 1 ML20136G5911997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Fort Calhoun Station ML20134M4281997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Fort Calhoun Station Unit 1 LIC-97-0002, Monthly Operating Rept for Dec 1996 for Fort Calhoun Station Unit 11996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Fort Calhoun Station Unit 1 ML20134M4341996-12-31031 December 1996 Revised Monthly Operating Rept for Dec 1996 for Fort Calhoun Station Unit 1 LIC-96-0196, Monthly Operating Rept for Nov 1996 for Fort Calhoun Station Unit 11996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Fort Calhoun Station Unit 1 LIC-96-0174, Monthly Operating Rept for Oct 1996 for FCS Unit 11996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for FCS Unit 1 LIC-96-0152, Monthly Operating Rept for Sept 1996 for Fort Calhoun Station Unit 11996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Fort Calhoun Station Unit 1 LIC-96-0134, Monthly Operating Rept for Aug 1996 for Fort Calhoun Station1996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Fort Calhoun Station LIC-96-0113, Monthly Operating Rept for Jul 1996 for Fort Calhoun Station Unit 11996-07-31031 July 1996 Monthly Operating Rept for Jul 1996 for Fort Calhoun Station Unit 1 LIC-96-0096, Monthly Operating Rept for June 1996 for Fort Calhoun Station Unit 11996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Fort Calhoun Station Unit 1 LIC-96-0084, Monthly Operating Rept for May 1996 for Fort Calhoun Station Unit 11996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Fort Calhoun Station Unit 1 ML20117G0821996-04-30030 April 1996 Monthly Operating Rept for April 1996 for FCS ML20117G0841996-03-31031 March 1996 Revised MOR for March 1996 for FCS LIC-96-0036, Monthly Operating Rept for Feb 1996 for Calhoun Station,Unit 11996-02-29029 February 1996 Monthly Operating Rept for Feb 1996 for Calhoun Station,Unit 1 LIC-96-0016, Monthly Operating Rept for Jan 1996 for Fort Calhoun Station Unit 11996-01-31031 January 1996 Monthly Operating Rept for Jan 1996 for Fort Calhoun Station Unit 1 LIC-96-0004, Monthly Operating Rept for Dec 1995 for Fort Calhoun Station1995-12-31031 December 1995 Monthly Operating Rept for Dec 1995 for Fort Calhoun Station LIC-95-0233, Monthly Operating Rept for Nov 1995 for FCS Unit 11995-11-30030 November 1995 Monthly Operating Rept for Nov 1995 for FCS Unit 1 ML20093G7571995-09-30030 September 1995 Monthly Operating Rept for Sept 1995 for Fort Calhoun Station Unit 1 LIC-95-0172, Monthly Operating Rept for Aug 1995 for Fort Calhoun Station1995-08-31031 August 1995 Monthly Operating Rept for Aug 1995 for Fort Calhoun Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217B5401999-10-0606 October 1999 Safety Evaluation Supporting Amend 193 to License DPR-40 ML20217A9931999-09-30030 September 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data LIC-99-0096, Monthly Operating Rept for Sept 1999 for Fcs,Unit 1.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fcs,Unit 1.With ML20211J9321999-09-0202 September 1999 Safety Evaluation Concluding That Licensee Proposed Alternatives Provide Acceptable Level of Quality & Safety. Proposed Alternatives Authorized for Remainder of Third ten- Yr ISI Interval for Fort Calhoun Station,Unit 1 LIC-99-0084, Monthly Operating Rept for Aug 1999 for Fort Calhoun Station.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fort Calhoun Station.With ML20216E6431999-08-26026 August 1999 Rev 19 to TDB-VI, COLR for FCS Unit 1 ML20210R1961999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fcs,Unit 1 ML20210G2181999-07-27027 July 1999 Safety Evaluation Supporting Amend 192 to License DPR-40 ML20210D9951999-07-22022 July 1999 Safety Evaluation Supporting Amend 191 to License DPR-40 ML20216E6361999-07-21021 July 1999 Rev 18 to TDB-VI, COLR for FCS Unit 1 ML20210R2081999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Fcs,Unit 1 LIC-99-0065, Monthly Operating Rept for June 1999 for Fort Calhoun Station,Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fort Calhoun Station,Unit 1.With ML20196H8621999-06-30030 June 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data, June 1999 Rept ML20210P5461999-06-0808 June 1999 Rev 0,Vols 1-5 of Fort Calhoun Station 1999 Emergency Preparedness Exercise Manual, to Be Conducted on 990810. Pages 2-20 & 2-40 in Vol 2 & Page 4-1 in Vol 4 of Incoming Submittal Not Included ML20195B4581999-05-31031 May 1999 Rev 3 to CE NPSD-683, Development of RCS Pressure & Temp Limits Rept for Removal of P-T Limits & LTOP Requirements from Ts ML20207H7401999-05-31031 May 1999 Performance Indicators Rept for May 1999 LIC-99-0053, Monthly Operating Rept for May 1999 for Fort Calhoun Station,Unit 11999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fort Calhoun Station,Unit 1 ML20195B4521999-05-17017 May 1999 Technical Data Book TDB-IX, RCS Pressure - Temp Limits Rept (Ptlr) ML20206L4241999-05-10010 May 1999 Safety Evaluation Supporting Corrective Actions to Ensure That Valves Are Capable of Performing Intended Safety Functions & OPPD Adequately Addressed Requested Actions Discussed in GL 95-07 ML20206M2601999-05-0606 May 1999 SER Concluding That Licensee IPEEE Complete Re Info Requested by Suppl 4 to GL 88-20 & IPEEE Results Reasonable Given FCS Design,Operation & History LIC-99-0047, Monthly Operating Rept for Apr 1999 for Fort Calhoun Station Unit 1.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fort Calhoun Station Unit 1.With ML20195E8621999-04-30030 April 1999 Performance Indicators, for Apr 1999 ML20205Q5831999-04-15015 April 1999 Safety Evaluation Supporting Amend 190 to License DPR-40 ML20210J4331999-03-31031 March 1999 Changes,Tests, & Experiments Carried Out Without Prior Commission Approval for Period 981101-990331.With USAR Changes Other than Those Resulting from 10CFR50.59 ML20206G2641999-03-31031 March 1999 Performance Indicators Rept for Mar 1999 LIC-99-0034, Monthly Operating Rept for Mar 1999 for Fcs,Unit 1.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fcs,Unit 1.With ML20205J8181999-02-28028 February 1999 Performance Indicators, for Feb 1999 LIC-99-0025, Monthly Operating Rept for Feb 1999 for Fort Calhoun Station,Unit 1.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fort Calhoun Station,Unit 1.With ML20207F3291999-01-31031 January 1999 FCS Performance Indicators for Jan 1999 ML20203B0991998-12-31031 December 1998 Performance Indicators for Dec 1998 LIC-99-0026, 1998 Omaha Public Power District Annual Rept. with1998-12-31031 December 1998 1998 Omaha Public Power District Annual Rept. with LIC-99-0003, Monthly Operating Rept for Dec 1998 for Fort Calhoun Station.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fort Calhoun Station.With ML20198S3771998-12-31031 December 1998 Safety Evaluation Supporting Amend 189 to License DPR-40 ML20198S4831998-12-31031 December 1998 Safety Evaluation Supporting Amend 188 to License DPR-40 ML20196G2251998-12-18018 December 1998 Rev 2 to EA-FC-90-082, Potential Over-Pressurization of Containment Penetration Piping Following Main Steam Line Break in Containment ML20198M3141998-11-30030 November 1998 Performance Indicators Rept for Nov 1998 LIC-98-0172, Monthly Operating Rept for Nov 1998 for Fort Calhoun Station,Unit 1.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fort Calhoun Station,Unit 1.With LIC-98-0160, Special Rept:On 981113,MSL RM RM-064 Was Declared Inoperable Due to Leakage Past Isolation Valve HCV-922.Troubleshooting Has Indicated That Leakage Has Stopped & Cause of Leak Continues to Be Investigated1998-11-25025 November 1998 Special Rept:On 981113,MSL RM RM-064 Was Declared Inoperable Due to Leakage Past Isolation Valve HCV-922.Troubleshooting Has Indicated That Leakage Has Stopped & Cause of Leak Continues to Be Investigated ML20203B0721998-11-16016 November 1998 Rev 6 to HI-92828, Licensing Rept for Spent Fuel Storage Capacity Expansion ML20196E4981998-10-31031 October 1998 Performance Indicators Rept for Oct 1998 ML20196G2441998-10-31031 October 1998 Changes,Tests & Experiments Carried Out Without Prior Commission Approval. with USAR Changes Other than Those Resulting from 10CFR50.59 LIC-98-0154, Monthly Operating Rept for Oct 1998 for Fort Calhoun Station,Unit 1.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fort Calhoun Station,Unit 1.With ML20154M4881998-10-19019 October 1998 Safety Evaluation Supporting Amend 186 to License DPR-40 ML20154N2411998-10-19019 October 1998 Safety Evaluation Supporting Amend 187 to License DPR-40 LIC-98-0136, Monthly Operating Rept for Sept 1998 for Fort Calhoun Station,Unit 1.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fort Calhoun Station,Unit 1.With ML20155G4261998-09-30030 September 1998 Performance Indicators for Sept 1998 ML20154A1251998-08-31031 August 1998 Performance Indicators, Rept for Aug 1998 LIC-98-0122, Monthly Operating Rept for Aug 1998 for Fort Calhoun Station Unit 1.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fort Calhoun Station Unit 1.With ML20238F7231998-08-17017 August 1998 Owner'S Rept for Isis ML18066A2771998-08-13013 August 1998 Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency 1999-09-30
[Table view] |
Text
{{#Wiki_filter:. l Omaha Public PowerDistrict 444 South 16th Street Mall Omaha NE 68102-2247
, January 15, 1997 LIC-97-0002 l
U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station P1-137 Washington, D.C. 20555 1
Reference:
Docket No. 50-285 l
l 1
SUBJECT:
December 1996 Monthly Operating Report (MOR) 2 Enclosed please find the December 1996 MOR for Fort Calhoun Station (FCS)
Unit No.1 as required by FCS Technical Specification 5.9.1.
. If you should have any questions, please contact me.
1 Sincerely, A
i J. W. Tills Manager - Nuclear Licensing JWT/mle 1
Enclosures l c: Winston & Strawn L. J. Callan, NRC Regional Administrator, Region IV L. R. Wharton, NRC Project Manager '
W. C. Walker, NRC Senior Resident Inspector R. J. Simon, Westinghouse INP0 Records Center g qf l
-{p l
9701220426 961231 PDR ADOCK 05000285 R PDR i
45.5134 Employment with Equal Opportunity
2 LIC-97-0002 j Enclosure j Page 1 1
OMAHA PUBLIC POWER DISTRICT
- Fort Calhoun Station Unit No. 1
) .
j December 1996
- Monthly Operating Report i
i 1. OPERATIONS
SUMMARY
i l Following the 1996 refueling outage, from December 1 through December 6, l the Fort Calhoun Station (FCS) increased power to 97%. On December 6 at
- 0902 hours, power was reduced to 92% to complete Moderator Temperature
! Coefficient testing. This testing was completed on December 8 at 1109 hours.
1 j On December 8 at 1440 hours, power was reduced to 85% to facilitate l turbine control valve testing. The testing was satisfactorily completed j at 1800 hours and power ascension commenced.
i Unreliable emergency response facility ([tt ; computer operation caused i reactor power to be maintained between 95% and 98% between December 9 and December 16. This was done to maintain Peak Linear Heat Rate (PLHR) 4 at less than 90% of the limit (15.5 KW/ft as defined in Technical
{ Specification 2.10.4 and the Core Operating Limits Report). Technical Specification 2.10.4(c)i would have required power to be reduced to 80%
(rodded) or 85% (unrodded) if the ERF computer had failed while at a ~
! higher power level. Hardware problems were detected when the "C" host was running as the active computer. Circuit boards were reseated, power l was cycled and the "D" host was selected as the active computer. This i resolved the problem and on December 16 at 0910 hours, the ERF computer tested satisfactorily and reactor power was increased to 100%.
i On December 31 at 1100 hours FCS entered Abnormal Operating Procedure i A0P-05, Emergency Shutdown, due to a non-isolatable steam leak on a i drain line going to the condensor. At 1128 hours, a Notification Of i Unusual Event (NOUE) was declared per EAL 11.6, " Plant Conditions
{ Warrant Increased Awareness By Plant Staff Or Government Authorities."
- Appropriate NRC, state and local authorities were notified of the NOVE.
At 1330 hours, the turbine was manually tripped and the leak was isolated. The reactor remained critical at approximately 10% power during the repairs. At 1333 hours, A0P-05 was exited and at 1340 hours the NOVE was terminated. The leak was repaired and the turbine / generator was placed on line at 1821 hours. Dr. December 31 at 2400 hours, FCS was at 30% power waiting to clear steam generator chemistry holds prior to increasing power."
l LIC-97-0002 Enclosure Page 2
- 2. SAFETY VALVES OR PORV CHALLENGES OR FAILURES WHICH OCCURRED During the month of December, no power operated relief valves (PORV) or primary system safety valve challenges or failures occurred.
- 3. RESULTS OF LEAK RATE TESTS The reactor coolant system (RCS) leak rate was steady throughout the month continuing the trend of minimal RCS leakage following the 1996 refueling outage. December daily leak rates wefe constant at approximately 0.2 gpm except for increases caused by a charging pump packing leak. The leak rate returned to normal following completion of each charging pump packing replacement. No degrading trends were noted this month and the RCS continues to operate with minimal leakage.
- 4. CHANGES. TESTS AND EXPERIMENTS RE0VIRING NUCLEAR REGULATORY COMMISSION AUTHORIZATION PURSUANT TO 10CFR50.59 Amendment No. Description Amendment 179 Amendment 179 revises the Technical l Specifications to increase the amount of '
trisodium phosphate (TSP) dodecahydrate located in the containment sump storage baskets. l 1
- 5. SIGNIFICANT SAFETY RELATED MAINTENANCE FOR THE MONTH OF DECEMBER 1996 Replaced a 2 micron filter in CH-17A (Purification Filter "A")
with a 1 micron filter per ECN 94-568 Replaced Breaker MCC-3B1-E2R (Battery Room Fan VA-71A) per ECN 96-444 Removed gag on MS-282 (Main Steam Line "B" Relief Valve)
Repaired compressor on VA-46A (Control Room Air Conditioning Unit)
Replaced optics and master bulbs in YIT-6288A (Toxic Gas Monitor, Chlorine Gas)
Replaced 5 General Electric CR120A relays per ECN 95-374 1
1 i
LIC-97-0002 Enclosure Page 3 l
- 6. OPERATING DATA REPORT Attachment I l
- 7. AVERAGE DAILY UNIT POWER LEVEL
- Attachment II l 8. UNIT SHUTDOWNS AND POWER REDUCTIONS i
- Attachment III
- 9. REFUELING INFORMATION. FORT CALHOUN STATION UNIT N0. 1
- Attachment IV 4
- . . . - . . . ~.~ --..- - .-..-- -._- ---._.- -. . - - . - . - . . - _ - . . - . _
. . ATTACHMENT I OPERATING DATA REPORT l
i DOCKET NO. 50-285 UNIT FORT.CALHOUN STATION l DATE . JANUARY _07_,1997 COMPLETED BY M. L. EDWARDS OPERATING STATUS TELEPHONE 402-533-692i-
- l. Unit Name: FORT CALHOUN STATION
- 2. Reporting Period: DEf?3pER 1996 NOTES
- 3. Licensed Thermal Power (MWt): 1500
- 4. Nameplate Rating (Gross MWe): 50f ~
- 5. Design Elec. Rating (Net MWe): 475[
- 6. Max. Dep. Capacity (Gross MWe): 50_2
- 7. Max. Dep. Capacity (Net MWe): 478
- 8. If changes occur in Capacity Ratings (3 through 7) since last report, give reasons:
N/A
- 9. Power Level to which restricted, if any (Net MWe): N/A
- 10. Reasons for restrictions, if any:
N/A THIS MONTH YR-TO-DATE CUMULATIVE
- 11. Hours in Reporting Period........... 744.0 8784.0 203978.0
- 12. Number of Hours Reactor was Critical 744.0 6983.6 160691.6
- 13. Reactor Reserve Shutdown Hours...... .0 .0 1309.5
- 14. Hours Generator On-line............. T39.1 ~ 6887.3 158867.8
- 15. Unit Reserve Shutdown Hours......... .0 .0 .0
- 16. Gross Thermal Energy Generated (MWH) 1064592.8 9817571.7 212503880.0
- 17. Gross Elec. Energy Generated (MWH).. 3Ti226.0 3284507.9 70218233.1
- 18. Net Elec. Energy Generated (MWH).... 344367.7 3128752.5 66986121.3
- 19. Unit Service Factor................. 99.3 78.4 77.9
~
- 20. Unit Availability Factor............ 99.3~~ 78. 4 77.9
- 21. Unit Capacity Factor (using MDC Net) 96.8 74.5 70.9
- 22. Unit Capacity Factor (using DER Not) 96.8 74.5 69.3
- 23. Unit Forced Outage Rate............. .0 5.3 4.0
- 24. Shutdowns scheduled over next 6 months (type, date, and duration of each):
N/A
- 25. If shut down at end of report period, estimated date of startup:
- 26. Units in test status (prior to comm. oper.): Forecast Achieved i INITIAL CRITICALITY l
INITIAL ELECTRICITY N/A I
COMMERCIAL OPERATION _
ATTACHMENT II AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-285 l UNIT FORT.CALHOUN ST_ATION DATE JANUARY O_L 1997 COMPLETED BY M. L. EDWARDS TELEPHONE To2 ST3-69T9 MONTH DECEMBER 1996 l
DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL I (MWe-Net) (MWe-Net) 1 321 17 486 2 411 18 488 3 465 19 488 4 471 20 488 5 471 21 ___
488 6 458 22 488 1
7 444 23 488 8 435 24 488 9 468 25 488 l 10 470 26 488 11 470 27 488 12 470 28 488 13 472 29 488 14 475 30 488 15 476 31 261 16 481 INSTRUCTIONS On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
ATTACHMENT III DOCKET NO. 50-285 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Fort Calhoun St.
DATE January 9. 1997 COMPLETED BY M. L. Edwards TELEPHONE (402) 533-6929 REPORT MONTH December 1996 iNo? L Date) Type 1:. Duration 1 iReason .'- Method of.; L Licenseei lSystem ! 1 Component 1 5 Cause & Corrective ~
' .; Code51
)(Hours)) j Shutting : l Event r E. Code" : Action' to -
1Down2 . Report No.: i: Prevent Recurrence t
- Reactor' :
96-07 961231 F 4.9 A 1 N/A CC PIPEXX On December 31, 1996 at 1100 hours, a non-isolatable steam leak on a drain line going to the condenser developed. The turbine was manually tripped and the leak was isolated. The reactor remained critical at approximately 10% power 4
during the repairs. Following repairs, the generator was placed online at 1821 hours.
1 2 3 4 F: Forced Reason: -
Method: - Exhibit F - Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File (NUREG-0161)
D-Regulatory Restriction 4-Other (Explain)
E-Operator Training & License Examination F-Administrative 5 H-Other (Explain) Exhibit H - Same Source (9/77)
P S
'o -
Attachment IV Refueling Information Fort Calhoun Station Unit No.1 Report for the month ending: December 31. 1996
- 1. Scheduled date for next refueling shutdown.
- 2. Scheduled date for restart following refueling. May 2, 1998 j !
- 3. Will refueling or resumption of operations No thereafter require a technical specification change or other license amendment?
- a. If answer is yes, what, in general, will N/A these be?
- b. If answer is no, has the reload fuel No design and core configuration been l i
reviewed by your Plant Safety Review l Committee to determine whether any l unreviewed safety questions are l associated with the core reload? l
- c. If no such review has taken place, when Prior to May 2, 1998 ;
is it scheduled? l
- 4. Scheduled date(s) for submitting proposed No submittal required i licensing action and support information. , j
- 5. Important licensing considerations associated None i with refueling, e.g., new or different fuel ,
design or supplier, unreviewed design or l performance analysis methods, significant changes in fuel design, new operating ; ,
procedures. ! )
- 6. The number of fuel assemblies: i a) in the core 133 Assemblies b) in the spent fuel pool 662 Assemblies c) spent fuel pool storage capacity 1083 Assemblies i
- 7. The projected date of the last refueling that can be discharged to the spent fuel pool 2007 Outage assuming the present lic,ensed capacity.
Prepar by: _. 1 2a/ Date: //f/96