Informs That Sight Glasses on DG Fuel Oil Day Tanks Will Be Replaced by Sept 1996,based on Revised DG Outage Schedule
ML20115G582
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 07/10/1996
From: Tira Patterson
OMAHA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR 960710, LIC-96-0098, LIC-96-98, TAC-M69447, NUDOCS 9607190209
Download: ML20115G582 (1)


Text

(

i NBBB Omaha Public PowrDistrict 444 South 16th Street Mall Omaha NE68102-2247 July 10, 1996 .

LIC-96-0098 l l

l

\

U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station P1-137 Washington, D. C. 20555 l

l

References:

1. Dockat No. 50-285  !
2. Letter from OPPD (T. L. Patterson) to NRC (Document Control l l Desk) dated September 28, 1995 (LIC-95-0181) l

Subject:

Extension of Conmitment for Generic Implementation Procedure (GIP-2)

Outlier Resolution (Unresolved Safety Issue A-46, TAC No. 69447) i l

In Reference 2, the Omaha Public Power District (0 PPD) committed to replace the

sight glasses on the diesel generator (DG) fuel oil day tanks (F0-2-1 and F0-2-2) by June 1996 to resolve GIP-2 Outlier Item No. 20 regarding the vulnerability of the long sight glasses. In order to perform this work, the DGs are required to be out of service. Both DGs were previously scheduled to be out of service l earlier this year, however, due to OPPD's recent plant outages, the DG outages were deferred. The DG-1 and DG-2 outages are presently scheduled to occur on

! July 24 and August 7,1996, respectively. Based on this revised DG outage

! schedule, the sight glasses on the DG fuel oil day tanks will be replaced by September 1996.

If you should have any questions, please contact me.

Sincerely,

.l.A CA w h T. L. Patterson Division Manager Nuclear Operations TLP/dll c: Winston & Strawn L. J. Callan, NRC Regional Administrator, Region IV L. R. Wharton, NRC Project Manager W. C. Walker, NRC Senior Resident Inspector 9607190209 960710 PDR ADOCK 05000285 P PDR Employment with Equal Opportunity