JPN-89-037, Forwards Application for Amend to License DPR-59,revising Tech Specs to Clarify That 30-day Allowable out-of-svc Time Applies to RHR Svc Water Sys Only & Not to RHR Pumps or Spray Loop

From kanterella
Jump to navigation Jump to search
Forwards Application for Amend to License DPR-59,revising Tech Specs to Clarify That 30-day Allowable out-of-svc Time Applies to RHR Svc Water Sys Only & Not to RHR Pumps or Spray Loop
ML20247P714
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/31/1989
From: Brons J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20247P722 List:
References
JPN-89-037, JPN-89-37, NUDOCS 8906060230
Download: ML20247P714 (2)


Text

- - - - - - . _ - . . __ - . - . _ _ _ - - - _ _ -

223 Main Street WNte Plams, New York 10601 I I 914 681 0240 y'

  1. > NewYorkPower *

- c.o oe.

Executive Vice President nyg U3= Nuclem Genera $on May 31, 1989 JPN-89-037 U.S. Nuclear Regulatory Commission

-ATTN: Document Control Desk Mail Station Pl-137 Washington, DC 20555

SUBJECT:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Proposed Change to the Technical Specifications Regarding Clarification of RHR Containment Cooling Mode Requirements (J PTS-8 4 -0 0 6 )

REFERENCE:

1. NYPA letter, W. Fernandez to NRC, dated March 20, 1989, (JAFP-89-0214), responds to Inspection Report 50-333/88-29.

Dear Sir:

This application for an amendment to the James A.

FitzPatrick Technical Specifications proposes changes to Technical Specifications 3.5.B, 4.5.B, and Basis 3.5 on pages 115a, 116, and 127. These changes clarify that the 30 day allowable out-of-service time is for the RHR Service Water System only and does not apply to the RHR pumps or spray loop. Additional changes improve the structure and readability of the Technical Specifications.

These changes are purely administrative in nature.

They clarify the intent of the Technical Specifications, improve the consistency within the Technical Specifications, and assure a more conservative interpretation of the specification's action times.

The changes do not involve modification of any existing equipment, systems, or components; nor do they relax any administrative controls or revise limitations imposed on existing plant equipment.

This application for an amendment partially resolves NRC Open Item 88-29-01 and is one of the Technical j I

Specification corrections described in Reference 1.

Enclosed for filing is the signed original of a j document entitled " Application for Amendment to Operating ]

License," with Attachments I and II thereto, comprising  ;

a statement of the proposed changes to the Technical l Specifications and the associated Safety Evaluation. l l

M 8906060230.890531

{ PDR ADOCK 05000333 i

\

P PDC

. _ _ _ . .__--_ -___.- __ A

. .. l In accordance with 10 CFR 50.91, a copy of this application and the associated attachments are being provided to the designated New York State official. .

Should you or your staff have any questions regarding the proposed changes, please contact Mr. J. A. Gray, Jr. of my staff.  ;

Very truly yours, d

,4En@C.lL-g Brons Executive Vice President Nuclear Generation J

cc: U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. David E. LaBarge Project Directorate I-1 Division of Reactor Projects - I/II U.S. Nuclear Regulatory Commission Mail Stop 14 B2 Washington, DC 20555 Ms. Donna Ross New York State Energy Office 2 Empire State Plaza 16th Floor Albany, NY 12223 {