JAFP-82-0577, Forwards Results of Visual & Functional Tests for Mechanical Snubbers,In Response to IE Bulletin 81-01, Surveillance of Mechanical Snubbers. Visual Exam & Functional Test Results Satisfactory

From kanterella
(Redirected from JAFP-82-0577)
Jump to navigation Jump to search
Forwards Results of Visual & Functional Tests for Mechanical Snubbers,In Response to IE Bulletin 81-01, Surveillance of Mechanical Snubbers. Visual Exam & Functional Test Results Satisfactory
ML20079F763
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/28/1982
From: Corbin McNeil
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Haynes R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20079F765 List:
References
REF-SSINS-6820 IEB-81-01, IEB-81-1, JAFP-82-0577, JAFP-82-577, NUDOCS 8206080205
Download: ML20079F763 (3)


Text

_ _ _ _ _ _ - _ - _ _ - _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ .

C s n POWER AUTHORITY OF THE STATE OF NEW YORK g/

' f 3

JAMES A. FarzPATRicK NUCLEAR power PLANT ConBIN A.McNEILL JH.

Rnident Manager S P,0. Box 41 Lycoming, New York 13093 315-342 3840 May 28, 1982 SERIAL: JAFP 82-0577 Ronald C. Ilaynes , Director United States Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Subject:

I.E. Bulletin 81-01 " Surveillance of Mechanical Snubbers"

References:

(1) I.E. Bulletin No. 81-01 " Surveillance of Mechanical Snubbers" (2) PASNY Letter PASNY 81-0232 dated March 11, 1981 from R. J. Pasternak (PASNY) to Boyce H. Grier (NRC),

subject "I.E. Bulletin No. 81-01 Surveillance of Mechanical Snubbers" (3) PASNY Letter JPN-81-51 dated July 13, 1981 from J. P. Bayne to Director of Nuclear Reactor Regulation, subj ect

" James A. FitzPatrick Nuclear Power Plant, Docket No. 50-333, Proposed Change to the Technical Specifications Related to Snubber Surveillance"

Enclosures:

(1) Summary of Visual Exam Results (2) Functional Test Results

Dear Mr. Ilaynes:

As required by reference (1) and committed to by reference (2), a visual and functional test of safety-related mechanical snubbers was performed during Fit:: Patrick's recent refueling outage in accordance with the proposed technical specifications submitted by reference (3). Enclosure (1) summarizes the results of the satisfactory visual exams and enclosure (2) are copics of the satisfactory functional test results performed by Wyle Laboratories.

8206080205 820529 PDR ADOCK 05000333 G pyg $&

1

'O The list of mechanical snubbers in enclosure (1) differs slightly from the table provided in reference (3) due to the addition of one additional unit and a renumbering of existing units for clarity. A charige to reference (3) to update the table of mechanical snubbers will be submitted by August 1, 1982.

Very truly yours, CAM:WF:nyw Corbin A. McNeill, Jr.

Enclosures Resident Manager cc: USNRC, Director, Office of Inspection and Enforcement Resident NRC Inspector Internal Distribution J. Glauser, Pacific Scientific

ENCLOSURE 1

SUMMARY

OF VISUAL EXAM RESULTS l

MECIIANICAL SNUBBER OVERALL VISUAL IN PLACE CLEVIS PIN TESTED EXAM STROKE TEST 6 ROD BUSHING 10-7B-MS-3 SAT. SAT. SAT.

10-9A-MS-40A SAT. SAT. SAT.

10-13A-MS-112 SAT. SAT. SAT.

10-15B-MS-124A SAT. SAT. SAT.

10-15B-MS-124B SAT. SAT. SAT.

10-15B-MS-125A SAT. SAT. SAT.

10-15B-MS-12 5 B SAT. SAT. SAT.

10-3B-MS-153 SAT. SAT. SAT.

10-35-MS-221A SAT. SAT. SAT.

10-9A-MS-254 SAT. SAT. SAT.

10-9B-MS-286 SAT. SAT. SAT.

10-15A-MS-304 SAT. SAT. SAT.

I 10-15A-MS-303 SAT. SAT. SAT.

10-15A-MS-307 SAT. SAT. SAT.

10-15A-MS-308 SAT. SAT. SAT.

10-15B-MS-119A SAT. SAT. SAT.

I l

- -