IR 05000458/2025001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 050004582025001
ML25119A328
Person / Time
Site: River Bend Entergy icon.png
Issue date: 05/06/2025
From: Douglas Dodson
NRC/RGN-IV/DORS/PBC
To: Hansett P
Entergy Operations
Dodson D
References
IR 2025001
Download: ML25119A328 (1)


Text

May 06, 2025

SUBJECT:

RIVER BEND STATION - INTEGRATED INSPECTION REPORT 05000458/2025001

Dear Phil Hansett:

On March 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at River Bend Station. On April 10, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation that was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation consistent with section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at River Bend Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Douglas E. Dodson II, Chief Reactor Projects Branch C Division of Operating Reactor Safety Docket No. 05000458 License No. NPF-47

Enclosure:

As stated

Inspection Report

Docket Number:

05000458

License Number:

NPF-47

Report Number:

05000458/2025001

Enterprise Identifier:

I-2025-001-0006

Licensee:

Entergy Operations, Inc.

Facility:

River Bend Station

Location:

St. Francisville, LA

Inspection Dates:

January 1, 2025, to March 31, 2025

Inspectors:

B. Baca, Health Physicist

J. Mejia, Reactor Inspector

J. O'Donnell, Senior Health Physicist

E. Powell, Resident Inspector

C. Wynar, Senior Resident Inspector

Approved By:

Douglas E. Dodson, II, Chief

Reactor Projects Branch C

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at River Bend Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71111.08G.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

River Bend Station began the inspection period at 100 percent rated thermal power. On January 24, 2025, the station reduced power to approximately 82 percent for a planned control rod pattern adjustment. On January 25, 2025, power was restored to 100 percent. Power remained at 100 percent until February 11, 2025, when the licensee shut down the plant by placing the mode switch in shut down for a planned refueling and maintenance outage. The plant remained shut down and at 0 percent power until March 30, 2025, when the mode switch was taken to startup. The station ended the inspection period in the middle of the startup procedure at approximately 3 percent rated thermal power.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of subfreezing temperatures and snow for the following systems:
  • instrument air system; service air system; condensate storage, makeup and transfer system; and makeup water system on January 22, 2025

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the stations overall preparations to protect risk-significant systems from impending severe thunderstorms and during a tornado watch on March 14, 2025.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)high pressure core spray system on March 13, 2025 (2)low pressure core spray system on March 13, 2025 (3)reactor core isolation cooling system on March 31, 2025 (4)low pressure coolant injection B system on March 31, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)hydraulic control unit area west, fire area RC-4/Z-3, on February 25, 2025 (2)shield building access area, fire area AB-15/Z-2, on March 6, 2025 (3)annulus, fire area RC-6, on March 12, 2025 (4)recirculation pump area, fire area RDW-1, on March 19, 2025 (5)fuel storage pool area, fire area FB-1/Z-1, on March 28, 2025

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire brigade drill on January 15, 2025.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) spent fuel pool cooling heat exchanger SFC-E1A on March 31, 2025

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

The inspectors evaluated boiling water reactor nondestructive testing by reviewing the following activities in Unit 1 during refueling outage 23 from February 17 to March 13, 2025:

(1)

Ultrasonic Examinations i.

low pressure core spray, CSH-027A-FW001, valve to pipe ii.

high pressure core spray, CSL-042A-FW002, pipe to valve iii.

reactor pressure vessel, B13-D001-N07-1, nozzle to vessel iv.

reactor pressure vessel, B13-D001-N07-0, nozzle inner radius v.

reactor pressure vessel, B13-D001-N08-1, nozzle to vessel vi.

reactor pressure vessel, B13-D001-N08-0, nozzle inner radius vii.

reactor pressure vessel, B13-D001-S-1-64, studs 1-64 b.

Penetrant Dye Examinations i.

standby liquid control, SLS-037D-FW002, elbow to pipe ii.

standby liquid control, SLS-037D-FW003A, pipe to elbow iii.

standby liquid control, SLS-037D-FW004, elbow to pipe c.

Visual Examinations i.

main steam, MSS-PSA-3046-A1, pipe support-anchor ii.

main steam, MSS-PSSH-3044-A1, pipe support-spring iii.

reactor pressure vessel, B13-D001-NT-1-64, nuts 1-64 iv.

reactor pressure vessel, B13-D001-WA-1-64, washers 1-64 v.

containment, DS-001, dome section vi.

containment, DS-003, dome section vii.

containment, WS-04, inside wall section viii.

containment, WS-07, inside wall section ix.

containment, WS-13, inside wall section

  • There were no relevant indications accepted for continued service.
  • Welding Activities a.

work order (WO) 54243150-01, -03, mechanical piping, RCS-750-119, FW-006AF, FW-015F, SW-013F, SW-014F b.

WO 589506-50, nozzle, G36-RYV081A, XI-FW002A

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during shutdown for refueling outage 23 on February 10, 2025.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated risk during unplanned 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> limiting condition for operation on January 28, 2025 (2)elevated risk during division 3 battery discharge test on January 31, 2025 (3)elevated risk during standby service water A nozzle inspection on February 6, 2025 (4)elevated risk during division 1 shutdown protected equipment and residual heat removal A shutdown cooling on February 11, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)control building chiller A trip on January 13, 2025 (condition report (CR)-RBS-2025-

===00140) (2)jet pump 6 damage/repair on March 18, 2025 (CR-RBS-2025-01075)

(3)service water return header B isolation valve (SWP-MOV96B) failed to fully close on March 25, 2025 (CR-RBS-2025-00585)

(4)emergency diesel generator surveillance 3.8.1.18 and 3.8.1.11 on March 28, 2025 (CR-RBS-2025-01409)

(5)leaking main steam isolation valve on March 31, 2025 (CR-RBS-2025-00802, CR-RBS-2025-00818, and CR-RBS-2025-00819)

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated Refueling Outage 23 activities from February 11, 2025, to March 31, 2025. The inspectors completed inspection procedure Sections 03.01.a, 03.01.b, and 03.01.c.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01)===

(1) WO 54020454, main steam isolation valve operability testing, on March 2, 2025
(2) WO 54249451, standby liquid control system Amphenol cable replacement, on March 4, 2025
(3) WO 00551736, reactor core isolation cooling trip throttle repair, on March 13, 2025
(4) WO 54250336, jet pump 6 repair, on March 14, 2025
(5) WO 00555639, control building chiller A controller repair for hot gas bypass valve, on March 31, 2025
(6) WO 54089055, low pressure core spray minimum flow check valve CSL-V10 repair, on March 31, 2025

Surveillance Testing (IP Section 03.01) (4 Samples)

(1) STP-508-4244, RPS/EOC-RPT Turbine First Stage Pressure Channel Calibration and Logic System Functional Test, Revision 015 on March 4, 2025
(2) STP-107-3806, Feedwater Penetration KJB-Z3A Valve Leak Rate Test, Revision 018 on March 12, 2025
(3) STP-309-0601, Division I ECCS Test, Revision 059 on March 18, 2025
(4) STP-051-4269, ATWS/Recirc Pump Trip Reactor Vessel Pressure High Channel Calibration and Logic System Functional Test, Revision 302 on March 31, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) STP-204-6303, Div I RHR Quarterly Valve Operability Test, Revision 22 on March 12, 2025

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1) WO 00596880, main steam isolation valve B21-AOVF022B, on March 25,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1)surveys of potentially contaminated material leaving the radiologically controlled area (RCA)

(2)workers exiting the RCA at the T Tunnel 95' RCA exit during a refueling outage

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1)work under vessel installing local range power monitors using radiation work permit (RWP) 2025-1917 (2)removal of safety relief valve B21-RVF041D using RWP 2025-1912 (3)dry run of control rod drive mechanism removal under vessel using RWP 2025-1917 High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (5 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1)

(VHRA) reactor building 131' - inclined fuel transfer system (IFTS) blind flange area gate (2)

(VHRA) fuel building 131' - mid support room gate (3)

(HRA) auxiliary building 141' - main steam tunnel (floor plugs removed)

(4)

(HRA) auxiliary building 95' - reactor water cleanup pump room door (5)

(HRA) radwaste building 90' - six-way valve room Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (2 Samples)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1)control room fresh air system (2)technical support center engineered safety feature ventilation

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1)refuel floor reactor vessel stud washer cleaning station with high efficiency particulate air (HEPA) filtration

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) January 1 through December 31, 2024 IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
(1) January 1 through December 31, 2024

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) January 1 through December 31, 2024

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) January 1 through December 31, 2024 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) January 1 through December 31, 2024

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)division 3 battery room temperature (2)high main steam tunnel temperatures resulting from incorrect fan blade pitch on main steam tunnel unit cooler HVR-UC8 (3)reactor core isolation cooling single failure criteria

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71111.08G This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

Violation: Title 10 CFR 50, Appendix B, Criterion XVII, Quality Assurance Records, requires that sufficient records shall be maintained to furnish evidence of activities affecting quality.

The records, in part, shall include the results of the inspections. Records shall be identifiable and retrievable.

Contrary to the above, from March 21, 2023, to February 18, 2025, the licensee failed to maintain records to furnish evidence of activities affecting quality, in that, results of an inspection were not maintained in records that were identifiable and retrievable. Specifically, the licensee discovered a copy of a field pressure test visual examination report with unidentifiable results in the observed conditions section that was signed by the examiner.

Another copy of the report was found in the database with the observed conditions but was not signed by the examiner and unable to be signed by the examiner after discovery. The original field report was not found. The report was from refueling outage 22, dated March 21, 2023, and was not processed within the 30-day requirement of licensee procedure EN-AD-103, Document Control and Records Management Program, Revision 28.

Significance/Severity: Green. The inspectors assessed the significance of the finding using IMC 0609, Appendix A, The Significance Determination Process (SDP) for Findings At Power. The inspectors screened the finding using Table 2 of IMC 0609, Attachment 4, Initial Characterization of Findings. The Barrier Integrity Cornerstone Note directs all other reactor coolant system boundary issues to be considered under the Initiating Events Cornerstone.

IMC 0609, Attachment 4, Table 3, routes the finding to the IMC 0609, Appendix A, Exhibit 1, Loss of Coolant Accident (LOCA) Initiators questions. Since the finding:

(1) could not result in exceeding the reactor coolant system leak rate for a small LOCA and
(2) could not have likely affected other systems used to mitigate a LOCA, the finding screens as Green. The finding represents the potential of missed exams and records within the pressure test program.

Corrective Action References: CR-RBS-2025-01712

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On February 25, 2025, the inspectors presented the occupational radiation safety inspection results to Brad Wertz, General Manager of Plant Operations, and other members of the licensee staff.
  • On March 13, 2025, the inspectors presented the inservice inspection activities results to Phil Hansett, Site Vice President, and other members of the licensee staff.
  • On April 10, 2025, the inspectors presented the integrated inspection results to Phil Hansett, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

AOP-0029

Severe Weather Operation

71111.04

Procedures

SOP-0031

Residual Heat Removal SYS 204

348

Procedures

SOP-0035

Reactor Core Isolation Cooling System (SYS #209)

R-STM-0203

High Pressure Core Spray

71111.04

Miscellaneous

R-STM-0205

Low Pressure Core Spray

71111.05

Calculations

G13.18.12.2-022

River Bend Station - Combustible Loading

010

71111.05

Procedures

ADM-0073

Temporary Services and Equipment

309

71111.05

Procedures

EN-DC-161

Control of Combustibles

71111.05

Procedures

RB-095-001

Recirculation Pump Area Fire Area RDW-1

71111.05

Procedures

RB-114-005

HCU Area West RC-4/Z-3

71111.08G

Corrective Action

Documents

CR-RBS-

2012-03147, 2012-03680, 2023-01603, 2023-01815, 2023-

01830, 2023-02153, 2023-02706, 2023-03001, 2023-03300,

23-03414, 2023-03584, 2023-04243, 2023-04246, 2023-

247, 2023-04618, 2023-06236, 2024-00646, 2024-00646,

24-00677, 2024-03183, 2024-05802, 2024-05803, 2025-

00650, 2025-00714, 2025-00808, 2025-00938, 2025-00970,

25-01015, 2025-01018, 2025-01019, 2025-01021, 2025-

01052

71111.08G

Corrective Action

Documents

Resulting from

Inspection

CR-RBS-

25-01024, 2025-01069, 2025-01071, 2025-01665, 2025-

01712, 2025-01713, 2025-01714

71111.08G

Drawings

1-RCS-119

71111.08G

Drawings

1-WCS-56-CD-A

71111.08G

Drawings

PID-25-01C

Engineering P&I Diagram System 053 Reactor Recirculation

71111.08G

Drawings

RBS-ISI-022

Seam Joint ID, Nozzle Location & Weld Map

71111.08G

Miscellaneous

CEP-PT-001

ASME Section XI Pressure Test (PT) Program

313

71111.08G

Miscellaneous

SEP-ISI-RBS-001

Program Section for ASME Section XI, Division 1 RBS

Inservice Inspection Program

71111.08G

Miscellaneous

SEP-PT-001

River Bend Station Inservice Inspection Pressure Testing

(PT) Program Section

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08G

NDE Reports

ISI-VT-08-040

Visual Examination, Component Support-RPV Skirt

2/10/2008

71111.08G

NDE Reports

ISI-VT-17-052

Visual Examination, RPV Skirt

2/16/2017

71111.08G

NDE Reports

RDC-201

JP05 WD-1, Jet Pump Wedge & Wedge Bearing Surface

2/16/2025

71111.08G

NDE Reports

RDC-205

JP02 WD-1, Jet Pump Wedge & Wedge Bearing Surface

2/19/2025

71111.08G

Procedures

CEP-CII-003

Visual Examinations of Class MC Components

309

71111.08G

Procedures

CEP-NDE-0400

Ultrasonic Examination

71111.08G

Procedures

CEP-NDE-0640

Non-Section XI Liquid Penetrant Examination (PT)

71111.08G

Procedures

CEP-NDE-0641

Liquid Penetrant Examination (PT) for ASME Section XI

71111.08G

Procedures

CEP-NDE-0901

VT-1 Examination

71111.08G

Procedures

CEP-NDE-0902

VT-2 Examination

71111.08G

Procedures

CEP-NDE-0903

VT-3 Examination

71111.08G

Procedures

CEP-WP-002

Welding Procedure Specification

71111.08G

Procedures

CEP-WP-004

Control and Documentation of Welding Activities

71111.08G

Procedures

CEP-WP-GWS-1

General Welding Standard ASME/ANSI

71111.08G

Self-Assessments

LO-RBS-2024-

00112

Pre-NRC ISI Activities Self-Assessment Report

11/25/2024

71111.08G

Work Orders

WO- 537913, 593349, 593991. 54116153, 54120602, 54120606

71111.13

Corrective Action

Documents

CR-RBS-

25-00343

71111.13

Procedures

EN-OP-119

Protected Equipment Postings

019

71111.13

Procedures

STP-203-1702

E22-S001A Bat Performance Discharge Test

26

71111.13

Work Order

WO 53005728

71111.15

Engineering

Changes

EC-0054250338

RPV Jet Pump #6 Modification (B-13-PD006-JP6) Main

Wedge Replacement

71111.15

Procedures

EN-OP-104

Operability Determination Process

71111.15

Work Order

WO 250336

71111.20

Miscellaneous

Out Risk Assessment Team RF-23 Outage Report

71111.24

Drawings

ESK-11EJS02

480V SWGR Standby Bus UNDV Trip Relays

71111.24

Engineering

Changes

EC-0054251412

HVK-CHL1C ECCS Retest

71111.24

Procedures

EN-LI-100

Process Applicability Determination

71124.01

ALARA Plans

RWP 2023-1609

23-1609 Close Out package

06/14/2023

71124.01

ALARA Plans

RWP 2023-1615

RWP Termination and Post-Job ALARA Review - RWP 2023-

07/17/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1615

71124.01

ALARA Plans

RWP 2023-1626

23-1626 Close Out package

07/12/2023

71124.01

ALARA Plans

RWP 2023-1700

23-1700 Close Out package

06/06/2023

71124.01

ALARA Plans

RWP 2023-1727

23-1727 Close Out package

08/14/2023

71124.01

ALARA Plans

RWP 2023-1750

23-1750 Close Out package

04/25/2023

71124.01

ALARA Plans

RWP 2023-1910

23-1910 Close Out package

05/31/2023

71124.01

ALARA Plans

RWP 2023-1912

23-1912 Close Out package

05/31/2023

71124.01

ALARA Plans

RWP 2023-1932

23-1932 Close Out package

06/06/2023

71124.01

ALARA Plans

RWP 2023-1952

23-1952 Close Out package

06/07/2023

71124.01

ALARA Plans

RWP 2023-1953

23-1953 Close Out package

06/08/2023

71124.01

ALARA Plans

RWP 2025-1736

ALARA Plan

2/10/2025

71124.01

ALARA Plans

RWP 2025-1917

ALARA Plan

2/10/2025

71124.01

Corrective Action

Documents

CR-RBS-

24-02464, 2024-02858, 2024-03755, 2024-03982, 2024-

206, 2024-04217, 2024-04960, 2024-05000, 2024-05544,

24-05751, 2024-05909, 2024-05954, 2024-06181, 2024-

06307, 2025-00208, 2025-00321, 2025-00451, 2025-00672,

25-00721, 2025-00733, 2025-00777, 2025-00798, 2025-

00815, 2025-00853, 2025-00881

71124.01

Corrective Action

Documents

Resulting from

Inspection

CR-RBS-

25-00895

71124.01

Miscellaneous

RWP 2023-1609 Dose Dump Report

71124.01

Miscellaneous

RWP 2023-1700 Dose Dump Report

71124.01

Miscellaneous

RWP 2023-1912 Dose Dump Report

71124.01

Miscellaneous

RWP 2023-1952 Dose Dump Report

71124.01

Miscellaneous

RWP 2023-1953 Dose Dump Report

71124.01

Miscellaneous

RWP 2023-1910 Dose Dump Report

71124.01

Miscellaneous

RBS-RPT-24-002

R0

Alpha / Plant Characterization Data

01/31/2024

71124.01

Procedures

EN-RP-100

Radiation Worker Expectations

71124.01

Procedures

EN-RP-101

Access Control for Radiologically Controlled Areas

71124.01

Procedures

EN-RP-105

Radiological Work Permits

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.01

Procedures

EN-RP-106-01

Radiological Survey Guidelines

71124.01

Procedures

EN-RP-108

Radiation Protection Posting

71124.01

Procedures

EN-RP-110-03

Collective Radiation Exposure (CRE) Reduction Guidelines

71124.01

Procedures

EN-RP-110-04

Radiation Protection Risk Assessment Process

71124.01

Procedures

EN-RP-110-06

Outage Dose Estimating and Tracking

71124.01

Procedures

EN-RP-121

Radioactive Material Control

71124.01

Procedures

EN-RP-123

Radiological Controls for Highly Radioactive Objects

71124.01

Procedures

EN-RP-131

Air Sampling

71124.01

Procedures

EN-RP-141

Job Coverage

71124.01

Procedures

EN-RP-210

Area Monitoring Program

71124.01

Procedures

EN-RP141-01

Job Coverage using Remote Monitoring Technology

71124.01

Radiation

Surveys

7500 RB 186

Refuel Floor blank map showing location of AMS-4s for CR-

RBS-2025-00721

71124.01

Radiation

Surveys

RBS-2023-

Under-vessel radiological surveys from the previous outage:

214, 00303, 00333, 00347, 00386, 00463, 00467, 00530,

00758, 0070, 00781, 00812, 00813, 00834, 00920, 01018,

01169, 01170, 01172, 01214, 01263

71124.01

Radiation

Surveys

RBS-2501-00105

Fuel Building 70' elevation - verification survey of the FB 79'

for unanticipated dose rate alarm

01/14/2025

71124.01

Radiation

Surveys

RBS-2502-00214

Reactor Building 186' - Reactor Cavity Drywell Head

2/11/2025

71124.01

Radiation

Surveys

RBS-2502-00468

DW access 95' equipment hatch

2/15/2025

71124.01

Radiation

Surveys

RBS-2502-00658

Drywell 82' Subpile Room

2/18/2025

71124.01

Radiation

Surveys

RBS-AS-021125-

0105

Particulate Air Sample, Reactor Building 131', Grab Sample

2/11/2025

71124.01

Radiation

Surveys

RBS-AS-021225-

0134

Particulate Air Sample, Reactor Building 186', Grab Sample

2/12/2025

71124.01

Radiation

Surveys

RBS-AS-021225-

0148

Particulate Air Sample, Reactor Building 186', Grab Sample

2/12/2025

71124.01

Radiation

Surveys

RBS-AS-021325-

0160

Particulate Air Sample, Reactor Building 186', Grab Sample

2/13/2025

71124.01

Radiation

RBS-AS-021325-

Particulate Air Sample, Reactor Building 186', Grab Sample

2/13/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Surveys

0161

71124.01

Radiation

Surveys

RBS-AS-021725-

249

Particulate Air Sample, Drywell 82', Grab Sample

2/17/2025

71124.01

Radiation Work

Permits (RWPs)

25-1736

RF 23 Risk Based - Shielding Installation/Removal Activities

(All Buildings)

71124.01

Radiation Work

Permits (RWPs)

25-1900

RF 23 Risk Based - Drywell Initial Entry Activities (Includes

DW Unidentified Leak Investigation & VHRA Down-posting

o/s DW)

71124.01

Radiation Work

Permits (RWPs)

25-1912

Safety Relief Valve (SRV) Activities

71124.01

Radiation Work

Permits (RWPs)

25-1917

RF 23 Risk Based - Under-Vessel Activities. (including High

Risk Packaging for Shipping)

71124.01

Radiation Work

Permits (RWPs)

25-1918

RF23 Risk Based - NI Cable Replacement

71124.01

Radiation Work

Permits (RWPs)

25-1999

RF23 Medium / High Risk - Activities in the Drywell -

Including Insulation Removal and Decon Impacted by Leaks

71124.01

Self-Assessments

LO-RBS-2024-

00058

IP 71124.01 - Radiological Hazard Assessment and

Exposure Control

11/07/2024

71124.03

Corrective Action

Documents

CR-RBS-

23-07410, 2024-00751

71124.03

Corrective Action

Documents

Resulting from

Inspection

CR-RBS-

25-00892, 2025-00896

71124.03

Miscellaneous

Posi3 USB Test Results Serial Numbers: AMAH196524,

AMAH196535, AMAH196537, AMAH196543, AMAH196548,

AMAH196553, AMAH196563, AMAG199928, AMAG199931,

AMAG204066, and AMAG204085

71124.03

Miscellaneous

Inspection and Maintenance of Respiratory Protection

Equipment for the month of April 2024

71124.03

Miscellaneous

Inspection and Maintenance of Respiratory Protection

Equipment for the month of June 2024

71124.03

Miscellaneous

Inspection and Maintenance of Respiratory Protection

Equipment for the month of September 2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.03

Miscellaneous

Inspection and Maintenance of Respiratory Protection

Equipment for the month of October 2024

71124.03

Miscellaneous

240305036-00

Laboratory Report Compressed Air/Gas Quality Testing:

Bauer UNICUS II 030424

03/06/2024

71124.03

Miscellaneous

240305037-01

Laboratory Report Compressed Air/Gas Quality Testing:

Electric Service Air System SAS-V1416

03/06/2024

71124.03

Miscellaneous

240618118-01

Laboratory Report Compressed Air/Gas Quality Testing:

Electric Service Air System SAS-V1416

06/19/2024

71124.03

Miscellaneous

240618119-00

Laboratory Report Compressed Air/Gas Quality Testing:

Bauer UNICUS II 030424

06/19/2024

71124.03

Miscellaneous

240911011-01

Laboratory Report Compressed Air/Gas Quality Testing:

Electric Service Air System SAS-V1416

09/12/2024

71124.03

Miscellaneous

240911028-00

Laboratory Report Compressed Air/Gas Quality Testing:

Bauer UNICUS II 030424

09/12/2024

71124.03

Miscellaneous

FCB T-GET-

RESP

Generic Respiratory Protection Training

71124.03

Miscellaneous

FPF-GET-RPT

Respiratory Protection Practical Factor Guide

71124.03

Procedures

EN-RP-131

Air Sampling

71124.03

Procedures

EN-RP-501

Respiratory Protection Program

71124.03

Procedures

EN-RP-502

Inspection and Maintenance of Respiratory Protection

Equipment

71124.03

Procedures

EN-RP-502-01

FireHawk M7 SCBA

71124.03

Procedures

EN-RP-502-02

Flow Testing MSA Breathing Apparatus

71124.03

Procedures

EN-RP-502-03

AirHawk II SCBA

71124.03

Procedures

EN-RP-503

Selection, Issue and Use of Respiratory Protection

Equipment

71124.03

Procedures

EN-RP-504

Breathing Air

71124.03

Procedures

EN-RP-504-01

UNICUS II Operating Instructions

71124.03

Procedures

EN-RP-505

PortaCount Respirator Fit Testing

71124.03

Radiation Work

Permits (RWPs)

251917

RF 23 Risk Based - Undervessel Activities (including High

Risk Packaging for Shipping)

71124.03

Self-Assessments

LO-RBS-2024-

00058

Focused Self-Assessment/Formal Benchmark Report:

RIVER BEND - IP 71124.01 - Radiological Hazard

Assessment and Exposure Controls, IP 71124.03 - In-Plant

11/07/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Airborne Radioactivity Control and Mitigation, IP 71151 - PI

Verification

71124.03

Self-Assessments

LO-RBS-2024-

00078-00001

21 - 2023 Triennial Respiratory Program Report, Radiation

Protection - River Bend Station

2/17/2024

71124.03

Self-Assessments

LO-RLO-2023-

00043

Radiation Protection High Efficiency Particulate Air (HEPA)

Program - River Bend

71151

Miscellaneous

RBG-48276

River Bend Nuclear Station Annual Radioactive Effluent

Release Report 2023

04/16/2024

71151

Work Orders

Work Order (WO)

RPP-0102: Dose Calculation from Gaseous Effluents -

54101888-01, 54113677-01, 54125667-01, 54136605-01,

54146423-01, 54154660-01, 54165481-01, 54178412-01,

54189653-01, 54204234-01, 54214897-01, 54224771-01

71151

Work Orders

Work Order (WO)

RPP-0097: Manual Method of Determining Cumulative Dose

Due to Liquid Effluents - 54101934-01, 54115416-01,

54125701-01, 54136661-01, 54146236-01, 54154702-01,

54165523-01, 54178435-01, 54189680-01, 54204271-01,

214947-01, 54224821-01

71152A

Corrective Action

Documents

CR-RBS-

24-05965, 2025-00670, 2025-01221

71152A

Procedures

EN-MA-118

Foreign Material Exclusion

71152A

Work Orders

WO 54152416