IR 05000458/2025013

From kanterella
Jump to navigation Jump to search
Age-Related Degradation Inspection Report 05000458/2025013
ML25337A015
Person / Time
Site: River Bend 
Issue date: 12/03/2025
From: Greg Warnick
NRC/RGN-IV/DORS/EB1
To: Hansett P
Entergy Operations
References
IR 2025013
Download: ML25337A015 (0)


Text

December 03, 2025

SUBJECT:

RIVER BEND STATION - AGE-RELATED DEGRADATION INSPECTION REPORT 05000458/2025013

Dear Phil Hansett:

On September 25, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at River Bend Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 1, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations.

However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of inspection reports that could not be issued within 45 days after the end of the inspection because of the shutdown.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at River Bend Station. If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at River Bend Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Gregory G. Warnick, Branch Chief Engineering Branch 2 Division of Operating Reactor Safety Docket No. 05000458 License No. NPF-47

Enclosure:

As stated

Inspection Report

Docket Number:

05000458

License Number:

NPF-47

Report Number:

05000458/2025013

Enterprise Identifier:

I-2025-013-0000

Licensee:

Entergy Operations, Inc

Facility:

River Bend Station

Location:

St. Francisville, LA

Inspection Dates:

September 08, 2025 to September 25, 2025

Inspectors:

W. Cullum, Senior Reactor Inspector

D. Stagner, Reactor Inspector

F. Thomas, Senior Reactor Inspector

Approved By:

Gregory G. Warnick, Branch Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at River Bend Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Establish Performance Goals Under 10CFR50.65(a)(1) for the Standby Service Water System Following Repetitive Maintenance Rule Functional Failures Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2025013-01 Open/Closed

[P.2] -

Evaluation 71111.21N.

The inspectors identified a Green finding and associated non-cited violation (NCV) of 10CFR50.65(a)(1) when the licensee failed to identify a maintenance rule functional failure of the standby service water system. During a leak rate test of SWP-MOV57A, leakage was observed past the valve seat in excess of the standby service water system overall leakage acceptance criteria. This condition was incorrectly determined to not be a maintenance rule functional failure due to compensatory actions that were established to maintain operability of the standby service water system. As a result, the licensee did not monitor the performance or condition of structures, systems, or components (SSCs), against licensee-established goals in a manner sufficient to provide reasonable assurance that they are capable of fulfilling their intended functions in accordance with 10CFR50.65(a)(1).

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.04 - Age-Related Degradation Age-Related Degradation

(1) E51-HYVC002, Reactor Core Isolation Cooling (RCIC) Governor Valve
(2) SWP-P2B, Standby Service Water Pump B
(3) SWP-MOV57A, Standby Service Water Normal Supply Header A Inlet Isolation Valve
(4) Standby Service Water Cooling Tower Division 2 Spargers
(5) C41-VEXF004A, Standby Liquid Control Pump 1A Discharge Header Explosive Valve
(6) E22-S004, 4KV Metal Clad Breaker Control, 1E22*PNLS001 Bus 10 & 11
(7) HVR-UC6, Auxiliary Building Unit Cooler 6 Fan Motor
(8) ENS-SWG1A ACB1, 4160V Standby Switchgear Bus 1A - Circuit Breaker

INSPECTION RESULTS

Failure to Establish Performance Goals Under 10CFR50.65(a)(1) for the Standby Service Water System Following Repetitive Maintenance Rule Functional Failures Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2025013-01 Open/Closed

[P.2] -

Evaluation 71111.21N.0 The inspectors identified a Green finding and associated non-cited violation (NCV) of 10CFR50.65(a)(1) when the licensee failed to identify a maintenance rule functional failure of the standby service water system. During a leak rate test of SWP-MOV57A, leakage was observed past the valve seat in excess of the standby service water system overall leakage acceptance criteria. This condition was incorrectly determined to not be a maintenance rule functional failure due to compensatory actions that were established to maintain operability of the standby service water system. As a result, the licensee did not monitor the performance or condition of structures, systems, or components (SSCs), against licensee-established goals in a manner sufficient to provide reasonable assurance that they are capable of fulfilling their intended functions in accordance with 10CFR50.65(a)(1).

Description:

Inspectors reviewed recent condition reports related to SWP-MOV57A. This valve is a component in the standby service water system (SSW). According to Updated Final Safety Analysis Report (UFSAR) Revision 27 Section 9.2.7.1, the standby service water system provides all the necessary cooling water to the reactor plant components required to safely bring the reactor to a cold shutdown condition and to maintain it in cold shutdown for a 30-day post-accident period. The system consists of two redundant trains with separate cooling tower basins which are capable of being cross connected but normally isolated by two motor-operated valves. SWP-MOV57A, along with three other valves in the system, has a design function to close during a design basis accident which serves to isolate the non-safety related loads from the safety-related loads in the standby service water system. Therefore, any leakage past this valve represents leakage outside of the standby service water system and must be accounted for to ensure adequate water inventory remains available for the 30-day mission time of the system following a design basis accident.

River Bend Station (RBS) uses calculations G13.18.13.2*086 Revision 4, Effects of Maximum Safeguards Operation on the Ultimate Heat Sink, and PM-194 Revision 12, Standby Cooling Tower Performance and Evaporation Losses Without Drywell Cooling Towers, to determine ultimate heat sink performance and inventory margin. These calculations determine that the current allowed system leakage is 6.9 gpm to ensure that enough inventory remains for the 30-day mission time.

In the maintenance rule program, there is a train level condition monitoring criterion established for the standby service water system. The train level condition monitoring criterion is described as, "Inability or failure of one SSW train to provide sufficient cooling water for heat removal capability from systems and components required to mitigate emergency conditions." The performance criterion is less than or equal to 2 per 2-year period.

The preventative maintenance template shows that the leakage test for SWP-MOV57A is conducted every refueling outage or once every 2 years. Therefore, the inspectors noted that the condition monitoring criteria would never be exceeded for SSW with the established performance criteria.

Looking at the history of maintenance rule functional failures, inspectors observed that in refueling outage RF-22, on March 24, 2023, SWP-MOV57A failed its leakage test with leakage documented at 30 gpm. This condition was documented in CR-RBS-2023-02997.

The licensee determined that this represented a maintenance rule functional failure since it represents system leakage above the acceptable level of 6.9 gpm. Therefore, SSW would not have enough inventory to satisfy its 30-day mission time.

Inspectors reviewed CR-RBS-2025-00779 which documents that, on February 14, 2025, during refueling outage RF-23, leakage past SWP-MOV57A was 7.59 gpm. Inspectors observed that this condition was determined not to be a maintenance rule functional failure by the licensee. The licensee provided the evaluation for the maintenance rule functional failure determination. This evaluation credited compensatory actions to restore inventory to the standby service water system via alternate sources.

Compensatory actions are only credited for operability considerations and cannot be applied to maintenance rule functional failure determinations. This is clear in the licensees procedure EN-DC-205, Revision 10, Maintenance Rule Monitoring, Attachment 2, Guidelines for Functional Failure Determination, item 2, which states Maintenance Rule monitoring is for the intended function of the SSC and should not take credit for operator actions unless these actions are intended by the design. If operator actions are compensatory actions required to maintain the equipment, then this may be considered a failure of the SSC.

The seat leakage of SWP-MOV57A should have been considered in the absence of compensatory actions and therefore would have represented a maintenance rule functional failure (MRFF). This MRFF should have shifted the standby service water system from the a(2) to the a(1) maintenance rule category with additional monitoring and plans required to restore the system performance to acceptable standards had the licensee established appropriate condition monitoring performance criteria.

Corrective Actions: The licensee entered this condition in the corrective action program. No operability determination was required since compensatory actions were already established to support operability of the standby service water system.

Corrective Action References: CR-RBS-2025-05265

Performance Assessment:

Performance Deficiency: The licensee failed to monitor the performance or condition of the standby service water system volume in a manner sufficient to provide reasonable assurance that these structures, systems, and components are capable of fulfilling their intended functions in accordance with 10CFR50.65(a)(1). Specifically, the licensee failed to identify that the maintenance rule condition monitoring criteria was exceeded when SWP-MOV57A exceeded the allowed leakage during testing as documented by CR-RBS-2025-00779.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to identify a maintenance rule functional failure resulted in not performing additional assessments and establishing goals to return the system performance to an acceptable level.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Inspectors used Exhibit 2, "Mitigating Systems Screening Questions," and determined that the issue screened to Green because the SSC retained its operability or PRA functionality.

Specifically, the standby service water system was considered operable due to compensatory measures that establish makeup from alternate sources to achieve the 30-day mission time.

Cross-Cutting Aspect: P.2 - Evaluation: The organization thoroughly evaluates issues to ensure that resolutions address causes and extent of conditions commensurate with their safety significance. Inspectors reviewed corrective actions for a similar NRC violation that was issued recently for maintenance rule discrepancies. The licensee performed an apparent cause determination under CR-RBS-2024-05326 and implemented several corrective actions.

However, no extent of condition was performed to look at other maintenance rule functional failures outside of the ones identified by the NRC. This was a missed opportunity to discover other maintenance rule evaluations which may have been performed erroneously.

Enforcement:

Violation: 10CFR50.65(a)(1) requires in part that licensees shall monitor the performance or condition of structures, systems, or components, against licensee-established goals, in a manner sufficient to provide reasonable assurance that these structures, systems, and components, are capable of fulfilling their intended functions. Such goals shall be established commensurate with safety.

Contrary to the above, from February 14, 2025, to September 25, 2025, the licensee did not monitor the performance or condition of structures, systems, or components, against licensee-established goals, in a manner sufficient to provide reasonable assurance that these structures, systems, and components, are capable of fulfilling their intended functions.

Specifically, the preventative maintenance program for the standby service water system was shown to be ineffective due to repeat maintenance preventable functional failures of SWP-MOV57A due to excessive seat leakage.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On September 25, 2025, the inspectors presented the River Bend Station Age-Related Degradation Inspection results to Phil Hansett, Site Vice-President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

CR-RBS-

25-04386, 2025-03716, 2025-01383, 2025-00836,

25-00779, 2025-00390, 2024-04957, 2023-00433,

23-02997, 2023-01889, 2023-02815

Corrective Action

Documents

Resulting from

Inspection

CR-RBS-

25-04966, 2025-05003, 2025-05007, 2025-05008,

25-05012, 2025-05014, 2025-05015, 2025-05023,

25-05024, 2025-05034, 2025-05251, 2025-05037

EE-001M

4160V One Line Diagram, Standby Bus E22-S004

EE-001SA

480V One Line Diagram, 1E22*S002 Control Building

EE-001TA

480V One Line Diagram, EHS-MCC2A & 2L Auxiliary

Building

ESK-06HVR12

Elementary Diagram, 480V Control Circuit Auxiliary

Building Unit Coolers UC4 & UC6

PID-09-10B

Engineering P&I Diagram, System 118, Service Water-

Normal

Drawings

PID-09-10E

Engineering P&ID System 256 Service Water - Standby

Engineering

Changes

EC-0054132003

SBCT Sparger Pipe Modifications

21.452-000-

003

Purchase Specification For Turbine, Steam, Auxiliary

Drive

21.243-000-

003F

Installation and Maintenance Manual for Explosive Valves

07/12/1996

24.110-000-

030A

Operating and Maintenance Instructions for Reactor Core

Isolation Cooling Systems

B

242.521-102-

001O

Magne-Blast Circuit Breaker Type AM-4.16-250-9

10/12/1992

242.521-102-

001Q

GE Metal-Clad Switchgear Type M26 & M36

10/12/1992

B515-0136

Installation and Maintenance of Axial Flow Fans

C41-VEXF004A

PM 500389621

PM Template / Maintenance Strategy

9/3/2025

71111.21N.04

Miscellaneous

EN-MA-141

Limitorque Valve Operator Model SMB/SB/SBD-000

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Through 5 MOV and HBC Periodic Inspection

EQAR-075

Environmental Qualification Assessment Report For

Reactor Core Isolation Cooling Turbine Controls

PID-27-06A

Engineering P&ID System 209 Reactor Core Isolation

Cooling

T12107

PM Job Plan to Replace C41-VEXF004A/B (STANDBY

LIQ CNTRL PMP 1A/B DISCH HEADER EXPLOSIVE

VLV) explosive charge, firing assembly, and inlet fitting

after test firing.

11/13/2025

VTD-B455-0100

Asea Brown-Boveri Installation/Maintenance Instructions

for Medium-Voltage Power Circuit Breakers Type 5HK

200 Thru 3000 Amperes 5000 Volts

VTD-B455-0139

Brown Boveri (Now ABB Power T&D Company Inc.)

Instructions for Undervoltage and Over-Voltage Relays

ITE-27 and ITE-59

VTD-B515-0121

Buffalo Forge Installation and Operation Instructions For

Air Handling Cabinets

VTD-H127-0103

Manual for Standby Service Water Pumps

CMP-EM-302-

1003

GE 4.16KV Switchgear - Clean and Inspect

001

EN-AD-104

Site Procedure Control Process

2

EN-DC-204

Maintenance Rule Scope and Basis

009

EN-DC-205

Maintenance Rule Monitoring

010

EN-DC-310

Predictive Maintenance Program

EN-DC-324

Preventive Maintenance Program

2

STP-209-0601

RCIC Initiation Functional

Procedures

STP-209-6310

RCI Quarterly Pump and Valve Operability Test

Work Orders

WO- 54037374, 54070128, 54079785, 54096866, 54114035,

54142462, 54143414, 54175197, 54210808, 54225062,

275241, 00128314, 52330722, 52891357, 53005728,

53020629, 53038705, 54045762, 54053010, 54087830,

54093435, 54118674, 54124859, 54148924, 54154000,

54181620, 54187952, 51008285, 52996077, 53019106,

53020105, 54039054, 54057906, 54078168, 54105055,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

54135956, 54161299, 54203356, 54235137, 54266581,

250898