IR 05000341/2019012

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams); Inspection Report 05000341/2019012 (DRS-N.Feliz-Adorno)
ML19211B289
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 07/29/2019
From: Karla Stoedter
NRC/RGN-III/DRS/EB2
To: Fessler P
DTE Energy
References
IR 2019012
Download: ML19211B289 (25)


Text

July 29, 2019

SUBJECT:

FERMI POWER PLANT, UNIT 2DESIGN BASIS ASSURANCE INSPECTION (TEAMS); INSPECTION REPORT 05000341/2019012

Dear Mr. Fessler:

On July 10, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Fermi Power Plant, Unit 2, and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. The inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating this violation as non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violations or significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Fermi.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Fermi. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Karla K. Stoedter, Chief Engineering Branch 2 Division of Reactor Safety

Docket No. 50-341 License No. NPF-43

Enclosure:

As stated

Inspection Report

Docket Number:

05000341

License Number:

NPF-43

Report Number:

05000341/2019012

Enterprise Identifier: I-2019-012-0005

Licensee:

DTE Electric Company

Facility:

Fermi Power Plant, Unit 2

Location:

Newport, MI

Inspection Dates:

May 06, 2019 to July 10, 2019

Inspectors:

A. Dahbur, Senior Reactor Inspector

N. Feliz-Adorno, Senior Reactor Inspector

W. Hopf, Contractor

M. Jones, Reactor Inspector

L. Rodriguez, Reactor Inspector

R. Waters, Contractor

Approved By:

Karla K. Stoedter, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Fermi Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

Licensee-identified non-cited violations are documented in report sections: 71111.21M.

List of Findings and Violations

Failure to Incorporate Acceptance Limits Contained in High Pressure Coolant Injection Design Documents Into Test Procedure Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/2019012-01 Open/Closed

[H.8] - Procedure Adherence 71111.21M The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation (NCV) of Title 10 of the Code of Federal Regulations (CFR), Part 50,

Appendix B, Criterion XI, Test Control, for the licensee's failure to incorporate the minimum total developed head acceptance limits contained in Design Document DC-0501, HPCI Hydraulic Analysis, Revision F, into Test Procedure 24.202.01, HPCI Pump and Valve Operability Test at 1025 psi, Revision 118.

Non-Conservative Motor-Operated Valve Output Torque Capacity Methodology Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/2019012-02 Open/Closed None (NPP)71111.21M The inspectors identified a finding of very low safety significance (Green) and associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the licensee's failure to verify the adequacy of the output torque capacity of safety-related motor-operated valves (MOVs).

Specifically, the licensee evaluated MOV output torque capability, in part, by using the ComEd WP-125 method and the full motor nominal voltage (rather than using the calculated terminal voltage) when the calculated voltage was greater than 90 percent of the nominal voltage.

However, the use of full motor nominal voltage when calculating the output torque capacity using the ComEd WP-125 method was non-conservative and resulted in output torque values which were not reflective of the actual motor capacity limit needed to ensure safety-related MOVs would perform their safety function.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the components and associated attributes, permanent modifications, and operating experience listed below. During this review, the inspectors noted degradation of containment coatings and became concerned that the coatings could peel off and interfere with the operation of safety systems in the unlikely event of an accident. The NRC determined this concern warranted additional inspection by a Special Inspection Team. The results of the Special Inspection will be documented in Inspection Report 05000341/2019050.

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1) Drywell Exhaust and Air Purge Isolation Valves (T4803-F602 & T4600-F411/F402)
  • Licensing basis requirements
  • Material condition and configuration
  • Operating procedures
  • System health, corrective maintenance, and corrective action history
  • Maintenance effectiveness
  • Consistency between station documentation (e.g., procedures) and vendor specifications
  • Environmental qualification
  • Valve capability calculations
  • Air supply availability and capability
  • Stroke timing
  • Testing procedures, acceptance criteria, and recent results
  • Thermal overload testing and sizing
  • Response to degraded voltage
  • Minimum voltage calculation
  • Torque requirement calculation Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (5 Samples)
(1) High Pressure Coolant Injection (HPCI) Pump (E4101C001A)
  • Licensing basis requirements
  • Material condition and configuration
  • Operating procedures
  • Modifications
  • System health, corrective maintenance, and corrective action history
  • Maintenance effectiveness
  • Consistency between station documentation (e.g., procedures) and vendor specifications
  • Turbine and pump performance and capability calculations
  • Runout and minimum flow
  • Submergence (i.e., net positive suction head (NPSH) and vortexing)
  • Protection against flooding and seismic events
  • Water supply availability
  • Steam supply availability
  • Suction strainer blockage
  • Room heat up and ventilation
  • Component lubrication
  • Surveillance and test procedures, acceptance criteria, and results
  • Component control instrumentation
  • Instrumentation set point calculations
(2) Reactor Core Isolation Cooling (RCIC) Pump (E5101C001)
  • Licensing basis requirements
  • Material condition and configuration
  • Operating procedures
  • Maintenance effectiveness
  • Component health, corrective maintenance, and corrective action history
  • Consistency between station documentation (e.g., procedures) and vendor specifications
  • Turbine and pump performance and capability calculations
  • Runout and minimum flow
  • Submergence (e.g., NPSH and vortexing)
  • Water supply availability
  • Room heat up and ventilation calculations
  • Surveillance and test procedures, acceptance criteria, and results (3)260/130 Volt DC Main Distribution Panels 2PA-2 and 2PB-2 (R3200S026/7)
  • Licensing basis requirements
  • Operating procedures
  • Component health, corrective maintenance, and corrective action history
  • Maintenance effectiveness
  • Flood and seismic protection
  • Room heat up and ventilation
  • Surveillance and test procedures, acceptance criteria, and results
  • Load, short circuit, and coordination calculations
  • Temperature effects and environmental qualification
  • Inverter capacity and capability to supply adequate voltage
  • Protective breakers and trip set points

(4)130/260 Volt DC Battery 2PA and 2PB (R3200S003/4)

  • Licensing basis requirements
  • System health, corrective maintenance, and corrective action history
  • Maintenance effectiveness
  • Performance testing
  • Technical Specification required surveillance testing
  • Discharge testing
  • Battery charger sizing
  • Terminal corrosion resistance
  • Short circuit calculation
  • Voltage drop calculation
  • Protection against flooding and seismic events
  • Room heat up and ventilation calculations
(5) Safety Relief Valve (B2104F013A)
  • Licensing basis requirements
  • Operating procedures
  • System health, corrective maintenance, and corrective action history
  • Maintenance effectiveness
  • Consistency between station documentation (e.g., procedures) and vendor specifications
  • Environmental qualification
  • Relief capacity
  • Pneumatic supply capability
  • Lift settings
  • Low-low set setpoint
  • Surveillance and test procedures, acceptance criteria, and results
  • Control logic

Modification Review - Permanent Mods (IP Section 02.03) (4 Samples)

(1)

===37272.001, RCIC Pump Discharge High Point Vent Relocation

(2) Calculation Change DC-0501 VOL I, HPCI Hydraulic Analysis
(3) Calculation Change DC-6478 VOL I, 120 Volts Alternating Current Protective Device Coordination Calculation for Divisions 1 and 2
(4) Calculation Change DC-5512 VOL I, Evaluation of 1E/Non-1E Separation Criteria

Review of Operating Experience Issues (IP Section 02.06)===

(1) NRC Information Notice 2005-30, Safe Shutdown Potentially Challenged by Unanalyzed Internal Flooding Events and Inadequate Design
(2) NRC Information Notice 2017-06, Battery and Battery Charger Short-Circuit Contribution to a Fault on DC System

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71111.21M This violation of very low safety significance was identified by the licensee and has been entered into the licensee Corrective Action Program and is being treated as a Non-Cited Violation (NCV), consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title 10 of the Code of Federal Regulations (CFR), Part 50, Appendix B, Criterion XVI, Corrective Action, requires, in part, that measures be established to assure conditions adverse to quality (CAQ), such as non-conformances, are promptly identified and corrected.

Contrary to the above, between June 28, 2007, and April 26, 2019, the licensee failed to establish measures to assure a CAQ was promptly corrected. Specifically, on June 28, 2007, the licensee identified the HPCI, RCIC, and core spray (CS) pumps, which are safety-related, were not protected from air-entraining vortices when their suctions were aligned to the condensate storage tank. This CAQ was captured in the Corrective Action Program as CARD 07-23630. However, on April 26, 2019, the licensee identified they had not corrected this CAQ because the implementation of the proposed corrective action (i.e., installation of a vortex suppressor) had been deferred multiple times without an appropriate justification.

Significance: Green. The finding was evaluated using the Significance Determination Process in accordance with Inspection Manual Chapter 0609 Appendix A, The Significance Determination Process for Findings At-Power, using Exhibit 2, Mitigating Systems Screening Questions. The finding screened as having very low safety significance (Green) because it did not result in the loss of operability or functionality of the HPCI, RCIC, or CS pumps.

Specifically, the licensee reasonably determined the HPCI and RCIC pump suctions would likely transfer to the torus before vortexing became a concern during a design basis event by crediting the torus high water level automatic suction transfer. In addition, the licensee reviewed historical condensate storage tank water levels and reasonably determined the condensate storage tank actual level was sufficient to enable CS to accomplish its function before vortexing became a concern.

Corrective Action References: CARD 07-23630, CARD 19-23227, CARD 19-23632, CARD 19-23797, and CARD 19-23966 Observation: Effectiveness Review of Corrective Actions Taken by the Licensee to Issues Identified during Previous Component Design Basis Inspection and Design Bases Assurance Inspections 71111.21M In accordance with IP 71111.21M, Section 02.05c, the inspectors reviewed the effectiveness of corrective actions taken by the licensee to address issues identified during previous Component Design Basis Inspections and Design Bases Assurance Inspections. No findings or violations were identified. The items reviewed were:

1. NCV 05000341/2007003-03, HPCI Pump In-Service Testing Acceptance Criterion

Was Not Conservative with Respect to the System Performance Requirements.

2. NCV 05000341/2016007-07, Failure to Ensure that Protective Devices for the Loads

Required at the Beginning of a Loss of Coolant Accident Would Not Trip Under Degraded Voltage Conditions.

Failure to Incorporate Acceptance Limits Contained in High Pressure Coolant Injection Design Documents into Test Procedure Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/2019012-01 Open/Closed

[H.8] - Procedure Adherence 71111.21M The inspectors identified a finding of very low safety significance (Green) and an associated NCV of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, for the licensees failure to incorporate the minimum total developed head acceptance limits contained in Design Document DC-0501, HPCI Hydraulic Analysis, Revision F, into Test Procedure 24.202.01, HPCI Pump and Valve Operability Test at 1025 psi, Revision 118.

Description:

The HPCI pump is safety-related and is part of the emergency core cooling systems designed to provide core cooling during design basis events. To verify the pump develops the flow rate required by the applicable safety analyses, Technical Specifications Surveillance Requirement (SR) 3.5.1.9 requires periodic in-service testing in accordance with the ASME OM Code. This SR is implemented by Procedure 24.202.01, HPCI Pump and Valve Operability Test at 1025 psi, Revision 118, which is intended to evaluate test results against the acceptance criteria established by Calculation DC-0501, HPCI Hydraulic Analysis, Revision F.

However, the inspectors noted the HPCI pump minimum total developed head acceptance limits contained in Procedure 24.202.01 were less restrictive than the acceptance limits established in Calculation DC-0501. Therefore, the test procedure acceptance limits did not ensure the HPCI pump was capable of developing the flow rates required by the applicable safety analyses.

Further review determined the calculation was revised in January 2018, and the licensee failed to update the procedure with the revised acceptance limits. Through discussions with the licensee, the inspectors learned the test procedure was not updated because a procedure revision notice had not been issued. The licensee relies on procedure revision notices to identify and update procedures affected by calculation changes.

Corrective Actions: As an immediate corrective action, the licensee reviewed historical test data obtained since the issuance of Revision F of DC-0501 and reasonably determined the HPCI pump performance was acceptable. The licensees proposed corrective action is to revise Procedure 24.202.01 before the next scheduled test to incorporate the revised acceptance limits.

Corrective Action References: CARD 19-23989

Performance Assessment:

Performance Deficiency: The inspectors determined the licensees failure to incorporate the acceptance limits contained in Design Document DC-0501, Revision F, into Test Procedure 24.202.01, Revision 118, was contrary to 10 CFR Part 50, Appendix B, Criterion XI, Test Control, and was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, the failure to incorporate the acceptance limits contained in the revised hydraulic analysis into the test procedure would have the potential to lead to the acceptance of a condition where the HPCI pump is incapable of performing its accident mitigating function.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding affected the Mitigating Systems cornerstone and screened as having very low safety significance (Green) because it did not result in the loss of operability or functionality of the HPCI pump.

Specifically, the licensee reviewed historical test data since the issuance of Revision F of DC-0501 and reasonably determined the HPCI pump performance was acceptable.

Cross-Cutting Aspect: H.8 - Procedure Adherence: Individuals follow processes, procedures, and work instructions. Specifically, the licensee did not identify and update procedures affected by the revision of Calculation DC-0501 in 2018, which was not in accordance with Procedure MES20, Implementation of Modifications, Revision 35B.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires, in part, that a test program be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents. The licensee established Procedure 24.202.01, HPCI Pump and Valve Operability Test at 1025 psi, Revision 118, as the implementing procedure for the HPCI in-service testing required by SR 3.5.1.9. Also, the licensee established Calculation DC-0501, HPCI Hydraulic Analysis, Revision F, as the design document for the applicable test acceptance limits.

Contrary to the above, since January 2018, the licensee failed to establish a test program to assure that testing required to demonstrate the safety related HPCI pump will perform satisfactorily in service was identified and performed in accordance with written test procedures which incorporated the requirements and acceptance limits contained in applicable design documents. Specifically, the licensee failed to incorporate the HPCI minimum total developed head acceptance limits contained in Revision F of DC-0501 into Revision 118 of Test Procedure 24.202.01.

Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Non-Conservative Motor-Operated Valve Output Torque Capacity Methodology Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/2019012-02 Open/Closed None (NPP)71111.21M The inspectors identified a finding of very-low safety significance (Green) and associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the licensee's failure to verify the adequacy of the output torque capacity of safety-related MOVs. Specifically, the licensee evaluated MOV output torque capability, in part, by using the ComEd WP-125 method and the full motor nominal voltage (rather than using the calculated terminal voltage) when the calculated voltage was greater than 90 percent of the nominal voltage. However, the use of full motor nominal voltage when calculating the output torque capacity using the ComEd WP-125 method was non-conservative and resulted in output torque values which were not reflective of the actual motor capacity limit needed to ensure safety-related MOVs would perform their safety function.

Description:

The licensee verified MOV output torque capacity in Calculation DC-5719, Minimum Required Target Thrust (MRTT) for Generic Letter 89-10 Gate, Globe and Quarter-Turn Valves, Revision V. This calculation determined output torque values using the following two methods:

(1) the Limitorque Torque Capability method and
(2) the ComEd WP-125 method. Regardless of the calculational method used, the licensee utilized full nominal voltage values as an input even when expecting degraded voltage values. The licensee selected the higher of the resulting two output torque values as the motor capability limit during MOV diagnostic testing, which was intended to demonstrate the MOVs can perform their accident mitigating functions.

The inspectors noted the use of full nominal voltage in place of the degraded terminal voltage was only allowed by the Limitorque Torque Capability method. Specifically, Limitorque Technical Update 98-01 allowed for the use of full nominal voltage in place of the calculated terminal voltage when the calculated value was greater than 90 percent of the nominal value.

However, the application of this voltage allowance when calculating output torque values using the ComEd WP-125 method was not allowed because it resulted in non-conservative output torque values and could result in multiple safety-related valves being unable to perform their mitigating functions.

Corrective Actions: As an immediate corrective action, the licensee preliminarily revised their calculation with the correct version of the ComEd WP-125 method using the calculated terminal voltage and determined eight MOVs had negative analytical torque margin. As a result, the licensee performed further analysis for these MOVs using different analytical strategies and reasonably determined they remained operable. These MOVs were the reactor recirculation pump A discharge isolation valve (B3105F031A), residual heat removal (RHR)

Division 1, pump C, suppression pool suction isolation valve (E1150F004C), RHR Division 2 drywell spray inboard isolation valve (E1150F021B), RHR Division 1 suppression pool containment spray test isolation valve (E1150F028A), RHR Division 2 suppression pool containment spray test isolation valve (E1150F028B), CS Division 2 torus suction isolation valve (E2150F036B), reactor building close cooling water Division 1 supply isolation valve (P4400F603A), and emergency equipment cooling water Division 1 drywell return outboard isolation valve (P4400F607A).

Corrective Action References: CARD 19-23915, CARD 19-23640, CARD 19-23636, CARD 19-23865, and CARD 19-23863.

Performance Assessment:

Performance Deficiency: The inspectors determined the licensees failure to verify the adequacy of the output torque capacity for safety-related MOVs was contrary to the requirements of 10 CFR Part 50, Appendix B, Criterion III, Design Control, and was a performance deficiency. Specifically, the licensee evaluated MOV output torque capability, in part, by using the ComEd WP-125 method and the full motor nominal voltage in place of the calculated terminal voltage when the calculated value was greater than 90 percent of nominal. However, the use of full nominal voltage in place of the calculated terminal voltage for calculating the output torque capacity using the ComEd WP-125 method was non-conservative.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone. The performance deficiency adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of mitigating systems to respond to initiating events to prevent undesirable consequences. Specifically, the failure to verify the adequacy of safety-related MOV output torque capacity did not ensure the MOVs were capable of performing their accident mitigating functions.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding screened as of very low safety significance (Green) because it did not result in the loss of operability or functionality of mitigating systems. Specifically, the licensee performed an operability evaluation and reasonably determined that all impacted MOVs remained operable.

Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in part, that design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Contrary to the above, as of May 21, 2019, the licensee failed to verify or check the adequacy of design of safety-related MOVs by the performance of design reviews, the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Specifically, the licensee evaluated MOV output torque capability, in part, by using the ComEd WP-125 calculational method and the full motor nominal voltage when the calculated terminal voltage was greater than 90 percent of the nominal voltage. However, the use of full nominal voltage in place of the calculated terminal voltage for calculating the output torque capacity using the ComEd WP-125 method was non-conservative and resulted in output torque capabilities which were not reflective of the those needed during accident conditions.

Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On July 10, 2019, the inspectors presented the Design Basis Assurance Inspection (Teams) inspection results to Paul Fessler and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

2-00058

Summary Report for the GE Component Seismic Evaluation

6M721-2044

RCIC System

BE

DBD-E51-00

Reactor Core Isolation Cooling

F

DC-0369 Volume

I

RCIC System Design Computations

F

DC-0469 Volume

I

Essential Accumulators for Class I Valves (MSIVs,

ADS-SRVs, LLS-SRVs)

04/17/1997

DC-0501

HPCI Hydraulic Analysis

F

DC-0502 Volume

I

RCIC Hydraulic Analysis

G

DC-0885

ECCS Suction Line Air Ingestion

E

DC-0885 Volume

I

ECCS Suction Line Air Ingestion

E

DC-3078

Reactor Water Level Transmitters: Zero Elevation and Span

C

DC-4255 Volume

II

Sizing of the Primary Containment Pneumatic Supply

Back-Up Nitrogen Bottles

08/25/2008

DC-4523

Reactor Wide Range Water Level Surveillance Procedure

Validation

J

DC-4523 Volume

I

Reactor Wide Range Water Level Surveillance Procedure

Validation

J

DC-4528

Reactor Narrow Range Water Level Surveillance Procedure

Validation

G

DC-5147 Volume

I

DBTF Concerns With Battery Room/Charger Area HVAC

DC-5426 Volume

I

PBOC - High and Moderate Energy Line Break Evaluation

D

DC-5487

Maximum Expected Differential Pressure (MEDP) for Valves

T4803F601, F602, T4804F601A/B, F602A/B, F603A/B,

F604A/B, F605A/B, F606A/B, F001A/B, F002A/B, F003A/B

C

DC-5589 Volume

I

Reactor Building Environmental Response for HELB and

LOCA Conditions

C

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DC-5719 VOL I

Minimum Required Target Thrust (MRTT) for Generic letter

89-10 Gate, Globe and Quarter-Turn Valves (Torque)

V

DC-5954 Volume

I

Anchorage Qualification of Div. II 260/130V Battery Racks

DC-5979

Estimation of Debris Sources for ECCS Suction Strainers

DC-6212 Volume

I

Environmental Response Profiles for Areas Containing

Safety Related Equipment

A

DC-6372 Volume

I

Assessment of Channel Instrument Error (CIE) for RCIC

Flow and Speed Loops

DC-6397 Volume

I

Calculation of Safety Related GL 89-10/96-05 and non

GL 89-10/96-05 AC MOV Motor Terminal Voltages

C

DC-6478 Volume

I

20 VAC Protective Device Coordination Calculation for

Division 1 and 2

C

DC-6480 Volume

I

130/260 DC System Analysis

C

DC-6480 Volume

I

130/260 V DC System Analysis

C

DC-6482

260/130V and 48/24V DC Protective Devices Coordination

C

DC-6482 Volume

I

260/130V and 48/24V Protective Device Coordination

Calculation

C

EDP-37272

RCIC Pump Discharge High Point Vent Relocation

M4A

SBFW Pump NPSHA

2/10/2008

QR-284030-01

Environmental and Seismic Qualification Report

TSR-35639

Revision of Design Calculation DC-2680

A

TSR-36510

Issue New/Revised AOV Torque Calculations (2206C,

2399C, 2402C, 2414C, DC-5989 Vol. I), update CECO, and

Relevant BCDDs for Re-Analysis Using Lower Air Pressure

TSR-37565

Revise CECO & Post Changes Against BCDDs Such as

DC-5719 and DC-6083 (Both Vol. I)

Corrective Action

Documents

05-25383

SEN Internal Flood Design Deficiencies

05/20/2009

07-23630

CDBI: UFSAR Anti-Vortex Methodology Non-Conservative

06/28/2007

07-23851

NRC CDBI Inspection Item 073: HPCI IST Test Acceptance

Criteria Inadequate

07/11/2007

09-20540

WGI(URS) Review of the Design Calculation DC-0215

01/27/2009

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

10-298000

Degraded Torus Earthquake Tie Attached to Bay 9

10/30/2010

2-24503

Potential Non-Conservative Application of TS SR 3.5.1.4

05/16/2012

13-20872

HPCI Booster Pump Outboard Bearing Level Indication

2/05/2013

14-21750

Stroke Time Limits for T4600F402 do not Match in

24.404.03 Between Sections 5.1 and 5.2

2/27/2014

14-23884

Conflicting Design Basis MEDP Capability for T4803F601

and T4803F602

05/05/2014

15-20116

Revise 23.205 for LPCI Inoperability in SDC

01/06/2015

15-28410

Degraded Coatings Identified Inside the Torus

10/29/2015

16-26533

2016 CDBI Issue - Non-Conformance to License Bases for

Evaluation of Degraded Voltage

08/17/2016

16-26800

CDBI: Inappropriate Disposition of Penetration Min-K Debris

Generation

08/26/2016

17-22973

Extensive Coating Defects Identified during Torus

Underwater Inspection

04/02/2017

17-23743

RCIC Turbine Oil Filter Inlet Pressure Indication Reading

Low OOS

04/19/2017

17-25515

Drains Backed up Causing Overflow on to Floor

06/22/2017

18-24343

Procedure and Required M&TE Inconsistency

05/31/2018

18-24957

Floor Drains Overflowed From Pumping Down Sump DO-74

06/26/2018

18-26749

RCIC Lube Oil Pump Discharge Pressure Trend

09/07/2018

18-27527

Foreign Material Found in SRV T-Quencher in Bay 16

09/29/2018

19-23227

Recommend Review of Site Response to Open CARD 07-

23630

04/26/2019

19-23383

Oil Drops on HPCI Turbine Stop Valve Actuator

05/02/2019

91-0840

Seismic Adequacy of CST Water Source

10/31/1991

OE 2017-0529

IN-17-06, Battery and Battery Charger Short-Circuit Current

Contributions to a Fault on the Direct Current Distribution

11/03/2017

Corrective Action

Documents

Resulting from

Inspection

19-23216

PSA Main Control Room Abandonment Modeling

Discrepancy

04/26/2019

19-23490

2019 DBAI: DC-4523 Vol 1, Rev. J, Missing and Not

Updated References for NTSPs Moved From Tech Specs to

TRM (Legacy Issue)

05/06/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

19-23493

2019 DBAI: Discrepancy Between UFSAR and Tech Spec

Bases

05/06/2019

19-23495

2019 DBAI: Drawing I-2225-05 has the Incorrect PIS for

HPCI Turbine Speed Indicator

05/06/2019

19-23534

2019 DBAI: I-2201-15 Reference Drawing Listed for

Testability Trip Unit Relay B31K202A is Incorrect (Legacy

Issue)

05/07/2019

19-23571

2019 DBAI: DC-6480 Vol. I, Rev. C Issued Without Updating

Impacted MOV Outputs

05/08/2019

19-23574

2019 DBAI: Ambient Temperature Rating for DC Distribution

Cabinets R3200S026 and R3200S027

05/15/2019

19-23579

CARD 18-21882, Inadequate Evaluation of IN-1706

05/09/2019

19-23582

2019 DBAI: Use of Non-Conservative Values During

2.309.05

05/09/2019

19-23592

2019 DBAI: Two SRV Accumulator Check Valve Test

Procedures Exist

05/09/2019

19-23615

Unnecessary Evaluation of a Fault in DC Control Circuit for

480 Switchgear Breaker Feeding Non-1E Load from 1E

480V 1E Bus in Calculation DC-5512

05/09/2019

19-23616

2019 DBAI, SRV Set-Point out of Tolerance not Evaluated

for LLS/ADS SRVs

05/09/2019

19-23631

2019 DBAI: CST Valve Pit not Included on Confined Space

List

05/10/2019

19-23632

2019 DBAI: Update to 23.107.01 Section 3.5 to Correct

Inconsistency With Last Update

05/10/2019

19-23636

2019 DBAI: E4150F003 CECO Design Basis Open Stroke

Time Does not Match TRM 3.6-5 Open Stroke Time Note

05/10/2019

19-23637

2019 DBAI: HPCI/RCIC Procedures 24.202.03 and

24.206.03

05/10/2019

19-23640

DC-6447 Issued without Updating Impacted MOV Outputs

05/10/2019

19-23651

Information Notice IN-1706 - Battery Charger (Ametek) May

Contribute up to 10 Times their Rating for a Short Period

05/10/2019

19-23689

Calculation DC-6397 not Updated for Change to Thermal

Overload Resistance for Valve T4803F602

05/13/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

19-23754

2019 DBAI: Ambient Temperature Rating for DC Distribution

Cabinets R3200S026 and R3200S027

05/15/2019

19-23764

2019 DBAI: Typographical Errors Found in DC-3078 Vol. I

05/15/2019

19-23780

2019 DBAI: SRV Coatings/Corrosion When Shifting to a 24-

Month Cycle

05/16/2019

19-23797

2019 DBAI - Revisions to Procedures Related to CST Level

for Modes 4 and 5

05/16/2019

19-23850

2019 DBAI: Potential Trend in Missed Impacted Calculations 05/20/2019

19-23863

2019 DBAI: Margin Issues With AC Motor Operated Valves

05/20/2019

19-23865

2019 DBAI: Margin Issues With 250VDC Motor Operated

Valves Investigation

05/20/2019

19-23867

2019 DBAI: Past Operability Review not Documented for

CARD 17-23452

05/20/2019

19-23915

Methodology Error Found in MOV Torque Calculation

05/21/2019

19-23933

Revise HPCI/RCIC Surveillances to Clarify Tech Spec

Acceptance Criteria

05/22/2019

19-23939

2019 DBAI: MRFF Action Needed for Previously Closed

CARD 17-23452

05/22/2019

19-23961

2019 DBAI Related (Untimely Corrective Action for Coating

Restoration on 180 Torus Earthquake Tie)

05/23/2019

19-23966

2019 DBAI: Additional Procedure Guidance Needed for Use

of Core Spray Aligned to Condensate Storage Tank in

Modes 4 and 5

05/23/2019

19-23975

2019 DBAI Related - Consider Revision of 43.000.004

(Reference DBAI Item 19-398)

05/23/2019

19-23989

2019 DBAI - DC-0501 Vol. I, was Updated in January 2018

to Revision F Without Required PPRN Reviews

05/23/2019

19-24218

2019 DBAI: NRC Concern Blistered Torus Coating

06/03/2019

CARD 19-24605

2019 DBAI: Recommended Clarifications to Procedure

43.000.019 Primary Containment Inspection

06/18/2019

Drawings

61721-2095-30

Schematic Diagram Nuclear BLR PRCS INSTR A & B

Circuits Testability Modification

L

61721-2155-01

Schematic Diagram Reactor Protection System Power

Distribution Notes & References

T

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

61721-2225-03

Schematic Diagram HPCI Logic Circuit PT 1

AA

61721-2522-01

Tank Mounted Cabinet for Miscellaneous Instruments

O

61721-2654-14

Schematic Diagram - Nitrogen Inerating Inboard Isolation

Valve

Q

6M721-2089

System Diagram Nuclear Boiler System

BN

6M721-2900

System Diagram Nuclear Boiler System

AN

6SD721-2530-10

One Line Diagram; 260/130V ESS Dual Battery 2PA

Distribution-Division 1

AM

6SD721-2530-11

One Line Diagram 260/130V ESS Dual Battery 2PB

Distribution - Division II

AQ

Engineering

Evaluations

16-0246

High Pressure Coolant Injection (HPCI) Hydraulic Analysis

DECO-12-2191

Evaluation of Containment Coatings

June 1985

EQ1-EF2-155

EEQ Qualification Evaluation Report - Target Rock Valves

2/25/2009

ERE 32092

MOV Lubrication Change

C

NUC2016135.00

Evaluation of Fermi 2 Blister Torus Wetted (Immersion)

Region Substrate Coatings

03/10/2017

Miscellaneous

System Health Report Associated With RCIC

2018 Q3 &

Q4

2A2918AB

Nuclear Boiler Design Specification Data Sheet

EF2-57987

Letter Subject: Errors in BWR Water Level Indication

07/15/1982

EF2-60002

Letter Subject: Errors in BWR Water Level Indication

10/11/1982

EFA-R32-19-005

Engineering Functional Analysis - Information Notice IN -

1706 - Battery Chargers Contribution Fault Conditions

EQ0-EF2-018

Summary of Environmental Parameters Used for Fermi 2

EQ Program

N

EQ1-EF2-044

Qualification Evaluation Report

G

NEDC 31336P

Instrument Setpoint Methodology

A

NUC2017123

Reactor Torus Desludge, ASME XI IWE VT Exams,

Coatings, Inspection & Coating Repair - Immersion Area

05/30/2017

NUC2018130

Reactor Torus Desludge, ASME XI IWE VT Exams,

Coatings Inspection & Coating Repair - Immersion Area

11/12/2018

TSR-36108

Increases in ECCS Suction Strainer Debris Loads

VMR1-45.2

Vertical Induction Triclad Motors

F

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

VMR4-14.1

RCIC Turbine

G

VMR4-4.0

RCIC Pump

B

VMR4-4.1

RCIC Pump

A

NDE Reports

VT-S12-021

Torus Earthquake Ties (4 Locations)

04/14/2012

Operability

Evaluations

TE-B21-19-021

Past Operability Review for CARDs 19-23867 and 17-

23452

05/30/2019

TE-E11-18-081

Past Operability Evaluation of Foreign Material Impact to

ECCS Suction Strainers

Procedures

20.000.18

Control of the Plant from the Dedicated Shutdown Panel

20.000.18

Control of the Plant from the Dedicated Shutdown Panel

20.000.19

Shutdown from Outside the Control Room

20.300.Offsite

Loss of Offsite Power

2A

23.104

Condensate Storage and Transfer System

23.107.01

Standby Feedwater System

23.201

Safety Relief Valves and Automatic Depressurization

System

23.206

Reactor Core Isolation Cooling Syste

103

23.309

260/130 DC Electrical System (ESF and BOP)

23.601

Instrument Trip Sheets

24.107.03

SBFW Pump and Valve Operability and Lineup Verification

Test

24.137.02

MSIV/ADS and LLS SERV Accumulator Check Valve Test

24.201.01

SRV Vacuum Breaker Valve Operability Test

24.202.01

HPCI Pump and Valve Operability Test at 1025 PSI

118

24.202.03

HPCI System Piping Filled and Valve Position Verification

24.206.01

RCIC System Pump and Valve Operability Test

24.206.03

RCIC Discharge Piping Venting and Valve Verification Test

24.206.04

RCIC System Automatic Actuation and Flow Test

24.404.03

Standby Gas Treatment System Valve Operability Test

24.406.02

Nitrogen Inerting System Valve Position Indication Test

27.000.09

Time Critical Actions Validations and Verification

29.100.01 Sheet

RPV Control

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

29.ESP-06

Primary Containment Venting and Purge for Hydrogen and

Oxygen Control

29.ESP.07

Primary Containment Venting

3017-128-EZ-04

Electrical Design Instruction for Control and Power Cable

Ampacities

C

43.137.001

Main Steam Safety/Relief Valve Setpoint Testing

43.137.002

SRV Accumulator Check Valve Test

26A

44.210.059

D1 MS SRV Solenoid Functional Test

ARP 1D24

RCIC System Actuated

ARP 1D69

SBFW Sys Suction Pressure Low

ARP 1D79

RCIC Turbine Shutdown RPV H2) Level L8

ARP 1D81

RCIC Pump Discharge Flow Low

ARP 2D48

HPCI/RCIC Suction Trans CST Level Low

ARP 8D40

Cable Tray Cooling Fan Tripped

QCP-10-1

Underwater Coating Inspection

QCP-10-2

Underwater Coating Repair

TE-ANL-12-069

Risk Significant PSA Credited Operator Actions

C

Self-Assessments TMPE-18-0180

Quick Hit Self-Assessment: Preparation for the 2019 NRC

Design Basis Assessment Inspection Self-Assessment

09/22/2018

Work Orders

1162000318

Perform 43.137.002 Division 1 SRV Accumulator Check

Valve Test

05/10/2000

116201093

Perform 43.137.002 Division 1 SRV Accumulator Check

Valve Test

11/13/2001

1162201117

SRV Accumulator Check Valve Test

11/17/2001

25975596

Desludge, Inspect, Repair - Torus Coatings Below Water

Level

05/21/2009

25975596

Desludge, Inspect, Repair - Torus Coatings Below Water

Level

04/01/2009

25980121

Perform HPCI Turbine Internal Inspection

06/08/2009

26766225

Perform 43.000.019 Inside Torus / Inside DW / Outside DW

(Offline) (VT-3) Inspection

04/15/2017

303100100

Perform Internal Inspection of RCIC Turbine per NUE NE-

PJ-90-0373

04/20/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

34379073

Perform 43.000.019 Inside Torus / Inside Drywell / Outside

DW (Offline) Inspection

03/14/2014

34567763

Perform 43.137.001 Main Steam Safety Relief Valves

Setpoint Test

03/27/2014

37491496

Inspection of Div. 2 Torus Suction Strainer (RHR, CS, HPCI)

2/09/2015

37545467

Perform 24.137.02

11/09/2015

37545495

Perform 24.137.02

11/12/2015

37734090

Perform 43.137.001 Main Steam Safety Relief Valves

Setpoint Test

2/04/2015

38115948

Perform 44.210.059 ECCS/ADS/MDS D1 SRV Solenoid

Functional Test

11/06/2015

38442118

Desludge, Inspect, Repair - Torus Coatings Below Water

Level

04/28/2017

38574156

Perform 24.206.01 RCIC System Pump Operability and

Valve Test @ 1000 PSIG

2/09/2016

281891

Perform 43.401.510 LLRT Purge and Vent Test 1:

T4803F602, T4600F402, T4600F411

01/14/2016

282032

Perform 24.404.03 Sec-5.1 SGTS Valve Operability Test

04/13/2016

43040731

Lube, Clean Cooling Coils, Replace Belts

09/22/2016

43168864

Perform 44.030.400 ECCS HPCI/RCIC CST Level,

E41N061B, Calibration/Functional

10/28/2016

43579247

EDP-37272 R18 Installation RCIC High Point Vent

04/20/2017

43648553

Perform 24.404.03 SEC-5.2 SGTS Valve Operability &

Position Indication Verif.

01/08/2017

44066355

Perform 24.201.01 SRV Vacuum Breaker Operability

03/21/2017

44151810

Perform 24.137.02

04/13/2017

44153720

Perform 44.210.059 ECCS/ADS/MDS D1 SRV Solenoid

Functional Test

04/10/2017

268548

Perform 24.406.01 Sec-5.2 N2 Inerting Cold S/D Valve

Operability/Timing Test

04/02/2017

44417440

Perform 43.137.001 Main Steam Safety Relief Valves

Setpoint Test

06/22/2017

44883915

Check P1100 Cabinet Space Heaters & Thermostats for

Proper Operation

08/09/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

45151430

Inspection of Div. 2 Torus Suction Strainers (RHR, CS,

HPCI)

06/23/2017

275955

Perform 24.404.03 Sec-5.1 SGTS Valve Operability Test

10/09/2017

46582800

Perform 44.030.401 ECCS HPCI/RCIC CST Level,

E41N061D, Calibration/Functional

06/21/2018

46748956

Perform 24.202.01 HPCI Pump/Flow Test & Valve Stroke at

25 PSIG

06/03/2018

203637

Check Listed Cabinet Space Heaters & Thermostats for

Proper Operation

08/07/2018

47345713

Perform 24.201.01 SRV Vacuum Breaker Operability

09/26/2018

47435850

Penetration X-25 Exceeds it Leakage Limit - Failed LLRT

06/08/2017

47460525

Perform 44.210.059 ECCS/ADS/MDS D1 SRV Solenoid

Functional Test

10/15/2018

47490205

Perform 24.406.01 Sec-5.2 N2 Inerting Cold S/D Valve

Operability/Timing Test

10/05/2018

47490879

Perform 24.137.02 for T4901-F040 Only

04/16/2017

47500501

Perform 24.137.02

10/19/2018

47510304

Perform 24.202.04 HPCI Offline Auto Initiation and Time

Response Test

10/22/2018

47525996

Perform 24.202.02 HPCI Flow Rate Test at 165 PSIG

10/21/2018

47526001

Perform 24.206.04 Sec. 5.2 RCIC System Automatic

Actuation Test

10/26/2018

47642989

Perform Mini Periodic MOV Inspection (T4803-F602)

10/03/2018

47654752

Perform 24.404.03 Sec-5.1 SGTS Valve Operability Test

09/18/2018

48399139

Perform 43.401.510 LLRT Purge and Vent Test 1:

T4803F602, T4600F402, T4600F411

09/20/2018

48555968

Perform 24.202.08 Sec-5.2 (DW Press) HPCI LSFT & Pump

Operability at 1025 PSIG

08/23/2018

48693770

Extensive Coating Defects Identified During Torus

Underwater Inspection

01/04/2019

48693770

Extensive Coating Defects Identified During Torus

Underwater Inspection

09/22/2018

48693800

Inspect and Repair Torus Coating, Above Water

01/24/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

49309090

Perform 44.060.002 RCIC System Logic Functional Test -

Online

05/06/2019

50350374

Perform 24.206.01 RCIC System Pump Operability and

Valve Test @ 1000 PSIG

10/26/2018

D167030100

Perform MOV Thermal O/L Test - T4803F602 @ MCC 72B-

3A POS-5C-R

05/01/2009

E016150100

Disassemble Motor, Inspect and Clean in Accordance With

NE-6/6-EQMS.036

06/14/2006

T577090200

Replace Valve Seat per EQ Requirement Contained in LTR

NE-6.6-EQMS.118

01/07/2016