IR 05000333/2025002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000333/2025002
ML25219A001
Person / Time
Site: FitzPatrick 
Issue date: 08/07/2025
From: Sherlyn Haney
Division of Operating Reactors
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2025002
Download: ML25219A001 (1)


Text

August 7, 2025

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000333/2025002

Dear David Rhoades:

On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at James A. FitzPatrick Nuclear Power Plant. On July 31, 2025, the NRC inspectors discussed the results of this inspection with Alex Sterio, Site Vice President, and other members of your staff.

The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Sherlyn I. Haney, Acting Chief Projects Branch 1 Division of Operating Reactor Safety

Docket No. 05000333 License No. DPR-59

Enclosure:

As stated

Inspection Report

Docket Number:

05000333

License Number:

DPR-59

Report Number:

05000333/2025002

Enterprise Identifier: I-2025-002-0043

Licensee:

Constellation Nuclear

Facility:

James A. FitzPatrick Nuclear Power Plant

Location:

Oswego, NY

Inspection Dates:

April 1, 2025 to June 30, 2025

Inspectors:

E. Miller, Senior Resident Inspector

V. Fisher, Resident Inspector

H. Anagnostopoulos, Senior Health Physicist

B. Dyke, Operations Engineer

S. Veunephachan, Senior Health Physicist

Approved By:

Sherlyn I. Haney, Acting Chief

Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at James A. FitzPatrick Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

FitzPatrick began the inspection period operating at rated thermal power. On April 11, 2025, operators reduced reactor power to 65 percent to perform a planned replacement of the

'C' condensate booster pump motor, turbine valve testing, and control rod scram time testing.

On April 12, 2025, operators raised reactor power to 93 percent to enable continued maintenance of the 'C' condensate booster pump following turbine valve testing and control rod testing. On April 13, 2025, operators reduced reactor power to 84 percent to perform a control rod pattern adjustment. Following the control rod pattern adjustment and the C condensate booster pumps return to service, operators raised reactor power to rated thermal power. On June 13, 2025, operators reduced reactor power to 84 percent for a planned control rod pattern adjustment. Operators raised reactor power to rated thermal power the next day. FitzPatrick remained at, or near, rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated system configurations during a partial walkdown of the containment atmosphere dilution (CAD) system on June 17, 2025.

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the standby liquid control system on June 28, 2025.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Reactor building 369', fire area/zone IX/RB-1A on April 3, 2025
(2) West cable tunnel 258', fire area/zone IC/CT-1 on April 8, 2025
(3) Screenwell house and water treatment areas 235', 255' and 260', fire area/zone IB/SH-1 on May 15, 2025
(4) Cable spreading room 272', fire area/zone VII/CS-1 on May 20, 2025
(5) CAD shack 272', fire area/zone Yard CAD-1, CAD-2 on May 22, 2025

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated external flooding mitigation protections in manhole 1, the condensate storage tank south valve pit, and the condensate storage tank north valve pit on May 28, 2025.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness and performance of 93WE-1C, the 'C' emergency diesel generator (EDG) jacket water heat exchanger on June 3, 2025.

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam and the biennial written examinations completed on May 14, 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated operations personnel during a planned downpower to approximately 65 percent for a control rod pattern adjustment and turbine valve testing on April 11, 2025, and during a control rod pattern adjustment on June 6, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a simulator evaluation that included a loss of feedwater, a reactor water recirculation (RWR) seal failure and an unisolable main steam isolation valve leak on April 30, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Plant level events associated with a downpower on August 12, 2024, and for a feedwater heater tube rupture on April 8, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated risk work on 'B' EDG during planned maintenance on April 22, 2025
(2) Elevated risk work on high pressure coolant injection (HPCI) system during planned maintenance on April 28, 2025
(3) Elevated risk work on 'A' and 'C' EDGs during planned maintenance to replace emergency service water flow restrictors on May 5, 2025
(4) Emergent work during troubleshooting of the Class 1E 'A' 125 volt (V) direct current (DC) station battery due to a possible ground on the supply to the electro-hydraulic control system on May 14, 2025
(5) Emergent work associated with troubleshooting of the 'B' RWR flow unit due to a downscale failure on May 21, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (1 Sample)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Class 1E 'A' 125 V DC station battery following -27.5 V ground on April 22, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (9 Samples)

(1)93TI-3B, 'B' EDG jacket water outlet temperature element and thermowell replacement following a leak on April 23, 2025 (2)93EDG-B, 'B' EDG following planned maintenance on April 24, 2025 (3)23PCV-112, HPCI turbine lube oil pressure control valve following planned maintenance on April 28, 2025 (4)23PCV-12, HPCI trip system pressure control valve following planned maintenance on May 8, 2025 (5)

'A' RWR motor-generator set following planned replacement of the potentiometer on May 9, 2025

(6) Class 1E 'A' 125 V DC station battery ground troubleshooting of the electro-hydraulic control system DC power supply filter on May 15, 2025
(7) Class 1E 'A' 125 V DC station battery ground troubleshooting of the 71T-4 transformer overcurrent protection circuit on May 27, 2025
(8) Class 1E 'A' 125 V DC station battery ground troubleshooting of the automatic voltage regulator supply breaker 71DC-A4 and supply wiring to 345 kilovolt motor operated disconnect 71MOD-10031 on June 6, 2025
(9) Class 1E 'A' 125 V DC station battery ground troubleshooting of the automatic voltage regulator control and indication circuit on June 11 and 12, 2025

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) ISP-90-1A, 4KV Emergency 10500 Bus Undervoltage Relay (Degraded Voltage)

Calibration, on April 8, 2025

(2) ST-4N, High Pressure Coolant Injection (HPCI) Quick-start, Inservice, and Transient Monitoring Test (IST), on May 8, 2025

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) The inspectors evaluated the conduct of a routine FitzPatrick emergency response drill that included a hostile action, fuel damage and a failure of containment to isolate on June 10,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels, identifies the concentrations and quantities of radioactive materials, and assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Licensee surveys of potentially contaminated material leaving the radiologically controlled area
(2) Workers exiting the radiologically controlled area through personnel contamination monitoring equipment

Radiological Hazards Control and Work Coverage (IP Section 03.04) (2 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) Used resin liner transfer to storage cask
(2) Radiation protection lead shielding walkdown

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:

(1) Locked high radiation area, 'B' hopper room in reactor building 272' elevation
(2) Locked high radiation area, northeast condenser bay in reactor building 272' elevation
(3) Locked high radiation area, 'B' reactor water cleanup pump room in reactor building 300' elevation

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (5 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Area radiation monitor channel 16 (cleanup heat exchanger room entry, reactor building)
(2) Continuous air monitor S/N AMS-4-00913064 in reactor building 272' elevation
(3) Bench counter model 3030P S/N 0019275
(4) Portable area monitor WAM 500D in reactor building 326' elevation at the decay heat removal heat exchanger
(5) Personnel contamination monitor ARGOS-5AB S/N 0090742

Calibration and Testing Program (IP Section 03.02) (10 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Area radiation monitor channel 16 (cleanup heat exchanger room entry, reactor building)
(2) Continuous air monitor S/N AMS-4-00913064 in reactor building 272' elevation
(3) Bench counter model 3030P S/N 0019275
(4) Portable area monitor WAM 500D in the reactor building 326' elevation at the decay heat removal heat exchanger
(5) Personnel contamination monitor ARGOS-5AB S/N 0090742
(6) Telepole S/N 0025715
(7) E600 with REM Ball S/N 0022951
(8) G-M Frisker Ludlum L-177 S/N 0022942
(9) SAM-12 S/N 0091214
(10) Main steam line radiation monitor 17RM-251A

Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Off-gas stack flow transmitter (01-107FT-100)
(2) Containment high range radiation monitor 27RM-104A

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) For the period January 1, 2024 through December 31, 2024

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) For the period January 1, 2024 through December 31, 2024

===71152S - Semiannual Trend Problem Identification and Resolution

Semiannual Trend Review (Section 03.02)===

(1) The inspectors reviewed the FitzPatrick corrective action program to identify potential trends in human performance that might be indicative of a more significant safety issue.

71153 - Follow Up of Events and Notices of Enforcement Discretion Personnel Performance (IP Section 03.03)

(1) The inspectors evaluated the 'B' RWR flow unit downscale failure and the licensees performance on May 21,

INSPECTION RESULTS

Minor Performance Deficiency 71152S Semiannual Trend

Minor Performance Deficiency: The inspectors identified a trend associated with human performance issues. Issues included the following:

1. On September 8, 2024, as documented in the first quarter 2025 NRC inspection

report 05000333/2025001 (ML25133A193), the inspectors identified a Green non-cited violation for station personnels failure to follow a procedure step during a residual heat removal injection valve test during the September 2024 refuel outage.

The failure to follow the procedure resulted in an overthrust condition that required additional inspection and analysis. (Issue Reports (IRs) 04862298 and 04800066)

2. On December 19, 2024, the station identified a failure to perform surveillance ISP-30-

3, Containment Hydrogen/Oxygen Analyzer B Calibration. Specifically, Constellation staff did not recognize the required quarterly regulatory requirement prior to a preventive maintenance frequency change. The station entered Technical Requirement Manual (TRM) 3.0.C for the missed surveillance and conducted the surveillance successfully the next day. (IRs 04824953 and 04825048)

3. On March 12, 2025, maintenance staff did not lift the proper electrical lead prior to an

EDG test due to failing to stop when unsure about a procedure steps clarity. As a result, during the C EDG post-maintenance test run, the engine failed to reach proper speed. In addition, the inspectors identified a failure to complete a step to validate fuel injector linkage freedom of movement. The station corrected the procedure prior to the final post-maintenance test run and completed it successfully. In addition, maintenance staff validated that although the step was not complete, staff did validate fuel injector linkage was operating smoothly. (IR 04844796)

4. On May 1, 2025, the station identified a missed surveillance for the remote shutdown

panel due to a failure to generate a work order after a preventive maintenance task change. As a result, the station entered Technical Specification Surveillance Requirement 3.0.3 and performed the test the same day. The results of the test were successful. (IR 04862267)

5. On June 16, 2025, engineering staff failed to recognize a potential overstressed

condition for the reactor core isolation cooling steam supply outboard containment isolation valve, 13MOV-16. Specifically, following a weld repair under Engineering Change 642527, the American Society of Mechanical Engineers (ASME) Code B31.1 was not assessed to ensure compliance prior to implementation. Although the yield stress was exceeded, the ultimate yield stress was not, ensuring structural soundness of the repair. (IR 04872611)

6. On June 25, 2025, the inspectors identified a missed Offsite Dose Calculation Manual

(ODCM) surveillance that was not performed within its required frequency. The station failed to identify the required biennial regulatory requirement prior to a preventive maintenance frequency change. The station successfully performed the surveillance the same day. (IR 0487610)

Screening: The inspectors determined the performance deficiency was minor. Based on the overall results of the semiannual trend review, the inspectors determined that Constellation had generally identified adverse trends before they could become more significant safety problems. The inspectors independently evaluated the deficiencies noted above for significance in accordance with the guidance in IMC 0612, Appendix B, Issue Screening, and Appendix E, Examples of Minor Issues, and determined them to be minor, with the exception of issue

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 31, 2025, the inspectors presented the integrated inspection results to Alex Sterio, Site Vice President, and other members of the licensee staff.
  • On July 10, 2025, the inspectors presented the radiation monitoring instrumentation inspection results to Alex Sterio, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Procedures

EP-4

Boron Injection Using CRD System

FM-18A

Flow Diagram Drywell Inerting C.A.D. and Purge System 27

FM-21A

Flow Diagram Standby Liquid Control System 11

OP-17

Standby Liquid Control System

OP-37

Containment Atmosphere Dilution System

71111.05

Fire Plans

PFP-PWR02

West Cable Tunnel Elev. 258' Fire Area/Zone IC/CT-1

PFP-PWR11

Cable Spreading Room, Elev. 272' Fire Area/ Zone VII/CS-1

PFP-PWR28

Reactor Building Elev. 369' Fire Area/Zone IX/RB-1A

PFP-PWR34

Screenwell House and Water Treatment Area/Elev. 235',

255' and 260' Fire Area/ Zone IB/SH-1

PFP-PWR50

Containment Atmosphere Dilution (CAD) Shack, Elev. 272'

Fire Area/ Zone Yard CAD-1, CAD-2

71111.07A Procedures

ER-AA-340

GL 89-13 Program Implementing Procedure

Work Orders

05360649

71111.13

Corrective Action

Documents

04858059

04867575

04868062

Work Orders

261515

05172358

261516

05671309

71111.15

Corrective Action

Documents

04834397

04858059

Procedures

AOP-22

DC Power System A Ground Isolation

71111.24

Corrective Action

Documents

04821242

04821243

04859459

04859794

04861319

04862423

04862637

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

04862663

Procedures

ISP-90-1A

4KV Emergency 10500 Bus Undervoltage Relay (Degraded

Voltage) Calibration

ST-4N

HPCI Quick-Start, Inservice, and Transient Monitoring Test

(IST)

ST-9BB

EDG B and D Full Load Test and ESW Pump Operability

Test

28

Work Orders

04775630

05131950

05172358

05343997

05531241

05603182

05603524

05603525

05640517

05654679

71151

Procedures

LS-AA-2090

Monthly Data Elements for NRC ROP Indicator - Reactor

Coolant System (RCS) Specific Activity

71152S

Corrective Action

Documents

04844022

Procedures

ST-9BA

EDG A and C Full Load and ESW Pump Operability Test

ST-9R

EDG System Quick-Start Operability Test and Offsite Circuit

Verification

Work Orders

05626419

05631749

71153

Corrective Action

Documents

04867575