IR 05000313/2019004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000313/2019004 and 05000368/2019004
ML20030C514
Person / Time
Site: Arkansas Nuclear  
Issue date: 01/29/2020
From: John Dixon
NRC/RGN-IV/DRP/RPB-D
To: Dinelli J
Entergy Operations
References
EPID L-2019-004-0005 IR 2019004
Preceding documents:
Download: ML20030C514 (40)


Text

January 29, 2020

SUBJECT:

ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000313/2019004 AND 05000368/2019004

Dear Mr. Dinelli:

On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Arkansas Nuclear One, Units 1 and 2. On January 9, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. One of these findings involved a violation of NRC requirements. We are treating this violation as a non-cited violation consistent with Section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low safety significance is also documented in this report. We are treating this violation as a non-cited violation consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Arkansas Nuclear One.

If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Arkansas Nuclear One. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Reactor Projects

Docket Nos. 05000313 and 05000368 License Nos. DPR-51 and NPF-6

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000313 and 05000368

License Numbers:

DPR-51 and NPF-6

Report Numbers:

05000313/2019004 and 05000368/2019004

Enterprise Identifier: I-2019-004-0005

Licensee:

Entergy Operations, Inc.

Facility:

Arkansas Nuclear One, Units 1 and 2

Location:

Russellville, AR

Inspection Dates:

October 1, 2019, to December 31, 2019

Inspectors:

L. Carson, Senior Health Physicist

W. Cullum, Reactor Inspector

T. DeBey, Resident Inspector

N. Greene, Senior Health Physicist

C. Henderson, Senior Resident Inspector

R. Kopriva, Senior Reactor Inspector

D. Reinert, Reactor Inspector

W. Sifre, Senior Reactor Inspector

T. Sullivan, Resident Inspector

Approved By:

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Arkansas Nuclear One, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report Section: 71111.04Q.

List of Findings and Violations

Failure to Restore a Fire Barrier to Functional Prior to De-Posting a Fire Watch Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000313/2019004-01 Open/Closed

[H.5] - Work Management 71111.05Q The inspectors identified a Green finding and associated non-cited violation of Arkansas Nuclear One, Unit 1, License Condition 2.C.(8), Fire Protection, for the licensees failure to implement all provisions of the approved fire protection program. Specifically, the licensee failed to implement program procedures to restore a fire barrier to a functional status prior to de-posting an hourly fire watch and failed to identify a degraded fire barrier in accordance with documented inspection criteria.

Failure to Torque Temporary Power Supply Terminal Screws in accordance with Station Procedures and the Vendor Manual Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green FIN 05000313/2019004-02 Open/Closed

[H.5] - Work Management 71153 The inspectors reviewed a self-revealed, Green finding associated with the licensees failure to torque temporary power supply terminal screws in accordance with torque specifications contained in Procedure EN-MA-145, Maintenance Standard for Torque Applications,

Revision 9, and the vendor manual.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at full power. On October 5, 2019, the unit was shut down to begin Refueling Outage 1R28. On November 17, 2019, Unit 1 commenced a reactor startup and the reactor was made critical on November 18, 2019. The unit was returned to full power on November 22, 2019, where it remained for the rest of the reporting period except for minor power reductions in power to support scheduled surveillances.

Unit 2 began the inspection period at full power where it remained for the rest of the reporting period except for minor reductions in power to support scheduled surveillances.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 emergency diesel generator 2 crankcase pressure trip device on October 28, 2019
(2) Unit 1 train A low pressure injection/decay heat removal system on November 9, 2019
(3) Unit 1 spent fuel pool cooling system on December 12, 2019

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Unit 1 auxiliary building, 335 feet elevation, Fire Zone 162-A, Fire Area B-10, on October 15, 2019
(2) Unit 1 and Unit 2 control room envelope air conditioning unit VUC-9 loop seal degradation, Fire Zone 129-F and 1052, Fire Area B-1 and G, on October 21, 2019
(3) Unit 1 reactor building, Fire Zones 32-K, 33-K, 1063, 1064, 1065, 1066, and 1067, Fire Area J, on October 30, 2019
(4) Unit 1 computer and control rod drive equipment room, Fire Zone 160-B, Fire Area B-1, on November 17, 2019

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined, and accepted by reviewing the following activities from October 15, 2019, to October 23, 2019:

03.01.a - Nondestructive Examination and Welding Activities:

  • 01-029, Reactor Vessel Interior - Visual
  • 21-121, Makeup and Purification System Pipe to Pipe Weld - Ultrasonic Examination
  • 21-062, Makeup and Purification System Pipe to Pipe Weld - Ultrasonic Examination

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities:

  • The inspector reviewed a portion of the remote visual examination of the reactor vessel upper head penetrations. The examination was incomplete because the areas of interest were obscured by deposits caused by a leak of the nonsafety intermediate cooling water system. As a result, the licensee was unable to complete the required examination and will have to re-perform the examination during the next refueling outage. The inspectors reviewed the relief request submitted by the licensee (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19304A290) which was approved by the NRC on November 13, 2019, (ADAMS Accession No. ML19318D042).

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities:

  • CR-ANO-1-2018-01843 - Boric acid piling up on cable trays in the basement of the reactor building
  • CR-ANO-1-2019-02077 - Three injection block valves, two flow elements, one flow transmitter valve block and one flow orifice were observed having dry inactive white boron residue located at the packing or seal ring area
  • CR-ANO-1-2019-02609 - Boric acid leak found on letdown cooler outlet isolation valve CV-1216
  • CR-ANO-1-2019-02727 - Boric acid deposit was discovered in the packing area of pressurizer spray isolation valve RC-3
  • CR-ANO-1-2019-02757 - Boric acid deposit was discovered on the valve packing area of seal flow transmitter isolation valve PDT-1280

03.01.e - Problem Identification and Resolution:

  • The inspector reviewed 21 condition reports associated with inservice and operating experience issues and concluded that nondestructive examination/inservice inspection-related issues and operating experience are put into the corrective action program at low levels to ensure conditions and problems are identified.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 1 reactor shutdown for Refueling Outage 1R28 on October 5, 2019

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the Unit 1 licensed operator re-qualification scenario on December 19, 2019

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Unit 2 chemical and volume control system failures when in 50.65(a)(1) on October 22, 2019
(2) Unit 1 reactor building equipment hatch exceeding administrative local leak-rate test requirements on multiple tests on December 31, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Unit 1 and Unit 2 control room envelope air conditioning unit VUC-9 loop seal degradation on October 21, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (6 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Unit 1 emergency diesel generator 2 high crankcase trip during surveillance testing common cause operability on October 15, 2019
(2) Unit 1 and Unit 2 control room envelope air conditioning unit VUC-9 loop seal operability on October 21, 2019
(3) Unit 1 mode restraint operabilities on November 21, 2019
(4) Unit 1 reactor building spray system check valves BS-4A and BS-4B leakage operability on November 27, 2019
(5) Unit 1 reactor building Column 17 operability on December 9, 2019
(6) Unit 1 and Unit 2 startup transformer 2 and Unit 2 startup transformer 3 degraded voltage operability on December 9, 2019

71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)

The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for 10 CFR 50.59 from November 18-21, 2019:

(1) Engineering Change EC-51967, Cooling Capability of Switchgear Room Coolers 2VUC-2A, 2B, 2C, 2D with New Service Water Temperature Profile, Revision 0 (Evaluation)
(2) Engineering Change EC-61243, Tornado Missile Protection Features and Licensing Basis, Revision 1 (Evaluation)
(3) Engineering Change EC-78439, ANO-1 Cycle 29 Core Reload Evaluation, Revision 0. The inspectors reviewed the composition of the limited number of lead test assemblies (LTAs), placement of LTA in nonlimiting core locations, and Core Operating Limits Reports including the analytical methods that were previously reviewed and approved by the NRC (Evaluation)
(4) Engineering Change EC-45077, ANO Cask Transfer Facility, Revision 0 (Screening)
(5) Engineering Change EC-52059, Anchor Darling Wedge Pin Shear Stress Calculations, Revision 0 (Screening)
(6) Engineering Change EC-50092, Room 72 Floor Drain and Equipment Drain Flood Mitigation Modifications, Revision 0 (Screening)
(7) Engineering Change EC-44152, NE-0501 Source Range Fission Chamber Bypass due to Noise Susceptibility, Revision 1 (Screening)
(8) Engineering Change EC-66364, Emergency Diesel Generator Crank Case Over-pressure Switch Gasket and Plate Addition, Revision 0 (Screening)
(9) Engineering Change EC-67516, Removal of Unit 2 Door 260, Revision 0 (Screening)
(10) Engineering Change EC-49799, Temporary Modification to Remove 2P-32C RCP Axial Position 2ZIY-6066 from Service, Revision 0 (Evaluation)
(11) Engineering Change EC-58249, Cable Re-Routes and Interposing Relays NPFA 805 ANO Unit 1 Items S1-4, S1-7, S1-8, S1-24, S1-25 and S1-26 Base EC, Revision 0 (Evaluation)
(12) Engineering Change EC-66983, ANO-1 Emergency Feedwater (EFW) Pump Woodward Governor Controls Upgrade, Revision 0 (Evaluation)
(13) Engineering Change EC-80461, Fuel Thermal Conductivity Degradation in Loss of Coolant Accident (LOCA) Methodology, Revision 0 (Evaluation)
(14) Engineering Change EC-57619, Change Equipment Database (EDB) for valves 2PSV-2803A, 2PSV-2806A, 2PSV-2823A, and 2PSV-2826A to reclassify valves from safety-related to nonsafety-related, Revision 0 (Screening)
(15) Engineering Change EC-66585, TSR 1702-110 'B' Safety Injection Discharge - A shielding evaluation was requested to facilitate removal and replacement of shutdown cooling heat exchanger 2E-35B, Revision 0 (Screening)
(16) Engineering Change EC-70658, K-4A and K-4B Crankcase Pressure Change Trip Device Isolation Valve, with Child ECs 70659 and 70864, Revision 0 (Screening)
(17) Engineering Change EC-72501, Integrated Control System Reverse Engineered Module Change Evaluation for Input Buffer and Signal Lag Action Unit, Revision 0 (Screening)
(18) Engineering Change EC-72578, Replace Valve 2SV-5061-2 with a bolted bonnet Target Rock Model 97AA-001-1, Revision 0 (Screening)
(19) Engineering Change EC-76046, Unit 2 Emergency Diesel Generator Governor Upgrade (Train A) Child EC For MPU Bracket Installation Parent EC 73078, Revision 0 (Screening)
(20) Engineering Change EC-76269, P-36A, P-36B, AND P-36C Retainer Sleeve Spacer Equivalency - adds a spacer ring in between the retaining sleeve and mechanical seal sleeve, Revision 0 (Screening)
(21) Engineering Change EC-76707, 1R27 TSR 18-1-128 / 18-1-129 DH-17, DH-18 Replace EN-DC-218, PS-S-005, Revision 0 (Screening)
(22) Engineering Change EC-77219, Evaluation of HBD-14-18" Wall Thickness, Revisions 0 and 1 (Screening)

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (3 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1 core lead test assemblies loaded for Operating Cycle 29 on October 8, 2019
(2) Unit 1 turbine driven emergency feedwater pump train B steam admission valve temporary modification on November 7, 2019
(3) Unit 1 turbine driven emergency feedwater pump governor valve replacement to digital control on November 8, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post maintenance tests:

(1) Unit 1 and Unit 2 control room envelope air conditioning unit VUC-9 degraded loop seal repair on October 30, 2019
(2) Unit 1 emergency diesel generator exhaust stack replacement and lube oil cooler preventive maintenance on November 6, 2019
(3) Unit 1 and Unit 2 control room envelope penetration post-maintenance testing for cable installation on November 12, 2019
(4) Unit 1 containment liner repair post-maintenance test on November 13, 2019
(5) Unit 1 high pressure injection pump C rebuild post-maintenance testing on November 18, 2019
(6) Unit 1 turbine driven emergency feedwater pump governor valve replacement post-maintenance testing on November 22, 2019
(7) Unit 1 reactor building spray pump A and B lube oil cooler service water air operated inlet valve rebuild post-maintenance testing on December 12, 2019

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) Unit 1 Refueling Outage 1R28 on November 20, 2019

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 1 integrated leak rate surveillance testing on December 10, 2019
(2) Unit 2 train B main steam and feedwater isolation Channel 1 response time surveillance testing on December 10, 2019

Inservice Testing (IP Section 03.01) (1 Sample)

(1) Unit 1 high pressure injection pump C inservice test reference value determination following major pump maintenance on November 18, 2019

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Unit 1 train A core flood tank fill check valve MU-36A on October 21, 2019

FLEX Testing (IP Section 03.02) (1 Sample)

(1) Unit 1 and Unit 2 flex portable emergency diesel generators K11 and K12 surveillance testing on December 9,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 02.01) (1 Sample)

The inspectors evaluated radiological hazards assessments and controls.

(1) The inspectors reviewed the following:

Radiological Surveys

  • ANO-1910-01302, Unit 1 Reactor Building 354 feet elevation General Area
  • ANO-1910-01301, Unit 1 Reactor Building 335 feet elevation General Area
  • ANO-1909-00222, Unit 1 AUX 335 feet elevation General Area North End Room Number 45
  • ANO-1910-00068, Unit 1 AUX 335 feet elevation Drumming Station Room No. 2026

Risk Significant Radiological Work Activities

  • RWP 2019-1420, Remove/Replace Scaffold
  • RWP 2019-1421, Remove/Replace Insulation
  • RWP 2019-1430, Reactor Disassembly/Reassembly
  • RWP 2019-1432, Fuel Movement and Support
  • RWP 2019-1501, VCC-2C/2D Piping
  • RWP 2019-1902, P-32D Seal and Upper Thrust Bearing
  • RWP 2019-2056, Unit 2 Containment Power Entries for Inspection and Minor Maintenance Air Sample Survey Records
  • ANO-AS-092619-0298, Unit 1 AUX 335 feet elevation
  • ANO-AS-100619-0339, Unit 1 Reactor Auxiliary Building 401 feet elevation
  • ANO-AS-100719-0344, Reactor Auxiliary Building 404 feet elevation
  • ANO-AS-100919-0360, Unit 1 Reactor Auxiliary Building North Cavity
  • ANO-AS-101219-0397, Unit 1 Reactor Auxiliary Building 404 feet elevation
  • ANO-AS-101319-0406, Unit 1 AUX 386 feet elevation

Instructions to Workers (IP Section 02.02) (1 Sample)

The inspectors evaluated instructions to workers including radiation work permits used to access high radiation areas.

(1) The inspectors reviewed the following:

Radiation Work Packages (RWP)

  • RWP 2019-1430, Reactor Disassembly/Reassembly
  • RWP 2019-1432, Fuel Movement and Support
  • RWP 2019-1902, P-32D Seal and Upper Thrust Bearing
  • RWP 2019-2056, Unit 2 Containment Power Entries for Inspection and Minor Maintenance

Electronic Alarming Dosimeter Alarms

  • CR-ANO-C-2018-02066
  • CR-ANO-C-2018-03843
  • CR-ANO-1-2019-02993
  • CR-ANO-2-2018-03070
  • CR-ANO-2-2019-00530

Labeling of Containers

  • Various sealed containers in the Low Level Radwaste Building
  • Various waste drums stored in the Drumming Station and Radwaste Building

Contamination and Radioactive Material Control (IP Section 02.03) (1 Sample)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) The inspectors verified the following sealed sources are accounted for and are intact:
  • Source ID 49
  • Source ID 223
  • Source ID 724
  • Source ID 1210
  • Source ID 1211
  • Source ID 1468
  • Source ID 1798
  • Source ID 2552
  • Source ID 2553
  • Source ID 2612

Radiological Hazards Control and Work Coverage (IP Section 02.04) (1 Sample)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) The inspectors also reviewed the following RWP for areas with airborne radioactivity:
  • RWP 2019-1432, Fuel Movement and Support

High Radiation Area and Very High Radiation Area Controls (IP Section 02.05) (1 Sample)

(1) The inspectors evaluated risk-significant high radiation area and very high radiation area controls.

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 02.06) (1 Sample)

(1) The inspectors evaluated radiation worker performance and radiation protection technician proficiency.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Engineering Controls (IP Section 02.01) (1 Sample)

The inspectors evaluated airborne controls and radioactive monitoring.

(1) The inspectors reviewed the following:

Installed Ventilation Systems

  • Fuel Handling Area Ventilation Exhaust
  • Control Room Ventilation
  • Radwaste Area Ventilation

Temporary Ventilation System Setups

  • There was one temporary high-efficiency particulate air (HEPA) ventilation system available for observation in the Unit 1 containment area during this inspection.

Portable or Installed Monitoring Systems

  • Control Room Ventilation and Radiation Monitoring System
  • AMS-4 Spent Fuel Pool Area
  • AMS-4 Reactor Building/Containment Area Unit 1 Elevation 335 feet
  • AMS-4 Reactor Building/Containment Area Unit 1 Elevation 404 feet
  • Reactor Building/Containment Area Unit 1 Equipment Hatch

Use of Respiratory Protection Devices (IP Section 02.02) (1 Sample)

The inspectors evaluated the licensees use of respiratory protection devices by:

(1) Observing in-field applications; verifying the licensee validated the level of protection provided by the devices; inspecting the material condition of devices, reviewing records and certification of devices issued for use; reviewing the qualifications of workers that use the devices; and observing workers donning, doffing and testing devices.

The inspectors observed three operations personnel and three radiation protection technicians adequately don and doff self-contained breathing apparatus (SCBA).

The inspectors observed and inspected the material condition of SCBAs stored and staged near the control room, the fire brigade area, and operation support center for emergencies. The material conditions were determined to be adequate.

The inspectors verified that the plant breathing air systems, SCBA filling stations, and air compressors met or exceeded Grade-D air specifications.

The inspectors reviewed records and certification of devices issued for use and reviewed the qualifications of workers that use the devices.

The inspectors reviewed medical qualifications, respirator fit test records of several workers.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 02.03) (1 Sample)

The inspectors evaluated self-contained breathing apparatus program implementation.

(1) The inspectors reviewed the following:

Status and Surveillance Records for Self-Contained Breathing Apparatus

  • SCBA - Air Supply No. UEL-003, July 28, 2019
  • SCBA - Air Supply No. UEL-006, July 28, 2019
  • SCBA - Air Supply No. UEL-036, July 28, 2019
  • SCBA - Air Supply No. UEL-041, July 28, 2019

Self-Contained Breathing Apparatus Fit for On-Shift Operators and Health Physics Technicians

  • 1 Senior Reactor Operator, October 24, 2019
  • 2 Reactor Operators, October 24, 2019
  • 3 Senior Health Physics Technicians, October 24, 2019

Self-Contained Breathing Apparatus Maintenance Check

  • SCBA - Air Supply No. R-3176, July 3, 2019
  • SCBA - Air Supply No. R-3185, July 3, 2019
  • SCBA - Air Supply No. R-3206, July 3, 2019
  • SCBA - Air Supply No. R-3235, July 3, 2019 Compressed Air Quality Test
  • Eagle Air System Report No. 369034; August 2, 2019
  • Bauer Air System Report No. 369035; August 2,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS09: Residual Heat Removal Systems (IP Section 02.08)===

(1) Unit 1 residual heat removal systems (October 1, 2018, to September 30, 2019)
(2) Unit 2 residual heat removal systems (October 1, 2018, to September 30, 2019)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 cooling water support systems (October 1, 2018, to September 30, 2019)
(2) Unit 2 cooling water support systems (October 1, 2018, to September 30, 2019)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1)

(April 1, 2018, to September 30, 2019)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1)

(April 1, 2018, to September 30, 2019)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) Unit 1 and Unit 2 potential adverse trend in implementation of fatigue management program and corrective actions closed to work order backlog on December 9, 2019

Annual Follow-up of Selected Issues (IP Section 02.03) (3 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Unit 1 emergency feedwater steam admission valve CV-2663 push button failure on October 23, 2019
(2) Unit 1 and Unit 2 Siemens breaker anti-pump relay contact with high resistances extent of condition on November 21, 2019
(3) Unit 2 spent fuel pool lowering level due to failed cask loading pit seal on December 12, 2019

71153 - Followup of Events and Notices of Enforcement Discretion Personnel Performance (IP Section 03.03)

(1) Unit 1 spent fuel pool cooling pump B trip and licensee entry into spent fuel pool cooling abnormal procedure with reactor core in the spent fuel pool on October 22,

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71111.04Q This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Arkansas Nuclear One, Unit 1, Technical Specification 5.4.1.a, requires, in part, that written procedures be established, implemented, and maintained covering the applicable procedures in Appendix A to Regulatory Guide 1.33. Appendix A, Section 3.s.(2)(a), requires procedures for emergency power sources (e.g., diesel generators, batteries). The licensee established Procedure OP-1104.036, Emergency Diesel Generator Operation, Revision 82, for operation of the emergency diesel generators.

Contrary to the above, from September 2017 to September 2019, the licensee failed to maintain Procedure OP-1104.036 for operation of the emergency diesel generators.

Specifically, the licensee failed to establish a procedure verification step to ensure the crankcase pressure trip device was not in the trip condition prior to placing it into service, and that there was no indication of an emergency diesel generator positive crankcase pressure condition.

Significance/Severity: Green. The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was determined to be of very low safety significance (Green) because it

(1) did not represent a deficiency affecting the design or qualification of a mitigating structure, system, or component;
(2) did not represent a loss of system and/or function;
(3) did not represent an actual loss of function of at least a single train for more than its technical specification allowed outage time; and
(4) did not represent an actual loss of function of one or more nontechnical specification trains of equipment designated as high safety-significant in accordance with the licensees maintenance rule program for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Corrective Action References: Condition Report CR-ANO-1-2019-02219

Failure to Restore a Fire Barrier to Functional Prior to De-Posting a Fire Watch Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000313/2019004-01 Open/Closed

[H.5] - Work Management 71111.05Q The inspectors identified a Green finding and associated non-cited violation of Arkansas Nuclear One, Unit 1, License Condition 2.C.(8), Fire Protection, for the licensees failure to implement all provisions of the approved fire protection program. Specifically, the licensee failed to implement program procedures to restore a fire barrier to a functional status prior to de-posting an hourly fire watch and failed to identify a degraded fire barrier in accordance with documented inspection criteria.

Description:

On October 2, 2019, during a plant status walk-down of Arkansas Nuclear One, Unit 1, auxiliary building elevation 335 feet fire barrier penetrations contained in Fire Area B-10 of Fire Zone 162-A, the inspectors identified separation of the sealant around Fire Barrier 60-008 (FB-60-008). The licensee performed a walk-down to assess its condition to prevent the spreading of a fire from the Unit 1 auxiliary building stair well to the 335 feet elevation that contained the three safety-related high-pressure injection pumps. The licensee also determined there was separation of the sealant around Fire Barrier FB-60-008, and it was difficult to determine how far the separation penetrated the fire seal. Based on the identified condition the licensee declared Fire Barrier FB-60-008 nonfunctional and entered Technical Requirements Manual, Section 3.7.12, Fire Barriers, Action Statements A.3.1 and A.3.2, implemented an hourly fire watch under Fire Impairment 8556, and documented this deficiency in Condition Report CR-ANO-1-2019-02493.

The inspectors reviewed the surveillance history of Fire Barrier FB-60-008 and identified that it was declared nonfunctional in May 2016. The licensee documented this deficiency in Condition Report CR-ANO-1-2016-01522 and implemented an hourly fire watch under Fire Impairment 4265. Additionally, Condition Report CR-ANO-1-2016-01522 was closed to Work Order 446193 to repair Fire Barrier FB-60-008. Work Order 446193 was still in planned status as of October 2019, and the penetration remained unchanged from when the condition was identified in Condition Report CR-ANO-1-2016-01552. However, the hourly fire watch was de-posted in July 2016, and Fire Impairment 4265 was closed prior to Fire Barrier FB-60-008 being restored to functional status, which was not in accordance with Procedure OP-1000.120, ANO Fire Impairment Program, Revision 25, Section 6.3 prerequisites (i.e., the work order assigned to restore fire barrier functionality was completed).

Additionally, the repair of Fire Barrier FB-60-008 was assigned a Priority 3 in accordance with the licensee work management process, which required the licensee to restore Fire Barrier FB-60-008 to functional status around August 2016.

On September 5, 2018, a fire barrier surveillance was performed in accordance with Procedure OP-1405.016, Unit 1 Penetration Fire Barrier Visual Inspection, Revision 26, under Work Order 52746507 and was marked as satisfactory, without identifying the nonfunctional condition documented in Condition Report CR-ANO-1-2016-01522. However, Fire Barrier FB-60-008 did not meet three of the inspection criteria documented in Procedure OP-1405.016 at the time of the inspection, and it should have been declared as nonfunctional. The licensee documented the potential human performance gap associated with the performance of the fire barrier surveillance that did not identify the nonfunctional fire barrier in Condition Report CR-ANO-1-2019-02833.

Corrective Actions: The licensee implemented the required hourly fire watch under fire impairment and performed Work Order 532521 to restore Fire Barrier FB-60-008 to functional.

Corrective Action References: Condition Reports CR-ANO-1-2019-02493 and CR-ANO-1-2019-02833

Performance Assessment:

Performance Deficiency: The licensees failure to restore a nonfunctional fire barrier prior to de-posting an hourly fire watch was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the human performance attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the nonfunctional fire barrier coupled with the lack of a required fire watch could have resulted in a fire spreading from the Unit 1 auxiliary building stairwell to the 335 feet elevation that contained the three safety-related high-pressure injection pumps.

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. The inspectors assigned the finding to fire finding Category 1.4.1 and 1.4.4 using Inspection Manual Chapter 0609, Appendix F, 1, Fire Protection Significance Determination Process Worksheet, dated May 2, 2018, because the finding involved fire prevention and administrative controls and fire confinement. The inspectors determined that the finding had very low safety significance (Green) because the finding:

(1) did not increase the likelihood of a fire, delay detection of a fire, or result in a more significant fire than previously analyzed such that credited safe shutdown strategy could be adversely impacted; and
(2) the degraded fire confinement element continued to provide adequate fire endurance to prevent fire propagation through the fire confinement element given the combustible loading and location of equipment important to safe shutdown in the fire area of concern.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. Specifically, the licensee failed to effectively plan and execute work activities by incorporating risk insights, job site conditions, and coordinate with different groups to restore the nonfunctional Fire Barrier FB-60-008, within the required 90 days, prior to de-posting an hourly fire watch.

Enforcement:

Violation: License Condition 2.C.(8), Fire Protection, requires in part, Entergy Operations, Inc. (ANO-1) shall implement and maintain in effect all provisions of the approved fire protection program. Procedure OP-1000.120, ANO Fire Impairment Program, Revision 25, was established as part of the provisions of the approved fire protection program. Procedure OP-1000.120, Section 6.3, provides instructions for de-posting a fire watch if it was posted due to equipment failure, and the shift manager or designee was responsible for releasing the fire watch when the system or equipment was returned to service.

Contrary to the above, from July 12, 2016, to October 2, 2019, the licensee failed to implement all provisions of the approved fire protection program. Specifically, after a fire watch was posted due to equipment failure, the shift manager or designee failed ensure that the system or equipment was returned to service before releasing the fire watch in accordance with Procedure OP-1000.120. In particular, the individual released the fire watch prior to repair of the failed fire barrier and without the barrier being properly returned to service.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: Backlog of Condition Reports/Corrective Actions Closed to Work Management Process Semiannual Trend Review 71152

The inspectors reviewed the corrective action program documentation associated with the backlog of condition reports/corrective actions closed to the work management process. The inspectors reviewed the backlog associated with condition reports/corrective actions closed to the work management process, condition reports associated with this backlog, and the adverse condition analysis for Nuclear Independent Oversight (NIOS) quality assurance finding documented in Condition Report CR-ANO-C-2019-04254. The inspectors noted the following:

  • CR-ANO-C-2019-01330: The licensees problem identification and resolution-focused self-assessment identified a standard performance deficiency for the high number of condition reports closed to work orders without scheduled dates.
  • CR-ANO-C-2019-01541: In April 2019, the licensee identified that the backlog of adverse conditions closed to the work management system process had risen. The performance review group approved an aggregate performance issue on this issue, which was closed to work tracking actions associated with work order burn down curves. These actions remained open with a combined 25 extensions.
  • CR-ANO-C-2019-02072: In June 2019, the licensees NIOS identified that the required reviews of open condition reports associated with safety-related equipment and performance review group oversight work orders with condition reports closed to them where not performed consistently in accordance with the licensees corrective action program. The corrective action was to perform the review by January 2020.
  • CR-ANO-C-2019-04252: The licensee identified that multiple Priority 3 work orders have not been implemented in the next available system/component outage opportunity or have been scheduled beyond it. The licensees work management requires Priority 3 work orders be scheduled at the next available system/component outage within the cycle plan or based on a modified schedule.
  • CR-ANO-C-2019-04253: The licensee identified multiple condition reports closed to work orders that did not have scheduled completion dates. Others had scheduled completion dates that were in the past or were unrealistic dates. An example was Condition Report CR-ANO-2-2015-02479 that was closed to Priority 3 Work Order 38483 and was scheduled for October 10, 2606.

The adverse condition analysis documented in Condition Report CR-ANO-C-2019-04254 identified three causal factors and their associated corrective actions:

  • Causal Factor 1: Priority 3 work orders have not been scheduled in accordance with the work management program. Approximately 50 percent of the Priority 3 work orders either did not have a scheduled completion date or the dates were in the past.

This was contrary to scheduling requirements of the work management process. The corrective action is to schedule all Priority 3 work orders/work requests in accordance with the work management process and the 13-week cycle plan. This action is scheduled to be completed after the backlog review.

  • Causal Factor 2: The performance review group and the production department have not effectively managed the backlog of condition reports/corrective actions closed to the work management process, nor appropriately managed the risk associated with the backlog. The corrective action is to develop a burndown curve to track the backlog reduction and develop backlog metrics. The intent of this action is to allow the licensee to determine the status of the backlog and reduction efforts to provide support, challenge as necessary, and to be able to review a manageable sized backlog.
  • Causal Factor 3: The production department has scheduled backlog reviews, as required by the licensees work management process; however, the meeting has not been supported by the licensees organization as indicated by the multiple condition reports documenting the inability of the licensee to meet quorum for the backlog review. The corrective action is to perform a review of all the Priority 3, 4, 8, and 9 work orders with condition reports closed to them, in accordance with the work management process.

The inspectors noted the following areas of concern:

1. Work orders have not been scheduled in accordance with the work management

process, and a number of work orders have been in the backlog for greater than 3 years.

2. The performance review group and work management personnel have not effectively

managed the work order backlog, and appropriately managed the risk associated with the back log.

3. The work order backlog reviews have not been effective, because the licensees

organization has not fully supported the reviews.

4. The licensee has previously identified this issue during problem identification and

resolution self-assessment, Aggregate Performance Issue Review, and by NIOS. In each case the corrective action closes the condition reports to the work tracking action process (a non-corrective action program process) to review the work order backlog and perform the required backlog reviews. These issues where identified by the licensee in April 2019 and June 2019.

Failure to Torque Temporary Power Supply Terminal Screws in accordance with Station Procedures and the Vendor Manual Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity

Green FIN 05000313/2019004-02 Open/Closed

[H.5] - Work Management 71153 The inspectors reviewed a self-revealed, Green finding associated with the licensees failure to torque temporary power supply terminal screws in accordance with torque specifications contained in Procedure EN-MA-145, Maintenance Standard for Torque Applications, Revision 9, and the vendor manual.

Description:

On October 6, 2019, the licensee installed a temporary power supply to provide power to spent fuel pool pump B (P-40B) under Work Order 493512 to support maintenance activities for its primary power supply. Work Order 493512 directed maintenance personnel to implement Procedure OP-6030.110, Termination Splicing and Soldering of Cable and Wire, Revision 24, for the installation of pump P-40Bs temporary power supply. Specifically, Procedure OP-6030.110 provides directions to make the temporary power supply terminal set screw connections snug tight and to subsequently perform a wiggle test on the connections to ensure they are tight. This was contrary to the torque requirements of 90 to 100 inch-lbs specified in accordance with Procedure EN-MA-145 and the vendor manual.

On October 22, 2019, Unit 1 was in a defueled status with the reactor core being stored in the spent fuel pool in support of Refueling Outage 1R28 maintenance activities when pump P-40B tripped. Spent fuel pool pump A (P-40A) remained in service during the timeframe pump P-40B was tripped, providing uninterrupted cooling to the spent fuel pool, although at a reduced capacity. Licensee electricians discovered loose connections on the temporary power supply terminal set screws for all three phases of the lower portion of the overload heaters. This condition resulted in a loss of circuit continuity between the lugs and the terminals. The loose connections allowed heat to build up to the thermal overload limit for pump P-40B, causing it to trip. The licensee torqued the terminal connections in accordance with Procedure EN-MA-145 and the vendor manual, and pump P-40B was returned to service. During the timeframe pump P-40B was unavailable, spent fuel pool temperature rose from 110 to 120 degrees Fahrenheit (F); however, it remained below the safety analysis report design criterion of 150 degrees F. The licensee documented this deficiency in Condition Report CR-ANO-1-2019-03440 and performed an adverse condition analysis. The licensee identified one direct cause and causal factor:

  • Direct
Cause:

Pump P-40B temporary power supply terminal set screws had insufficient torque applied resulting in a high resistance and loss of circuit continuity between the lugs and the terminals.

  • Causal Factor: WO 493512 contained inadequate instructions to ensure pump P-40Bs temporary power supply terminal set screws where torqued to the required value of 90 to 100 inch-lbs.

The inspectors noted that Procedure EN-MA-145 provides torque values for electrical bus assemblies. Procedure EN-MA-145 states, This document applies to all bolted connections regardless of size and nonsafety-related electrical connections made via threaded fasteners. Procedure EN-MA-145 continues on to state the following, When a torque value cannot be determined from controlled drawings, vendor manuals, manufacturers specifications, engineering documents, or Attachment 9.11, the planner initiates a request to design engineering to provide the proper torque value for the application. The planner provides work order step text ensuring that the torque values, fastener material and size, torque pattern and specific assembly instructions are documented in the work order package. Paragraph 5.7, items [6] and [7] of Procedure EN-MA-145 state the following, Torque application values for various electrical bus bar combinations are provided in 9.12 or as per applicable site specific procedures or standards, and, Connections to terminal blocks and bolted splice connections using 1/4 inch diameter and smaller hardware shall be tightened to snug-tight and not torqued unless a torque value is specified in site procedures/drawings/specifications or vendor supplied documents. Check for tightness by applying light finger pressure to the terminal barrel in a clockwise (tightening)direction and verify no rotation of the terminal. The connections in question are size 5/16 inch.

Contrary to the above, the licensee failed to provide the required 90 to 100 inch-lbs torque value into work order instructions for pump P-40Bs temporary power supply terminal set screw connections in accordance with Procedure EN-MA-145 and the vendor manual.

Corrective Actions: The licensee updated pump P-40Bs temporary power supply installation model work order to include:

(1) the required torque specification of 90 to 100 inch-lbs for the terminal set screws;
(2) a post-maintenance testing requirement to perform in-service thermography testing after installation of the temporary power supply. Additionally, the licensee took steps to ensure Procedure OP-6030.110 aligns with the requirements of Procedure EN-MA-145.

Corrective Action References: Condition Report CR-ANO-1-2019-03440

Performance Assessment:

Performance Deficiency: The licensees failure to torque temporary power supply terminal screws in accordance with Procedure EN-MA-145 and the vendor manual was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the structure, system, and component performance attribute of the Barrier Integrity Cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the licensees failure to torque the temporary power supply terminal screws in accordance with Procedure EN-MA-145 resulted in the trip of spent fuel pool pump B and a 10 degree F rise in spent fuel pool temperature.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was determined to be of very low safety significance (Green) because it did not:

(1) adversely affect decay heat removal capabilities from the spent fuel pool causing the pool temperature to exceed the maximum analyzed temperature limit specified in the site-specific licensing basis;
(2) result from fuel handling errors, dropped fuel assembly, dropped storage cask, or crane operations over the spent fuel pool that caused mechanical damage to fuel clad and a detectible release of radionuclides;
(3) did not result in a loss of spent fuel pool water inventory decreasing below the minimum analyzed level specified in the site-specific licensing basis;
(4) affect the spent fuel pool neutron absorber, fuel bundle misplacement, or soluble boron concentration.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. Specifically, the licensee failed to provide the correct temporary power supply set screw torque value into instructions during the planning of WO 493512, because the licensee used the torque requirements contained in Procedure OP-6030.110, instead of the torque requirements contained in Procedure EN-MA-145 and the vendor manual.

Enforcement:

Inspectors did not identify a violation of regulatory requirements associated with this finding.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 23, 2019, the inspectors presented the Inservice Inspection Activities inspection results to Mr. J. Dinelli, Site Vice President, and other members of the licensee staff.
  • On October 25, 2019, the inspectors presented the Occupational Radiation Safety Cornerstone inspection results to Mr. R. Pitts, General Manager Plant Operations, and other members of the licensee staff.
  • On November 21, 2019, the inspectors presented the Evaluations of Changes, Tests, and Experiments (10 CFR 50.59) inspection results to Mr. J. Dinelli, Site Vice President, and other members of the licensee staff.
  • On January 9, 2020, the inspectors presented the integrated inspection results to Mr. J. Dinelli, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04Q Calculations

CALC-88-E-0098-

ANO-1 DBA Reanalysis

CALC-91-R-2013-

Service Water Performance Testing Methodology

CALC-95-R-0014-

DH Cooler Test Protocol

Corrective Action

Documents

CR-ANO-

1-2018-01722, 1-2019-02219, 1-2019-03439, 1-2019-03440,

1-2019-03447, 1-2019-03452

Drawings

M-217, Sheet 2

P&ID EDG K-4A (DG-1)

M-217, Sheet 3

P&ID EDG K-4B (DG-2)

M-232, Sheet 1

P&ID Decay Heat Removal System

108

Engineering

Changes

EC-70658

K-4A and K-4B EDG Crankcase Pressure Trip Device

Isolation Valve

EC-70659

K-4A EDG Crankcase Pressure Trip Device Isolation Valve

EC-70864

K-4B EDG Crankcase Pressure Trip Device Isolation Valve

Miscellaneous

ER 994916E101

Procedures

OP-1104.004

Decay Heat Removal Operating Procedure

131

OP-1104.036

Emergency Diesel Generator Operation

2, 83

OP-1309.016

Decay Heat Cooler Thermal Testing

Work Orders

WO 493512, 500672, 531004, 52712881, 52804684

71111.05Q Corrective Action

Documents

CR-ANO-

1-2016-01522, C-2019-04090

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

1-2019-02493, 1-2019-02833, 1-2019-04099, C-2019-04429

Drawings

M-210

Piping and Instrumentation Service Water

Miscellaneous

Fire Impairment

265, 8556

Procedures

OP-1000.120

ANO Fire Impairment Program

24, 25

OP-1405.016

Unit 1 Penetration Fire Barrier Visual Inspection

Work Orders

WO 446193, 52746507

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P

Corrective Action

Documents

CR-ANO-

1-2019-02577, 1-2018-01843, 1-2018-04927, 1-2019-01734,

1-2019-02077, 1-2019-02609, 1-2019-02620, 1-2019-02643,

1-2019-02675, 1-2019-02710, 1-2019-02726, 1-2019-02727,

1-2019-02729, 1-2019-02757, 1-2019-02766, 1-2019-02772,

1-2019-02838, 1-2019-02923, 1-2019-02924, 1-2019-02940,

1-2019-03094, 1-2019-03150, 1-2019-03174, 1-2018-04698,

1-2019-01574, 1-2019-01722, 1-2019-01823, 1-2019-02218,

Engineering

Changes

0000077083

Support MS-147 Functional with Locking Nuts Loose

Miscellaneous

1CAN041402

Request for Alternative from Volumetric/Surface Examination

Frequency Requirements of ASME Code Case N-729-1,

Arkansas Nuclear One, Unit 1, Docket No. 50-313, License

No. DPR-51

04/28/2014

1CAN061601

Request for Alternative from Volumetric/Surface Examination

Frequency Requirements of ASME Code Case N-729-1,

Arkansas Nuclear One, Unit 1, Docket No. 50-313, License

No. DPR-51

06/17/2016

1CAN071802

Inservice Inspection Summary Report for the Twenty-Seventh,

Refueling Outage (1R27), Arkansas Nuclear One - Unit 1,

Docket No. 50-313, License No. DPR-51

07/25/2018

Procedures

CEP-BAC-001

Boric Acid Corrosion Control (BACC) Program Plan

CEP-CII-003

Visual Examinations of Class MC Components

308

CEP-NDE-0255

Radiographic Examination of ASME, ANSI, AWS, API, AWWA

Welds and Components

CEP-NDE-0400

Ultrasonic Examination

CEP-NDE-0404

Manual Ultrasonic Examination of Ferritic Piping Welds

(ASME XI)

CEP-NDE-0423

Manual Ultrasonic Examination of Austenitic Piping Welds

(ASME XI)

CEP-NDE-0641

Liquid Penetrant Examination (PT) for ASME Section XI

CEP-NDE-0731

Magnetic Particle Examination (MT) for ASME Section XI

CEP-NDE-0901

VT-1 Examination

CEP-NDE-0902

VT-2 Examination

CEP-NDE-0903

VT-3 Examination

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CEP-NDE-0955

Visual Examination (VE) of Bare-Metal Surfaces

306

CEP-NDE-0965

Visual Welding Inspection ASME, ANSI B31.1

CEP-WP-002

Qualification, Development, and Control of Welding Procedure

Specifications

CEP-WP-003

Qualification and Control of Welders

CEP-WP-004

Control and Documentation of Welding Activities

CEP-WP-005

Control and Issuance of Welding Material

CEP-WP-GWS-1

General Welding Standard ASME/ANSI

CEP-WP-WIIR-1

Weld Inprocess Inspection Requirements

EN-DC-319

Boric Acid Corrosion Control Program (BACCP)

EN-DC-328

Entergy Nuclear Welding Program

SEP-BAC-ANO-

001

Boric Acid Corrosion Control Program Inspection and

Identification of Boric Acid Leaks for ANO-1 and ANO-2

71111.11Q Procedures

OP-1102.016

Power Reduction and Plant Shutdown

OP-1105.004

Integrated Control System

OP-1107.001

Electrical System Operations

24

71111.12

Calculations

CALC-ANO2-FP-

15-00001

NFPA 805 Monitoring Program Scoping

Corrective Action

Documents

CR-ANO-

1-2016-02355, 1-2018-03086, 1-2019-02481, 1-2019-02548,

1-2019-02586, 1-2019-03560, 1-2019-04092, 2-2016-03156,

2-2016-03178, 2-2019-01430, 2-2019-01432, 2-2019-01770,

2-2019-01771, C-2019-04424

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

2-2019-02300, 1-2019-04407

Procedures

EN-DC-357

NFPA Monitoring Program

OP-1003.015

ANO NFPA 805 Monitoring Program

OP-1015.002

Decay Heat Removal and LTOP System Control

OP-1015.036

Containment Building Closeout

OP-1305.037

Unit 1 Reactor Building Access & Ventilation Leak Rate

Testing

OP-1402.038

Unit 1 Equipment Hatch Opening, Closing, and Maintenance

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-2203.014

Alternate Shutdown

OP-2203.030

Remote Shutdown

OP-2203.049

Fires In Areas Affecting Safe Shutdown

OP-3305.001

Ops System Alignment Tests

Work Orders

WO 455290

71111.13

Corrective Action

Documents

CR-ANO-

C-2019-04090, C-2019-04130

71111.15

Calculations

CALC-11-E-0007-

ANO-2 Startup #3 and Unit 2 Auxiliary Millstone Studies

Corrective Action

Documents

CR-ANO-

1-2018-02589, 1-2018-03079, 1-2019-02219, 1-2019-02383,

1-2019-02446, 1-2019-02447, 1-2019-02448, 1-2019-02508,

1-2019-02916, 1-2019-03459, 1-2019-03627, 1-2019-03628,

1-2019-03667, 2-2019-02767, C-2019-04090, C-2019-04130,

C-2019-04137, C-2019-04191

Drawings

M-217, Sheet 2

P&ID EDG K-4A (DG-1)

M-217, Sheet 3

P&ID EDG K-4B (DG-2)

Engineering

Changes

EC-70658

K-4A and K-4B EDG Crankcase Pressure Trip Device

Isolation Valve

EC-70659

K-4A EDG Crankcase Pressure Trip Device Isolation Valve

EC-70864

K-4B EDG Crankcase Pressure Trip Device Isolation Valve

EC-77716

Disposition of Test Results and Check Valve Health for BS-4A

1R27

EC-84667

Clarification of IST Requirements for Spray Header Check

Valves, BS-4A and BS-4B

Engineering

Evaluations

ANO-290342-S04

Operability Evaluation of Unit 1 Reactor Building Column 17

for Dead+Live_Seismic

Miscellaneous

CES-02

ANO-1 General Structural Design Guide

SEP-ANO-1-IST-

ANO Unit 1 Inservice Testing Bases

SPEC-APL-C-501

Technical Specification for Earthquake Resistance Design of

Structures and/or Components Located in the Reactor

Building for the Arkansas Nuclear One Unit 1 Power Plant

Procedures

EN-OP-104

Operability Determination Process

OP-1104.036

Emergency Diesel Generator Operation

2, 83

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

WO 531004, 52271396, 52399617, 52508169, 52612456,

2733039, 52812299

71111.17T

Calculations

2-E-0021-01

Emergency Duty Cycle and Battery Sizing Calc

94-E-0043-01

ANO-1 Reactor Building Surface Areas for the Heat Sink and

Hydrogen Generation Calcs.

CALC-72

Auxiliary Bldg Floor Framing.

CALC-82-D-1111-

EC-66983. Room 112 Heat Load Assessment due to Addition

of New Q Equipment.

CALC-85-E-0053-

Fire Area 1-3 Combustible Loading Evaluation.

CALC-87-E-0026-

EFW Pump Room Temperature Profiles.

CALC-91-E-0120-

244

Seismic Qualification Review Summary for EFW Replacement

Tachometer SI-6601A (Panel C531).

CALC-92-E-0103-

ANO-1 Switchgear, Battery, DC, and Corridor 98 HVAC

Evaluation

CALC-92-E-0103-

ANO-1 4160V Switchgear, Battery, DC and Corridor 98

Alternate Ventilation System Analysis

CALC-93-SQ-

0002-247

Seismic Qualification Summary for MCC D15 & D25 and

Internals

CALC-ANO1-IC-

18-00001

To determine the heat rise within the Turbine Control Panel

provided as part of the Terry Turbine Governor Upgrade.

CALC-ANOC-CS-

15-00003

ANO Flood Protection Design Basis

CALC-ANOC-CS-

15-00012

ANO Flood Protection Room Evaluations - UNITS 1 and 2

Corrective Action

Documents

CR-ANO-

1-2016-01078, C-2018-01363, HQN-2018-01637, HQN-2018-

00717,

Drawings

8002891-1

Turbine Control Schematic

F

C-272

Equipment Support Details, EFW Turbine Control Panel

E-295

Schematic Diagram Emergency Feedwater Turbine MOV's

E-531

Connection Diagram Terminal Boxes

E-559

Connection Diagram Main Control Panel CO9

M-158, Sheet 1

Heating, Ventilating & Air Conditioning Aux. Building

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Switchgear Cable Supply and Relay Rooms Plans and

Sections EL. 372' 0"

M-158, Sheet 4

Heating, Ventilating & Air Conditioning Seismic Supports for

Emergency Cooling of Switchgear & Battery Rooms Area 4

EL. 372' 0"

M-263, Sheet 2

Piping & Instrument Diagram Aux. Building HVAC Elevation

2' 0"

M-263, Sheet 3

Piping & Instrument Diagram Aux. Building HVAC Elevation

386' 0"

Engineering

Changes

EC-58249

Cable Reroutes and Interposing Relays

EC-44152

NE-0501 Source Range Fission Chamber Bypass

EC-45077

ANO Cask Transfer Facility

EC-45808

EC Markup for CALC-92-E-0103-01 to Update Room 104 Free

Convection Model and Determine New Operator Actions

EC-49799

This temporary modification disconnects the RCP axial

position indication, ribbon

cable on the back of the module in 2C404. Evaluation #: 14-

2.

EC-49799

Process Applicability Determination - Screening. This

temporary modification disconnects the axial position

indication, ribbon cable on the back of the module in 2C404.

EC-49799.

Temporary Modification to Remove 2P-32C RCP Axial

Position 2ZIY-6066 from Service.

EC-50092

Room 72 Floor Drain and Equipment Drain Flood

EC-51967

Update Calc 91-E-0090-03 to Show Cooling Capability of

Switchgear Room

Coolers 2VUC-2A, 2B, 2C, 2D With New ECP SW

Temperature Profile

EC-52059

Anchor Darling DD 10 CFR Part 21 Wedge Pin Shear Stress

Calcs

EC-57619

Process Applicability Determination - Screening. Change

Equipment Database (EDB) for valves 2PSV-2803A, 2PSV-

2806A, 2PSV-2823A, and 2PSV-2826A to reclassify valves

from Safety Related to Non-Safety Related.

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EC-57619

Reclassification of Inter-Stage Relief Valves for the U2

Starting Air Compressors from Safety Related to Non-Safety

Related. (VALVES: 2PSV-2803A, 2PSV-2806A, 2PSV-2823A,

2PSV-2826A)

EC-58249

Cable Reroutes and Interposing Relays. Evaluation#: FFN-

2016-003

EC-58249

Process Applicability Determination - Screening. Cable

Reroutes and Interposing Relays

EC-61243

Tornado Missile Protection Features and Licensing Basis

EC-63697

Assessment of Reactor Building Corrosion as an Unqualified

Coating and Sump Debris Source

EC-66091

Change Design Basis Flooding Requirements for ANO-1 and

ANO-2 Decay Heat and ESF Vaults

EC-66364

EDG Crank Case Over-Pressure Switch Gasket and Plate

Addition CR-ANO-1-2016-2498

EC-66585

ANO-2 Shutdown Cooling Heat Exchanger Replacement

Project under the SGT, LLC Appendix B (QA) Program.

EC-66983

ANO-1 Emergency Feedwater (EFW) Pump Woodward

Governor Controls Upgrade. Evaluation # FFN-2018-003

EC-66983

Process Applicability Determination - Screening. ANO-1 EFW

Pump Woodward Governor Controls Upgrade

EC-66983

Arkansas Nuclear One (ANO) Emergency Feedwater Turbine

Governor Control System, Dresser-Rand, Curtis-Wright,

Engine Systems, Inc., Woodward, Vendor Manual for ANO

Unit 1 EFW Turbine Governor Control System, Vendor

Document ID: 85005G, 85017V1, 85017V2, 801283,

890038A, 82510, CB92387, CDS36294, 16540.

EC-67516

Remove Unit 2 Door 260

EC-68304

Revision of ANO-1&2 LOCA Dose Analysis to Reflect

December 2011 RADTRAD Error and DH Vault Leakage

EC-70658

Process Applicability Determination - Screening. Install a

valve on the upstream oil supply to the Emergency Diesel

Generator (EDG) crankcase pressure trip device on each

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EDG.

EC-72501

The Bailey 820 Analog Control, System is obsolete. The ANO

Electronic Resource Group (ERG) has reverse engineered

these modules and Engineering Change (EC) Evaluation

2501 approves them for use as an acceptable alternate

configuration.

EC-72578

Authorized valve 2SV-5061-2 to be replaced with a bolted

bonnet Target Rock Model 97AA-001-1.

EC-72713

HPSI Pump Seal Cooler Service Water Flow Requirements

EC-76046

Unit 2 Emergency Diesel Generator Governor Upgrade (Train

A)

EC-76269

This engineering change for Byron Jackson Horizontal

Double-Bearing Pump adds a spacer ring in between the

retaining sleeve and mechanical seal sleeve. It also

allows for 316SS to be used as an alternative material for all

impeller keys.

EC-76707

Temporary shielding calculation to support the activity of

Removing Valve DH-17

EC-77203

Removal of DR-200 in the Shift Manager's Office

EC-77219

Performance of an Engineering Change, Evaluation (EC

EVAL) to ensure reduction in wall thickness of Service Water

pipe HBD-14-18 does not exceed design limits.

EC-78350

Justification for Continued Operation Until Next Maintenance

Window Without Hardened Washers on P-36C

EC-78439

ANO-1 Cycle 29 Core Reload Evaluation

EC-80461

ANO-1 large break loss-of-coolant accident (LBLOCA) using

the latest NRC-approved LOCA methodology of BAW-

10192P-A that explicitly accounts for fuel thermal conductivity

degradation (TCD). Evaluation #: FFN-2019-001

EC-80461

Process Applicability Determination - Screening. ANO-1 large

break loss-of-coolant accident (LBLOCA) using the latest

NRC-approved LOCA methodology of BAW-10192P-A that

explicitly accounts for fuel thermal conductivity degradation

(TCD).

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EC-80488

Revise CALC-88-E-0100-27 for Unit 1 Core Flood System

EC-80594

TMOD to Support Online Work for 2PSV-5082. 2PSV-5082

Maintenance Could Create Voids That Are Problematic

Engineering

Evaluations

EC-66983 (FCR

81113)

EC66983 replaces the governor control system for the ANO 1

EFW Pump Turbine K-3. This document captures lengthy

mechanical evaluations (Section B.5) for Form 4 (P2E

7.001).

EC-66983 (FCR

81113)

EC66983 replaces the governor control system for the ANO 1

EFW Pump Turbine K-3. This document captures lengthy civil

evaluations (Section B.5) for Form 4 (P2E Attachment 7.001).

Procedures

1104.027

Battery and Switchgear Emergency Cooling System

EN-DC-115

Engineering Change Process

EN-LI-100

Process Applicability Determination

EN-LI-101

CFR 50.59 Evaluations

OP-1203.012N

Annunciator K16 Corrective Action

Self-Assessments LO-ALO-2019-

00026

Pre-NRC Focused Self-Assessment for the NRC Inspection of

CFR 50.59 (IP 71111.17T).

08/15/2019

71111.18

Calculations

ECH-NE-19-

000032

ANO-1 Cr-Coated Mark-B-HTP Lead Test Assembly (LTA)

Engineering Basis Summary

ECH-NE-19-

000033

ANO-1 Lead Coated Rods - Mechanical Review for

Operations

Corrective Action

Documents

CR-ANO-

1-2011-00147, 1-2011-00188, 1-2011-00194, 1-2011-00195,

1-2016-01517, 1-2017-02104, 1-2019-01847, 1-2019-02446,

1-2019-03079, 1-2019-03257, 1-2019-03738, C-2000-00076,

C-2011-00303

Drawings

E-295, Sheet 3A

Schematic Diagram Emergency Feedwater Turbine MOV's

Engineering

Changes

EC-27266

Operability Engineering Input for CR-ANO-1-2011-00147 PB-

2613 CV-2613

EC-66983

EC-78439

ANO-1 Cycle 29 Reload Core Lead Test Assemblies

EC-83800

Force CV-2663 into Auto by Removing Fuses F10 and F11 in

C09

Miscellaneous

ER-10090E101

Equivalency Evaluation for GE "CR2940" Model Selector

Switch

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

FS1-0045558-1.0

ANO1-29 Arkansas Nuclear One, Unit 1-Cycle 29 Reload

Report

08/08/2019

Procedures

EN-LI-101

CFR 50.59 Evaluations

17, 19

OP-1106.006

Emergency Feedwater Pump Operation

109

Work Orders

WO 263583, 381789, 445681, 499686, 529000, 529076,

2826120

71111.19

Corrective Action

Documents

CR-ANO-

1-2019-02446, 1-2019-02454, 1-2019-02466, 1-2019-02467,

1-2019-02476, 1-2019-02511, 1-2019-02592, 1-2019-02987,

1-2019-03446, 1-2019-03450, 1-2019-03552, 1-2019-03619,

1-2019-03756, 1-2019-03758, 1-2019-03769, 1-2019-03774,

1-2019-03779, 1-2019-03941, 1-2019-03945, 1-2019-03966,

1-2019-03973, C-2019-04090, C-2019-04130

Engineering

Changes

EC-80342

Fill ANO-1 Liner Plate Trough with Grout. Calculate Minimum

Thickness Requirement for ANO-1 Liner Plate

Miscellaneous

CEP-IST-4

Standard On Inservice Testing

309

ECT-66983-002

Post Modification Offline Test of EFW Digital Governor

Procedures

EN-DC-177

Control Habitability Program

EN-WM-107

Post Maintenance Testing

5, 6

OP-1000.120

ANO Fire Impairment Program

OP-1104.002

Makeup and Purification System Operation

OP-1104.005

Reactor Building Spray System Operation

OP-1104.036

Emergency Diesel Generator Operation

OP-1106.006

Emergency Feedwater Pump Operations

110

OP-1402.066

Month Inspection on Unit One Emergency Diesel

Generator Engine

OP-5120.523

Control Room Envelope Habitability Program

OP-6030.101

Installation of Penetration Seals

OP-6030.103

Installation of Concrete and NonShrink Grout

Work Orders

WO 444113, 448859, 465327, 499686, 504742, 510330, 532923,

2826120, 52841640, 52850596, 52857465

71111.20

Corrective Action

Documents

CR-ANO-

1-2017-01344, 1-2019-02417, 1-2019-02420, 1-2019-02468,

1-2019-02511, 1-2019-02625, 1-2019-03442, 1-2019-04082

Corrective Action

Documents

CR-ANO-

1-2019-02838, 1-2019-04226, 1-2019-04233, 1-2019-04234,

1-2019-04236

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Resulting from

Inspection

Drawings

M-230, Sheet 1

P&ID Reactor Coolant System

2

M-231, Sheet 1

P&ID Makeup and Purification System

116

M-231, Sheet 2

P&ID Makeup and Purification System

M-231, Sheet 3

P&ID Makeup and Purification System

M-232, Sheet 1

P&ID Decay Heat Removal System

108

Engineering

Changes

EC-ANO-69592-

2

Haul Path and Load Path Evaluation Associated with the

Placement of the Exhaust Stacks on the Unit 1 and Unit 2

EDG

Engineering

Evaluations

ER-ANO-2006-

0332-000

ANO-1 and ANO-2 Aux Bldg Susceptibility to Boric Acid

Corrosion

Miscellaneous

SEP-BAC-ANO-

001

Boric Acid Corrosion Control Program Inspection and

Identification of Boric Acid Leaks ANO-1 and ANO-2

STM 1-51-3

Fuel Transfer System

Procedures

EN-DC-319

Boric Acid Corrosion Control Program (BACCP)

EN-MA-118

Foreign Material Exclusion

OP-1005.002

Control of Heavy Loads

OP-1015.036

Containment Building Closeout

OP-1102.002

Plant Startup

2

OP-1102.008

Approach to Criticality

OP-1102.010

Plant Shutdown and Cooldown

OP-1102.016

Power Reduction and Plant Shutdown

OP-1104.004

Decay Heat Removal Procedure

131

OP-1203.028

Loss of Decay Heat Removal

OP-1502.004

Control of Unit 1 Refueling

OP-1504.005

Reactor Vessel Closure Head Stud Detensioning and

Removal

OP-1504.006

Unit 1 Reactor Vessel Closure Head Stud Detensioning and

Removal

OP-1504.007

Reactor Vessel Closure Head Removal and Storage

OP-1504.038

Removal and Replacement of the Core Support Assembly

Work Orders

WO 2960, 528927

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.22

Calculations

CALC-00-E-0023-

Unit 1 Appendix J Containment Maximum Allowed Leakage

Rate (La)

CALC-88-E-0098-

ANO-1 DBA Reanalysis

Corrective Action

Documents

CR-ANO-

1-2003-00760, 1-2019-02281, 1-2019-02446, 1-2019-02447,

1-2019-03752, 1-2019-03813, 1-2019-03927, 1-2019-03941,

1-2019-03945, 1-2019-04100, 1-2019-04102, 2-2019-00328,

2-2019-02477

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

1-2019-04088

Drawings

M-230, Sheet 1

P&ID Reactor Coolant System

2

M-236, Sheet 1

P&ID Reactor Building Spray and Core Flood System

Engineering

Changes

EC-73910

Baseline the Reference Values for the ANO1 IST Components

EC-84891

Engineering

Evaluations

ER-ANO-2003-

0564-000

Evaluation of the Unit 1 Appendix J Test Pressure (Pa) with

Allowances for Reactor Building Pressure Up to 3 psi

Miscellaneous

ANO1ILRT.19-

R191110B

Arkansas Nuclear One Unit 1 2019 ILRT Final Test Report

EN-OP-201-01

Flex Program Document

HES-02

Containment Leak Rate Testing Program

SEP-APJ-002

Arkansas Nuclear One Primary Containment Leakage Rate

Testing (Appendix J) Program Section

Procedures

OP-1104.002

Makeup and Purification System Operation

OP-1305.018

Local Leak Rate Testing - Type C

OP-1305.031

Integrated Leak Rate Testing

OP-2304.112

Plant Protection System Response Time Test Channel A

OP-2305.003

ESF Response Time Test

OP-3305.001

OPS System Alignment Tests

OP-4120.404

Unit 1 Integrated Leak Rate Test

OP-5120.400

Unit 1 Integrated Leak Rate Test

OP-5120.402

Unit 1 Primary Containment Leak Rate Running Total

Work Orders

WO 398744, 398746, 507360, 530402, 50573613, 52510650,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2541798, 52770826, 52852885, 52886070

71124.01

Corrective Action

Documents

CR-ANO-

1-2018-01336; 1-2018-01377; 1-2018-02231; 1-2018-02388;

1-2018-04973; 1-2019-01279; 1-2019-02993; 2-2018-00740;

2-2018-03070; 2-2018-03171; 2-2018-03258; 2-2018-03601;

2-2018-03880; 2-2019-00530; 2-2019-01431, C-2018-02066;

C-2018-02084; C-2018-03843; C-2019-01454

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

C-2019-04152

Miscellaneous

ANO Alpha Hazard Evaluation

10/15/2018

LHRA/VHRA Key Inventory

10/23/2019

ANO 1R28 Outage Status Report

10/25/2019

ANO-2018-0083

2018 Radiation Energy Distribution Evaluation

2/28/2019

ANO-2019-0011

ANO 2018 Annual Radiation Protection Report

2/28/2019

Att. 9.3 to EN-RP-

208

Quarterly Whole Body Counting Report

06/30/2019

Att. 9.4 to EN-RP-

143

Radioactive Seal Source Leak Test

2/29/2019

NRC Form 748

NSTS Annual Inventory Reconciliation Report

01/10/2019

Procedures

1601.502

Radioactive Material Control at Radwaste

EN-RP-100

Radiation Worker Expectations

EN-RP-101

Access Control for Radiologically Controlled Area

EN-RP-102

Radiological Control

EN-RP-108

Radiation Protection Posting

EN-RP-109

Hot Spot Program

EN-RP-121

Radioactive Material Control

EN-RP-131

Air Sampling

EN-RP-143

Source Control

13, 14

EN-RP-208

Whole Body Counting and In-Vitro Bioassay

Radiation Surveys ANO-1908-00356

Low Level Rad Waste

08/28/2019

ANO-1909-00218

Unit 1 AUX 335' General Area South End

09/14/2019

ANO-1909-00222

Unit 1 AUX 335' General Area North End

09/14/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ANO-1910-00068

Unit 1 AUX 335' EL Drumming Station Room Number 2026

10/03/2019

ANO-1910-00471

Unit 2 AUX 354 EL General Area

10/09/2019

ANO-1910-00692

Unit 2 AUX 317' General Area

10/12/2019

ANO-1910-01301

Unit 1 RX Building 335' General Area

10/23/2019

ANO-1910-01302

Unit 1 RX Building 354' General Area

10/22/2019

Radiation Work

Permits (RWPs)

2019-1027

Maintenance Activities Make-Up Pumps

2019-1420

Scaffold Activities in Non-High Radiation Areas

2019-1421

Insulation Activities (Non-LHRAs) - 1R28

2019-1430

Reactor Disassembly, Reassembly and Support Activities

During 1R28

2019-1432

De-fuel and Re-fuel the Reactor

2019-1432

De-fuel and Re-fuel the Reactor

2019-1480

Remove and Install the Core Barrel

2019-1501

Replace VCC-2C/2D Service Water Piping

2019-1902

Replace P-32D Seal Cartridge and P-32D Upper Thrust

Bearing

2019-2056

Unit 2 Containment Power Entries for Inspection and Minor

Maintenance

Self-Assessments LO-ALO-2018-

00063

Radiation Safety - Hazard Assessment, Airborne Controls, and

Performance Indicators

08/05/2019

QA-14/15-2017-

ANO-01

Quality Assurance Audit Report: Combined Radiation

Protection and Radwaste

11/16/2017

71124.03

Corrective Action

Documents

CR-ANO-

1-2018-00771, 1-2018-02145, 1-2018-04993, 2-2018-01418,

2-2018-01420, 2-2018-03288, C-2018-01793, C-2019-02193,

C-2019-02377, C-2019-03205, C-2019-03401

Procedures

1601.488

Eberline Model AMS-4 Beta Particulate Air Monitor Calibration 1

2104.007

Control Room Emergency Air Conditioning and Ventilation

3E4-1104.035

Fuel Handling and Radwaste Ventilation

3E4-1104.33

Reactor Building Ventilation

3E4-2104.035

Ventilation System Operations

EN-RP-310

Operation and Initial Setup of the Eberline Model AMS-4

Continuous Air Monitor

EN-RP-402

DOP Challenge Testing of HEPA Vacuums and Portable

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Ventilation Units

EN-RP-404

Operation and Maintenance of HEPA Vacuum Cleaners and

HEPA Ventilation Units

EN-RP-501

Respiratory Protection Program

EN-RP-502

Inspection and Maintenance of Respiratory Protection

Equipment

EN-RP-503

Selection, Issue and Use of Respiratory Protection Equipment

EN-RP-504

Breathing Air

Radiation Work

Permits (RWPs)

RWP 2018-1508

Remove and Replace CRDM

04/10/2018

Self-Assessments ANO-2019-0011

Arkansas Nuclear One 2018 Annual Radiation Protection

Report

2/28/2019

LO-ALO-2018-

00063

Radiation Safety - Hazard Assessment, Airborne Controls, and

Performance Indicator

08/05/2019

QA-14/15-2017-

AN0-01

Combined Radiation Protection and Radwaste

11/06/2017

Work Orders

WO 52746663

Perform Test on 2VEF-14 Fuel Handling Area Exhaust

08/29/2018

WO 52775596

Perform 18 Month Test of 2VSF-9 Control Room Filtration

System

01/31/2019

WO 52806599

Perform 18 Month Test of VEF-38A

05/22/2019

WO 52866018

Perform 18 Month Test 2VEF-15 Reactor Building

06/12/2019

71151

Miscellaneous

1Q2019

MSPI RHR & SW

2Q2019

MSPI RHR & SW

3Q2019

MSPI RHR & SW

4Q2018

MSPI RHR & SW

Procedures

EN-RP-101

Access Control for Radiologically Controlled Areas

Self-Assessments LO-ALO-2018-

00063

Radiation Safety - Hazard Assessment, Airborne Controls, and

Performance Indicators

08/05/2019

71152

Corrective Action

Documents

CR-ANO-

1-2011-00147, 1-2011-00188, 1-2011-00194, 1-2011-00195,

1-2016-01003, 1-2016-01004, 1-2016-01517, 1-2016-01769,

1-2017-02104, 1-2019-01847, 1-2019-02763, 1-2019-02987,

1-2019-03079, 1-2019-03581, 2-2012-02766, 2-2016-00097,

2-2017-01673, 2-2017-05811, 2-2019-00554, 2-2019-00557,

2-2019-00770, 2-2019-02306, 2-2019-02506, 2-2019-02509,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-2019-02571, C-2000-00076, C-2011-00303, C-2019-03563,

C-2019-04471

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

2-2019-03115

Engineering

Changes

EC-27266

Operability Engineering Input for CR-ANO-1-2011-00147 PB-

2613 CV-2613

EC-83800

Force CV-2663 into Auto by Removing Fuses F10 and F11 in

C09

Miscellaneous

20

Fire Impairment

CEP-IST-4

Standard On Inservice Testing

309

E-295, Sheet 3A

Schematic Diagram Emergency Feedwater Turbine MOV's

ER-10090E101

Equivalency Evaluation for GE "CR2940" Model Selector

Switch

Procedures

OP-1104.005

Reactor Building Spray System Operation

OP-1106.006

Emergency Feedwater Pump Operation

109

OP-2107.001

Electrical System Operations

130

Work Orders

WO 2768, 258162, 263583, 435034, 438206, 438561, 445681,

448429, 485002, 486111, 486213, 488334, 489290, 511214,

20860, 529000, 532923, 52843383, 52857465

71153

Corrective Action

Documents

CR-ANO-

1-2019-03439, 1-2019-03440

Procedures

OP-1203.050

Unit 1 Spent Fuel Pool Emergencies

Work Orders

WO 493512