IR 05000313/2019003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000313/2019003 and 05000368/2019003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2019001
ML19310H020
Person / Time
Site: Arkansas Nuclear  
Issue date: 11/05/2019
From: John Dixon
NRC/RGN-IV/DRP
To: Dinelli J
Entergy Operations
References
IR 2019001, IR 2019003
Preceding documents:
Download: ML19310H020 (32)


Text

November 5, 2019

SUBJECT:

ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000313/2019003 AND 05000368/2019003 AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT 07200013/2019001

Dear Mr. Dinelli:

On September 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Arkansas Nuclear One, Units 1 and 2. On October 3, 2019, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or significance of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Arkansas Nuclear One.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Arkansas Nuclear One. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Reactor Projects

Docket Nos. 05000313, 05000368, and 07200013 License Nos. DPR-51 and NPF-6

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000313, 05000368, and 07200013

License Numbers:

DPR-51 and NPF-6

Report Numbers:

05000313/2019003, 05000368/2019003, and 07200013/2019001

Enterprise Identifier: I-2019-003-0005 and I-2019-001-0084

Licensee:

Entergy Operations, Inc.

Facility:

Arkansas Nuclear One, Units 1 and 2

Location:

Russellville, AR

Inspection Dates:

July 1, 2019 to September 30, 2019

Inspectors:

L. Brookhart, Senior Spent Fuel Storage Inspector

T. DeBey, Resident Inspector

N. Fields, Health Physicist

M. Hayes, Operations Engineer

S. Hedger, Emergency Preparedness Inspector

C. Henderson, Senior Resident Inspector

J. Kirkland, Senior Operations Engineer

T. Sullivan, Resident Inspector

Approved By:

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection and an independent spent fuel storage installation inspection at Arkansas Nuclear One, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Install Correct Component and Perform Post Maintenance Testing Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000368/2019003-01 Open/Closed

[H.14] -

Conservative Bias 71111.19 The inspectors reviewed a self-revealed, Green finding and associated non-cited violation of Arkansas Nuclear One, Unit 2, Technical Specification 6.4.1.a, for the licensees failure to properly pre-plan and perform maintenance that can affect the performance of safety-related equipment. Specifically, the licensee failed to install the correct diodes for control element assembly hold bus 2C70 and to perform post-maintenance testing to demonstrate component functionality.

Failure to Promptly Identify and Correct a Condition Adverse to Quality Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000368/2019003-02 Open/Closed

[P.2] -

Evaluation 71152 The inspectors reviewed a self-revealed, Green finding and associated non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the licensees failure to promptly identify and correct conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances.

Specifically, the licensee failed to promptly identify and correct damage to Unit 2s reactor coolant pump C controlled bleed off piping in 2011, 2015, and 2017, when insulation was removed making the piping available for inspection.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000313/2018-004-01 Reactor Trip Due to the Loss of a Non-Vital 4160 Volt Bus.

71153 Closed LER 05000368/2019-001-00 Reactor Trip Due to a Reactor Coolant Pump Motor Failure.

71153 Closed

PLANT STATUS

Unit 1 began the inspection period at full power where it remained for the rest of the reporting period except for minor reductions in power to support scheduled surveillances.

Unit 2 began the inspection period in shutdown for Forced Outage 2F19-01, as a result of a fault in reactor coolant pump motor B, which started on May 26, 2019. On July 28, 2019, Unit 2 commenced a reactor startup and the reactor was made critical. The unit was returned to full power on July 30, 2019, where it remained for the rest of the reporting period except for minor reductions in power to support scheduled surveillances and for degraded condenser vacuum conditions.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 train A chemical and volume control system with charging pump C operating on August 6, 2019
(2) Unit 1 emergency diesel generator 2 fuel oil system with emergency fuel oil bunker T-57A on recirculation on August 16, 2019
(3) Unit 2 train A 4160 volt safety-related switchgear room coolers D and C on August 29, 2019

71111.05A - Fire Protection (Annual)

Annual Inspection (IP Section 03.02) (1 Sample)

(1) Unit 2 fire drill for a main generator hydrogen fire, Fire Zone 2200-M, Fire Area B-2, on August 26, 2019

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Unit 1 and Unit 2 fire risk management actions for common feedwater pump B unavailability for Fire Areas 2200-MM turbine building 372 feet nonvital switchgear area and Unit 2 transformer yard on August 15, 2019
(2) Unit 1 fire impairment for reverse osmosis unit installation in the drumming station for Fire Zones 34-Y, 2026-Y, and 20-Y-2 on August 16, 2019
(3) Unit 1 and Unit 2 alternate AC diesel generator building Fire Zone 3040 on September 3, 2019
(4) Unit 2 control room safety-related panels for Fire Zone 2002 and 2199-G, Fire Area G, on September 12, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Underground Cables (IP Section 02.02c.) (1 Sample)

The inspectors evaluated cable submergence protection in:

(1) Unit 1 and Unit 2 manhole 10 flood seals for the emergency diesel generator fuel oil vault on September 9, 2019

71111.07A - Heat Sink Performance

Annual Review (IP Section 02.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 2 train A 4160 volt safety-related switchgear room cooler D replacement on September 5, 2019

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered on August 15, 2019.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations

The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on July 8, 2019.

Annual Requalification Operating Tests

The inspectors evaluated the adequacy of the licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test

The inspectors evaluated the effectiveness of the licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2), and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security

The inspectors evaluated the ability of the licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations

The inspectors evaluated the effectiveness of remedial training conducted by the licensee and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions

The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator

The inspectors evaluated the adequacy of the licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

Problem Identification and Resolution

The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) Unit 2 short notice downpower to 96.6 percent reactor power for degraded main condenser A vacuum on August 7, 2019

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) Unit 1 licensed operator training scenario on September 12, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Unit 1 and Unit 2 common feedwater system and alternate AC emergency diesel generator availability during a loss of the 13.8 kV London line on July 9, 2019
(2) Unit 1 emergent work for train B turbine driven emergency feedwater pump steam admission valve failure to return to automatic during surveillance testing on August 1, 2019
(3) Unit 1 and Unit 2 planned emergency diesel generator pump maintenance with common feedwater pump B unavailable due to emergent corrective maintenance on August 7, 2019
(4) Unit 2 emergent work for train B main steam and feedwater isolation solid state relay failure for Channel 1 on August 27, 2019
(5) Unit 1 and Unit 2 emergent work for the auto transformer on August 29, 2019
(6) Unit 1 emergent work for emergency diesel generator 2 trip on high crankcase pressure during surveillance testing on September 9, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (5 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Unit 2 shutdown cooling system operability on July 18, 2019
(2) Unit 2 service water pump A high temperature winding operability on August 28, 2019
(3) Unit 2 containment cooling fan B mode restraint operability on August 29, 2019
(4) Unit 2 train B emergency feedwater system discharge valves to steam generators A and B failed to open operability on September 18, 2019
(5) Unit 1 and Unit 2 emergency cooling pond operability during service water bay B maintenance with a leaking sluice gate on September 19, 2019

71111.19 - Post-Maintenance Testing

Post Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post maintenance tests:

(1) Unit 2 reactor coolant pump A, B, C, and D control bleed off line replacement on July 22, 2019
(2) Unit 1 and Unit 2 common feedwater pump post maintenance testing following bearing replacement on August 16, 2019
(3) Unit 2 train B main steam and feedwater isolation solid state relay replacement for Channel 1 on August 27, 2019
(4) Unit 1 and Unit 2 alternate AC diesel generator temperature and pressure control valve replacement on September 3, 2019
(5) Unit 2 lowering control element assembly hold bus C2 voltage and two control element assemblies dropped on September 5, 2019
(6) Unit 1 emergency diesel generator 2 repair of the high crankcase pressure switch on September 9, 2019

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) Unit 2 Forced Outage 2F19-01, as a result of a fault on reactor coolant pump motor B, on July 29, 2019

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 2 control element assemblies drop time testing for operating for an extended period of time on the lower gripper and the hold bus on July 19, 2019
(2) Unit 1 engineering safeguards actuation system analog Channel 1, 2, and 3 monthly surveillance testing on August 16, 2019

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the maintenance and testing of the alert and notification system between April 1, 2017, and August 24, 2019.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Response Organization between April 1, 2017, and August 24, 2019. Inspectors also evaluated the licensees ability to staff their emergency response facilities in accordance with emergency plan commitments.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the 10 CFR 50.54(q) emergency plan change process and practices between April 1, 2017, and August 24, 2019. The evaluation reviewed screenings and evaluations documenting the implementation of this process. The reviews of the change process documentation do not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program between April 1, 2017, and August 24, 2019. The evaluation reviewed activations of the emergency plan, the conduct of drills and exercises, licensee audits and assessments, and the maintenance of equipment important to emergency preparedness.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Unit 2 resin leak in the drumming station with a reactor coolant pump shaft shear and loss of coolant accident on August 23,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (IP Section 02.12)===

(1)

(July 1, 2018 - June 30, 2019)

EP02: ERO Drill Participation (IP Section 02.13) (1 Sample)

(1) (July 1, 2018 - June 30, 2019)

EP03: Alert & Notification System Reliability (IP Section 02.14) (1 Sample)

(1) (July 1, 2018 - June 30, 2019)

MS06: Emergency AC Power Systems (IP Section 02.05) (2 Samples)

(1) Unit 1 (July 1, 2018 - June 30, 2019)
(2) Unit 2 (July 1, 2018 - June 30, 2019)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1 (July 1, 2018 - June 30, 2019)
(2) Unit 2 (July 1, 2018 - June 30, 2019)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (July 1, 2018 - June 30, 2019)
(2) Unit 2 (July 1, 2018 - Jun 30, 2019)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Unit 2 containment air cooler B auxiliary contact high resistance and C breaker trip due to relay failures on September 5, 2019
(2) Unit 2 reactor coolant pump C control bleed off line through wall leak on September 12, 2019

71153 - Followup of Events and Notices of Enforcement Discretion Event Followup (IP Section 03.01)

(1) Unit 2 lowering level in the spent fuel pool due to a failed air seal between the spent fuel pool and cask loading pit on August 29, 2019

Event Report (IP Section 03.02) (2 Samples)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000313/2018-004-01, Reactor Trip Due to the Loss of a Non-Vital 4160 Volt Bus, (ADAMS Accession No. ML19238A058)

The circumstances surrounding this LER are documented in Inspection Report 05000313/2019001 and 05000368/2019001 as FIN 05000313/2019001-03 and NCV 05000313/2019001-04.

(2) LER 05000368/2019-001-00, Reactor Trip Due to a Reactor Coolant Pump Motor Failure (ADAMS Accession No. ML19204A311)

The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensees ability to foresee and correct, and therefore, was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855 - Operation of an ISFSI Operation of an ISFSI

(1) The ANO independent spent fuel storage installation (ISFSI) consisted of four ISFSI pads containing two different cask designs. ANO had loaded 24 canisters of the Energy Solutions ventilated storage cask (VSC) VSC-24 design (Certificate of Compliance (CoC) No. 1007) from 1996 to 2003. Since that time, ANO had been loading HI-STORM 100S Version C overpacks containing either a multi-purpose canister (MPC)-24 or MPC-32 design. At the time of the routine inspection, the HI-STORM-100 ISFSI pads contained a total of 67 overpacks and the licensee was in the process of loading canister 68. ANO was currently loading canisters to the Holtec CoC No. 1014, Amendment 13, and Final Safety Analysis Report (FSAR),

Revision 18.

The inspectors evaluated the licensees ISFSI cask loading from July 22 through July 26, 2019. Specifically, the inspectors observed the following activities:

  • Heavy load lift by the vertical cask transporter (VCT) of the storage cask (HI-STORM) into the cask transfer facility (CTF) in preparation for stack-up operations.

The inspectors also evaluated the licensee's operational response and recovery actions associated with the small amount of helium leakage encountered when attempting to remove the removable valve operating assemblies from the MPC following initial helium backfill.

The inspectors performed a walkdown of all ISFSI radiologically controlled areas, including performing independent radiation surveys, a walkdown of the CTF, and a walkdown of the ISFSI haul path. The inspectors also performed a walkdown of the spent fuel floor for both Unit 1 and Unit 2, and a walkdown of the location of radiation monitors 2RITS-8750-1A and 2RITS-8750-1B. The inspectors performed a walkdown of the low profile transporter (LPT) in the turbine building train bay.

The inspectors evaluated the following:

  • Spent fuel selection for the four Unit 1 casks and the four Unit 2 casks in this loading campaign (HI-STORMs 61-68)
  • Compliance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 72.104 for calendar years 2017 and 2018
  • Fire hazards analyses and control of combustibles for ISFSI operations
  • Conditions for use of the cask supplemental cooling system
  • Selected radiological surveys of the ISFSI and dry fuel storage casks
  • Selected ISFSI condition reports
  • Quality assurance (QA) program implementation, including recent QA audits, surveillances, receipt inspection, and quality control activities
  • Compliance to technical specification for operational surveillance activities and FSAR required annual maintenance activities
  • Documentation of annual maintenance activities for heavy lifting components, which included special lifting devices, the sites cask handling crane (Auxiliary Building L-3 crane), and the sites VCT

60857 - Review of 10 CFR 72.48 Evaluations Review of 10 CFR 72.48 Evaluations

(1) The inspectors reviewed a list of 10 CFR 72.48 screenings performed by the licensee since October 2017. During this time period the licensee did not perform any 10 CFR 72.48 evaluations. The inspectors evaluated the following:
  • Selected licensee 10 CFR 72.48 screenings and associated changes, tests, or experiments
  • The process by which the licensee evaluates 10 CFR 72.48 screenings and evaluations performed by the Certificate of Compliance (CoC) holder
  • The licensee's change in CoC loading amendment from Amendment 5 to Amendment 13
  • Changes made to the licensees 10 CFR 72.212 Report (Revisions 11 and 12)since October

INSPECTION RESULTS

Failure to Install Correct Component and Perform Post Maintenance Testing Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events

Green NCV 05000368/2019003-01 Open/Closed

[H.14] -

Conservative Bias 71111.19 The inspectors reviewed a self-revealed, Green finding and associated non-cited violation of Arkansas Nuclear One, Unit 2, Technical Specification 6.4.1.a, for the licensees failure to properly pre-plan and perform maintenance that can affect the performance of safety-related equipment. Specifically, the licensee failed to install the correct diodes for control element assembly hold bus 2C70 and to perform post-maintenance testing to demonstrate component functionality.

Description:

In November 2018, during Refueling Outage 2R26, Work Order 52770071 was issued for replacement/refurbishment of the Unit 2 control element assembly (CEA) hold bus 2C70. The hold bus is designed to provide DC voltage to hold a CEA subgroup in a fixed reactor core location when the normal CEA power supply is unavailable. During the performance of the hold bus work, two diodes of the wrong type were installed. The postmaintenance testing (PMT) in Work Order 52770071, step 4.2, Section 6 (Attachment 1)required verification that the hold bus would hold a CEA subgroup. The PMT was not performed, but a note was added to the work order to indicate that it would be done during a potential forced outage and that the maintenance work order was updated to have a scheduled task prior to reactor startup. However, the testing was not done before the Unit 2 reactor startup following Refueling Outage 2R26. The presence of the two incorrect diodes ensured that transfer of CEA subgroups 1 through 10 to hold bus 2C70 would have resulted in a dropped CEA during power operations. This would have required immediate operator action to reduce power by 28 percent or greater in accordance with technical specifications and Procedure OP-2203.003, CEA Malfunction, Revision 25, and the potential recovery of the dropped CEA or the performance of a reactor shutdown to meet technical specification requirements.

On January 7, 2019, the licensee documented in Condition Report CR-ANO-2-2019-00041 that preventive maintenance on hold bus 2C70 was not fully completed. The condition report referenced two work orders that had not been completed, including Work Order 52770071.

This condition report was closed on January 14, 2019, with no additional corrective actions taken for hold bus 2C70.

On July 27, 2019, during Unit 2s Forced Outage 2FP19-01, the licensee performed a voltage adjustment to lower hold bus 2C70 voltage due to concerns with CEA drop times. The PMT for this maintenance was to place a CEA subgroup onto hold bus 2C70 as a functional test.

When the CEA subgroup was transferred to hold bus 2C70, two CEAs inserted into the reactor core. The licensees troubleshooting of the event determined two incorrect diodes were installed during Refueling Outage 2R26. The licensee entered this issue into the corrective action program as Condition Report CR-ANO-2-2019-02163 and performed a human performance analysis.

The licensees human performance analysis identified two causal factors:

  • Inadequate work instruction: Work Standard T23467 had vague open-ended repair instructions without materials identified for the repairs
  • Inadequate verification and validation practices: Craft performing the work did not verify that the parts being installed were the correct ones for that component/application

The human performance evaluation focused on why the incorrect diodes were installed, but did not determine why the licensee failed to perform the required post-maintenance test prior to reactor startup from Refueling Outage 2R26 and why no additional actions were taken when it was identified in Condition Report CR-ANO-2-2019-00041. The licensee entered this issue into the corrective action program as Condition Report CR-ANO-2-2019-02607 and performed an adverse condition analysis.

Corrective Actions: The licensee replaced the incorrect diodes and performed the required post maintenance testing prior to reactor startup from Forced Outage 2FP19-01. Additionally, the licensee revised the work standard for the hold bus refurbishment to include instructions and materials for the refurbishment.

Corrective Action References: Condition Reports CR-ANO-2-2019-00041, CR-ANO-2-2019-02163, CR-ANO-2-2019-02150, and CR-ANO-2-2019-02607

Performance Assessment:

Performance Deficiency: The licensees failure to properly pre-plan maintenance activities to ensure the correct components were installed and to perform the required post-maintenance testing was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have adversely impacted the equipment performance attribute of the Initiating Events Cornerstone and would have affected the associated cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, if a control element assembly subgroup was transferred to hold bus 2C70 during power operations, it would have resulted in one control element assembly dropping into the reactor core.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined that the finding had very low safety significance (Green) because the finding did not cause a reactor trip and the loss of mitigation equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition.

Cross-Cutting Aspect: H.14 - Conservative Bias: Individuals use decision-making-practices that emphasize prudent choices over those that are simply allowable. A proposed action is determined to be safe in order to proceed, rather than unsafe in order to stop. Specifically, the licensee failed to consider the risk-significance of the proposed action to defer postmaintenance testing following hold bus 2C70 diode replacement to ensure equipment functionality. Additionally, the licensee failed to consider the risk-significance of the proposed action to close Condition Report CR-ANO-2-2019-00041 with no additional actions to verify hold bus 2C70 functionality.

Enforcement:

Violation: Unit 2 Technical Specification 6.4.1.a requires, in part, that written procedures be established, implemented, and maintained covering the applicable procedures in Appendix A to Regulatory Guide 1.33. Appendix A, Section 9.a, states, in part, that maintenance that can affect the performance of safety-related equipment should be properly preplanned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances. Work Order 52770071, step 4.1, provides instructions to refurbish the hold bus 270 power supply, and step 4.2, Section 6 (Attachment 1), provides instructions to perform the post maintenance testing of the hold bus 2C70 power supply.

Contrary to the above, on November 2018, the licensee failed to properly preplan and implement maintenance that can affect the performance of safety-related equipment.

Specifically, the licensee failed to have adequate work instructions in Work Order 52770071, step 4.1, to install the correct diodes for hold bus 2C70 and implement step 4.2 to perform Section 6 (Attachment 1), post maintenance testing. This condition resulted in the installation of the incorrect diodes and the failure to perform post maintenance testing for hold bus 2C70.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Promptly Identify and Correct a Condition Adverse to Quality Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events

Green NCV 05000368/2019003-02 Open/Closed

[P.2] -

Evaluation 71152 The inspectors reviewed a self-revealed, Green finding and associated non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the licensees failure to promptly identify and correct conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances.

Specifically, the licensee failed to promptly identify and correct damage to Unit 2s reactor coolant pump C controlled bleed off piping in 2011, 2015, and 2017, when insulation was removed making the piping available for inspection.

Description:

In May 2019, during full power operations, Unit 2 operators observed an unexplained rise in the containment sump level which was not commensurate with the existing plant conditions. This prompted the operators to commence a reactor coolant system leak investigation. Prior to completion of the online leak investigation, Unit 2 experienced a reactor trip and entered Forced Outage 2FP19-01, as a result of a fault in reactor coolant pump motor B. During Forced Outage 2FP19-01, the licensee discovered that reactor coolant pump C controlled bleed off (CBO) piping was leaking due to a through wall crack in a socket weld. The licensee entered this issue into the corrective action program as Condition Report CR-ANO-2-2019-01365 and performed an adverse condition analysis.

The licensees adverse condition analysis determined the direct cause associated with the through wall leak on the CBO piping was a crack initiated from external damage from a thin cutting tool. The CBO piping was also subjected to vibration loads, which resulted in the propagation of a through wall crack due to cyclic fatigue. The causal factor was poor maintenance work practices that led to significant CBO piping damage which likely took place during 2008 when the removal/replacement of fibrous insulation on various lines was authorized due to damaged insulation. During the insulation removal/replacement, which occurred multiple times since 2008, the licensee did not document any observed damage to the CBO piping.

The licensee documented damage to reactor coolant pump C CBO piping insulation three times since 2011 (Condition Reports CR-ANO-2-2011-00567, CR-ANO-2-2015-03185, and CR-ANO-2-2017-01735), which provided them the opportunity to identify and correct the damage. In each instance, the licensee only addressed the replacement of the insulation, and no instructions were incorporated into the work orders which replaced the insulation to also inspect the underlying CBO piping. The licensee stated that damage to the CBO piping most likely occurred during 2008 when the removal/replacement of fibrous insulation on various lines was authorized due to damaged insulation; however, damage to the CBO piping could also have occurred when the insulation was replaced in 2011 and 2015, and during the permanent removal of the insulation in 2017. The licensees focus was the vibration-induced insulation damage, and the licensee did not thoroughly evaluate the issue to determine if the CBO piping was also damaged. Specifically, the licensee did not use its internal and external operating experience to thoroughly review the vibration-induced insulation damage to identify the CBO piping damage in 2011, 2015, or 2017.

The inspectors noted that NRC Information Notice (IN) 2007-21, Pipe Wear Due to Interaction of Flow Induced Vibration and Reflective Metal Insulation, provided operating experience to licensees that significant wear marks were observed on the outside wall of chemical and volume control system stainless steel piping due to interaction between the piping base metal and the installed reflective metal insulation. The NRC IN stated that the most probable cause of the abrasive wear was flow induced vibration combined with end cap to piping interaction. The NRC IN recommended that licensees review the information for applicability to their facilities and consider actions, as appropriate, to identify and address similar problems, up to and including the periodic removal of insulation to allow visual inspection for piping degradation. Additionally, the licensee had its own internal operating experience associated with damage identified on piping that interfaces with the reactor coolant system. In 1989, 1994, and 2009, the licensee identified cuts on piping (Condition Reports CR-ANO-1-1989-00110, CR-ANO-2-1994-00183, and CR-ANO-2-2009-02680) and, in 2014, gouges were noted during ASME inspections of charging piping to the reactor coolant pump B discharge cold leg (Condition Report CR-ANO-2-2014-01157).

Corrective Actions: The licensee replaced reactor coolant pump A, B, C, and D CBO lines and performed an extent of condition that identified one additional location that required replacement.

Corrective Action Reference: Condition Report CR-ANO-2-2019-01365

Performance Assessment:

Performance Deficiency: The licensees failure to promptly identify and correct a condition adverse to quality when removing reactor coolant pump CBO insulation was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the equipment performance attribute of the Initiating Events Cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the failure to promptly identify and correct the damage on the reactor coolant pump CBO piping resulted in a failed socket weld and a reactor coolant leak, which degraded the safety-related ASME Class II boundary.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding had very low safety significance (Green) because the finding after a reasonable assessment of degradation

(1) did not result in exceeding the reactor coolant system leak rate for a small loss-of-coolant accident; and
(2) likely did not affect other systems used to mitigate a loss-of-coolant accident resulting in a total loss of their function.

Cross-Cutting Aspect: P.2 - Evaluation: The organization thoroughly evaluates issues to ensure that resolutions address causes and extent of conditions commensurate with their safety significance. Specifically, the licensee failed to thoroughly evaluate CBO piping for damage, using internal and external operating experience, when insulation was removed due to vibration induced damage in 2011, 2015, and 2017.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations Part 50, Appendix B, Criterion XVI, Corrective Action, requires that measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected.

Contrary to the above, between February 2011 and September 2017, the licensee failed to promptly identify and correct a condition adverse to quality. Specifically, the licensee failed to promptly identify and correct damage to reactor coolant pump C control bleed off line piping which eventually led to a failure of the line and subsequent reactor coolant leak requiring a forced shutdown to make repairs in May 2019.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 11, 2019, the inspectors presented the Unit 1 biennial requalification inspection results to Mr. D. Pehrson, Senior Manager, Operations, and other members of the licensee staff.
  • On July 25, 2019, the inspectors presented the independent spent fuel storage installation inspection results to Mr. R. Anderson, Site Vice President, and other members of the licensee staff.
  • On August 15, 2019, the inspectors presented the Unit 1 biennial requalification inspection results to Mr. R. Martin, Superintendent, Operations Training, and other members of the licensee staff.
  • On August 15, 2019, the inspectors presented the Unit 2 annual requalification inspection results to Mr. R. Martin, Superintendent, Operations Training, and other members of the licensee staff.
  • On September 26, 2019, the inspectors presented the emergency preparedness program inspection telephonic exit with Mr. B. Patrick, Director, Regulatory Assurance and Performance Improvement, and other members of the licensee staff.
  • On October 3, 2019, the inspectors presented the integrated inspection results to Mr. J. Dinelli, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60855

Calculations

HI-2125213

Evaluation of MPC Lid Temperature under HI-TRAC Operation

at ANO

Corrective Action

Documents

CR-ANO-

1-2017-0355, 2-2019-02041, 2-2019-02065, C-2017-04091,

C-2017-04221, C-2017-04585, C-2017-04833, C-2018-00313,

C-2018-02422, C-2018-03438, C-2019-00149, C-2019-01006

07/24/2019

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

1-2019-02142, 1-2019-02404, C-2019-03052

Miscellaneous

CFR 72.212 Evaluation Report ANO Independent Spent

Fuel Storage Installation

Unit 2 Station Log, Tuesday July 23, 2019

07/23/2019

Procedures

1601.305

Radiation Monitoring Requirements for Loading and Storage

of the HI-STORM

013

203.012H

Annunciator 2K08 Corrective Action

039

3305.003B

Unit 2 Operations Rounds Required Readings

EN-DC-215

Fuel Selection for Holtec Dry Cask Storage

EN-RP-105

Radiological Work Permits

OP-1015.003B

Unit Two Operations Logs

OP-2104.007

Control Room Emergency Air Conditioning and Ventilation

076

OP-3403.005

HI-STORM 100 System Loading Operations

044

OP-3406.005

HI-STORM and HI-TRAC Transport Operations Using LPT,

VCT, and Holtec Railcar

018

OP-3406.006

Forced Helium Dehydration System Operations

011

Radiation Surveys ANO-1906-00461

Map Number DFS-H8 Location Hi-Storm Work Order #454379

06/24/2019

ANO-1907-00290

Map Number DFS-H8 Location Hi-Storm Work Order #515364

07/17/2019

ANO-1907-00291

Map Number DFS-H9 Location Hi-Storm Work Order #515364

07/17/2019

Radiation Work

Permits (RWPs)

RWP 2017-1061

Load Dry Fuel Storage MPC and Store in Hi-Storm with Unit 1

Fuel (Includes DFS support activities)

10/18/2017

RWP 2017-1063

Dry Fuel Storage Unit 1

03/07/2018

Work Orders

60855

WO 2367600, 52702275, 52800723

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60857

Engineering

Changes

2.48 Screening

and Applicability

Determinations

EN-DC-2015-008, EN-DC-215-009, EN-DC-215-010, EN-DC-

215-011, EC 46581, EC-ANO-000074974-0000,

07/24/2019

Procedures

EN-LI-100

Process Applicability Determination

71111.04Q Calculations

CALC-91-E-0090-

ANO-2 Switchgear, Battery, DC, Corridor 2104 Emergency

(Post-Accident) Temperature Evaluation

Corrective Action

Documents

CR-ANO-

1-2019-02012, 2-2019-01429, 2-2019-01430, 2-2019-01432,

2-2019-01881, 2-2019-01887

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

C-2019-02993

Drawings

M-217, Sheet 1

Piping and Instrument Diagram Emergency Diesel Generator

Fuel Oil Storage

Engineering

Changes

EC 20198

ANO-2 Switchgear, Battery, DC, Corridor 2104 Emergency

(Post-Accident) Temperature Evaluation

EC 69053

2VUC-2C Cooling Coil Casing Configuration Changes

EC 83577,

Sheet 1

2VUC-2D Cooling Coil Replacement - Vendor Flange Material

Change 2HCC-259-3

Procedures

EN-OP-102

Protective and Caution Tagging

OP-1104.023

Diesel Oil Transfer Procedure

OP-1104.036

Emergency Diesel Generator Operation

OP-1203.012A

Annunciator K01 Corrective Action

OP-2104.035

Ventilation System Operations

OP-2203.012U

Annunciator 2E12 Corrective Action

OP-2305.018

Underground EDG F.O. Tank 2T-57A/B Recirculation and

Cleanup

71111.05A

Corrective Action

Documents

CR-ANO-

C-2019-03123

Fire Plans

PFP-U2

Unit 2 Prefire Plans

Miscellaneous

FBDRL-2019-14

Fire Drill

Procedures

OP-1903.010

Emergency Action Level Classification

OP-2203.034

Fire or Explosion

71111.05Q Calculations

CALC-95-R-

Basis Requirements for the Component Database on Station

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

00024-01

Doors and Hatches

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

C-2019-02986

Fire Plans

FZ-3040

Fire Zone Detail Alternate Generator Building - Area AGB

354

FZ-2002

Fire Zone Detail Control Room, Area G, Fire Zone 2199-G

PFP-U1

Unit 1 Prefire Plan

Miscellaneous

ER-ANO-2004-

230-011

Add Reverse Osmosis Unit to Fire Zone 2026-Y

ER-ANO-2004-

0619-001

RO Unit Watch Requirements

Fire Impairments

8395, 8396, 8397

Procedures

COPD-024

Risk Assessment Guidelines

OP-1000.120

ANO Fire Impairment Program

Work Orders

WO 2842614

71111.06

Calculations

CALC-ANOC-CS-

15-0003

ANO Flood Protection Design Basis

Corrective Action

Documents

CR-ANO-

1-2009-02250, 1-2019-00521, 1-2019-00911, 1-2019-01310,

1-2019-01581, C-2019-00907, C-2019-01773, C-2019-01976

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

C-2019-03310

Engineering

Changes

EC 33613

Conduit Internal Water Seal

EC 57218

External Flooding Protection Design Basis

Miscellaneous

CFSD-100

BDBEE/ELAP Emergency Response

CFSG-005

Initial Assessment and Flex Equipment Staging

Procedures

OP-1203.025

Natural Emergencies

OP-2203.008

Natural Emergencies

ULD-0-TOP-17

ANO Flooding

Work Orders

WO 374472, 521304, 525350, 525777

71111.07A

Corrective Action

CR-ANO-

2-2016-02844, 2-2017-01145, 2-2017-03648, 2-2019-00486,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

2-2019-01881, 2-2019-01887,

Engineering

Changes

EC 69053

2VUC-2C Cooling Coil Casing Configuration Changes

EC 83577,

Sheet 1

2VUC-2D Cooling Coil Replacement - Vendor Flange Material

Change 2HCC-259-3

Miscellaneous

Cooling Coil Casing Configuration

Procedures

EN-MA-145

Maintenance Standard for Torque Applications

Work Orders

WO 28032

71111.11A

Miscellaneous

Unit 2 Annual Exam Results

71111.11B

Corrective Action

Documents

CR-ANO-

1-2018-01260, 1-2018-03238, 1-2018-03611, 1-2018-04206,

1-2018-04957, 1-2019-00756, 1-2019-01164, 1-2019-01480,

1-2019-01635

Miscellaneous

ANO1 Cycle 28 Core Reload Test

ANO1 Cycle 28 Simulator Operability Test

Unit 1 Licensed Operator 2018-2019 Requalification Cycle

Curriculum (Sample Plan

Week 3 ANO Unit 1 2019 RO Biennial Requalification Exam

Week 3 ANO Unit 1 2019 SRO Biennial Requalification Exam

ANO Unit 1 Annual and Biennial Exam Results

A1JPM-RO-

AOP01

Perform RO #1 Follow-up Actions for Remote Shutdown, Aux

Feedwater Pump Available

A1JPM-RO-

AOP39

Respond to Loss of Instrument Air Pressure

A1JPM-RO-

AOP41

Perform Actions for an Inadvertent Actuation of ESAS

A1JPM-RO-

AOP42

Fire Affecting Safe Shutdown: Outside AO Actions (Fire

Area C)

A1JPM-RO-

ED017

Perform Transfer of D11 from Normal Supply to Emergency

Supply Using Local Controls at D01

A1JPM-RO-

EDG11

Reset Emergency Diesel Generator #2 Overspeed Trip

Mechanism

A1JPM-RO-

EFIC2

Perform EFW Pump (P-7A or P7B) Suction Transfer to

Service Water

A1JPM-RO-

EOP10

Perform Actions Required to Correct Inadequate Core Cooling

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

A1JPM-RO-

EOP13

Emergency and Abnormal Operations

A1JPM-RO-

EOP22

Respond to Degraded Power (Verify both EDGs supplying

associated ES buses with proper voltage, frequency and

loading)

A1JPM-SRO-

EAL09

Classify an Emergency Event

A1JPM-SRO-

EAL14

Classify an Emergency Event

ANSI/ANS-3.4-

1983Property "ANSI code" (as page type) with input value "ANSI/ANS-3.4-</br></br>1983" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process.

Medical Certification and Monitoring of Personnel Requiring

Operator Licenses for Nuclear Power Plants

SES-1-007

Dynamic Simulator Scenario Week 5

SES-1-030

Dynamic Simulator Scenario Week 4

SES-1-036

Dynamic Simulator Scenario Week 4

SES-1-047

Dynamic Simulator Scenario Week 5

TQF-214-71111

Assessment Plan for Licensed Operator Requalification (LOR)

Program Pre-71111.11 Assessment

Procedures

1063.008

Operations Training Sequence

DG-TRNA-015-

EXAMSEC

Simulator Exam Security Guidelines

EN-TQ-114

Licensed Operator Requalification Training Program

Description

EN-TQ-201-04

SAT - Implementation Phase

EN-TQ-202

Simulator Configuration Control

TQF-201-IM05

Remedial Training Plan

71111.11Q Corrective Action

Documents

CR-ANO-

2-2019-02295

Procedures

EN-OP-115

Conduct of Operations

OP-1202.008

Blackout

OP-1202.012

Repetitive Tasks

OP-1203.045

Rapid Plant Shutdown

71111.13

Corrective Action

Documents

CR-ANO-

1-2017-02104, 1-2019-01847, 1-2019-02219, 2-2019-02477,

C-2017-04125, C-2019-01042, C-2019-02108, C-2019-02428,

C-2019-02429, C-2019-02430, C-2019-02431, C-2019-02452,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

C-2019-02485, C-2019-02486

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

C-2019-02877

Drawings

E-4, Sheet 2

Single Line and Relay Metering Diagram Common Feed

Water 4.16 kV Switchgear Bus A-15

E-4, Sheet 3

Single Line and Relay Metering Diagram Common Feed

Water 4.16 kV Switchgear Bus A-19

M-217, Sheet 2

P&ID EDG K-4A (DG-1)

M-217, Sheet 3

P&ID EDG K-4B (DG-2)

Engineering

Changes

EC 70658

K-4A and K-4B EDG Crankcase Pressure Trip Device

Isolation Valve

EC 70659

K-4A EDG Crankcase Pressure Trip Device Isolation Valve

EC-70864

K-4B EDG Crankcase Pressure Trip Device Isolation Valve

Procedures

COPD-024

Risk Assessment Guidelines

58, 68

EM-MA-125

Troubleshooting Control of Maintenance Activities

EN-DC-128

Fire Protection Impact Reviews

EN-OP-119

Protected Equipment Postings

EN-WM-104

On Line Risk Assessment

OP-1104.036

Emergency Diesel Generator Operations

OP-1106.007

Common Feedwater System

OP-1107.001

Electrical System Operations

23

OP-1203.046

Loss of Load Center

OP-2104.037

Alternate AC Diesel Generator Operations

OP-2202.010

Standard Attachments

OP-2203.012D

Annunciator 2K04 Corrective Action

OP-2203.012L

Annunciator 2K12 Corrective Action

OP-2203.012Z

Annunciator 2C435 Corrective Action

OP-2203.054

Abnormal Grid

Work Orders

WO 530402, 531004, 5283255, 52798239,

71111.15

Calculations

CALC-93-D-5015-

Unit 1 Intake Structure Natural Convection-GOTHIC Model

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CALC-93-R-1006-

Unit 1 Intake Structure Environmental Temperature Study

CALC-M-3600-

139

Intake Structure Critical Ambient Temperature

Corrective Action

Documents

CR-ANO-

1-2018-02614, 1-2019-01897, 1-2019-02029, 1-2019-02304,

2-2018-00949, 2-2019-01372, 2-2019-01373, 2-2019-01374,

2-2019-01687, 2-2019-01861, 2-2019-01875, 2-2019-01887,

C-2019-00310

Corrective Action

Documents

Resulting from

Inspection

CR-ANO-

1-2019-01903

Drawings

E-2014, Sheet 3

Single Line Diagram 480 Volt Motor Control Centers 2B53

E-2361 Sheet 1A

Schematic Diagram Containment Cooling Fan 2VSF1B

M-217, Sheet 2

P&ID EDG K-4A (DG-1)

Engineering

Changes

EC 83577

EC 83885

P-4A SW Winding Temp

Procedures

OP-1015.008

Unit 2 SDC Control

OP-1015.048

Shutdown Operations Protection Plan

OP-2104.029

Service Water System Operations

115

OP-2106.006

Emergency Feedwater Operations

OP-2305.003

ESF Response Time Test

OP-2305.062

SW System Flow Testing

Work Orders

WO 484566, 527146, 528032-01, 531004, 527962, 501701,

2813296

71111.19

Corrective Action

Documents

CR-ANO-

1-2019-02219, 2-2019-01374, 2-2019-01743, 2-2019-02104,

2-2019-02136, 2-2019-02260, 2-2019-02477

Miscellaneous

Flowserve Memo

06/27/2017

Procedures

OP-1104.036

Emergency Diesel Generator Operations

OP-1106.007

Common Feedwater System

OP-2104.037

OP-2304.037

Unit 2 Plant Protection System Channel A Test

OP-2304.112

Plant Protection System Response Time Test Channel A

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

WO 487977-02, 525408, 527621, 527622, 52836554-01, 530402,

28622. 531004

71111.20

Corrective Action

Documents

CR-ANO-

2-2019-01365

71111.22

Corrective Action

Documents

CR-ANO-

1-2019-01956 Rev. 5, 2-2019-00328, 2-2019-01374, 2-2019-

01743,

Engineering

Changes

EC 82959

Miscellaneous

741007

Combustion Engineering Test Report

STM 1-65

Engineered Safeguards Actuation System

Procedures

OP-1304.049

Unit 1 ESAS Analog Channel 1 Test

OP-1304.052

Unit 1 ESAS Analog Channel 1 Calibration

Work Orders

WO 27621, 527622, 2790774, 52673734

71114.02

Miscellaneous

Design Report Update, Upgraded Public Alert and Notification

System (ANS), Arkansas Nuclear One (ANO)

May 2016

Design Report Update, Upgraded Public Alert and Notification

System (ANS), Arkansas Nuclear One (ANO), Supplement (1)

February

2017

EP-002

Early Warning System

71114.03

Miscellaneous

Form 1903.062C,

Change 31

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 06/27/2017

06/29/2017

Form 1903.062C,

Change 32

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 09/29/2017

10/04/2017

Form 1903.062C,

Change 32

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 10/31/2017

11/13/2017

Form 1903.062C,

Change 34

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 03/03/2018

03/17/2018

Form 1903.062C,

Change 34

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 06/17/2018

07/09/2018

Form 1903.062C,

Change 35

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 08/09/2018

08/16/2018

Form 1903.062C,

Change 35

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 12/21/2018

01/02/2019

Form 1903.062C,

Change 35

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 01/26/2019

2/04/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Form 1903.062C,

Change 35

Emergency Response Staffing Drill, Scenario: ERO Test;

Date: 05/05/2019

05/10/2019

Procedures

1903.011

Emergency Response/Notifications

EN-EP-310

Emergency Response Organization Notification System

71114.04

Miscellaneous

9.1,

CFR

50.54(q)(2)

Review

Procedure/Document Number: 1903.010, Revision: 055

04/09/2018

9.1,

CFR

50.54(q)(2)

Review

Procedure/Document Number: 1903.011, Revision: 056

10/25/2018

9.1,

CFR

50.54(q)(2)

Review

Procedure/Document Number: 1903.062, Revision: 033

2/08/2017

9.1,

CFR

50.54(q)(2)

Review

Procedure/Document Number: 1904.002, Revision: 042

09/21/2017

9.1,

CFR

50.54(q)(2)

Review

Procedure/Document Number: 1903.011, Revision: 54

04/24/2017

9.2,

CFR

50.54(q)(3)

Screening

Procedure/Document Number: 1903.069, Revision: 007

09/13/2017

9.2,

CFR

50.54(q)(3)

Screening

Procedure/Document Number: OP-1903.011, OP-1903.011-Y,

OP-1903.011-Z; Revisions: 056, 048, 047

10/25/2018

9.2,

CFR

Procedure/Document Number: 1903.010, Revision: 056

06/13/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

50.54(q)(3)

Screening

9.2,

CFR

50.54(q)(3)

Screening

Procedure/Document Number: OP-1903.010, Revision: 054

03/20/2018

9.3,

CFR

50.54(q)(3)

Evaluation

Procedure/Document Number: 1903.010, Revision: 054

03/20/2018

9.3,

CFR

50.54(q)(3)

Evaluation

Procedure/Document Number: OP-1903.010, Revision: 056

06/13/2018

9.3,

CFR

50.54(q)(3)

Evaluation

Procedure/Document Number: 1903.069, Revision: 007

09/13/2017

Procedures

1604.051

Eberline Radiation Monitoring System

1903.010

Emergency Action Level Classifications

2, 54, 55,

56, 57

1903.062

Communications System Operating Procedure

1904.047

Offsite Dose Projections

203.012K

Annunciator 2K11 Corrective Action

EN-EP-305

Emergency Planning 10CFR50.54(q) Review Program

4, 5, 6

71114.05

Corrective Action

Documents

CR-

HQN-2018-00961

CR-ANO-

C-2017-00961, C-2017-01742, C-2017-01851, C-2017-01972,

C-2017-02758, C-2017-02938, C-2017-02950, C-2017-04431,

C-2018-00456, C-2018-00525, C-2018-01424, C-2018-01658,

C-2018-01783, C-2018-01851, C-2018-01882, C-2018-01890,

C-2018-01947, C-2018-02809, C-2018-02810, C-2018-02879,

C-2018-03597, C-2018-03686, C-2018-04572, C-2019-01825,

C-2019-01851, C-2019-01890, C-2019-03166, C-2019-03203,

C-2019-03621

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

Arkansas Nuclear One ERO Team "Green" Site Drill Report,

September 5, 2018

06/02/2019

Nuclear Independent Oversight Functional Area Performance

Report, Site: Arkansas Nuclear One

06/06/2018

Nuclear Independent Oversight Functional Area Performance

Report, Site: ANO

2/08/2018

Nuclear Independent Oversight Functional Area Performance

Report, Site: Arkansas Nuclear One

2/25/2019

Nuclear Independent Oversight Functional Area Performance

Report, Site: Arkansas Nuclear One

10/17/2018

Nuclear Independent Oversight Functional Area Performance

Report, Site: Arkansas Nuclear One

06/07/2017

Nuclear Independent Oversight Functional Area Performance

Report, Site: ANO

10/19/2017

Arkansas Nuclear One Blue Team Site Drill Report,

May 15, 2019

06/12/2019

Arkansas Nuclear One Radiological Monitoring Drill Report,

April 17, 2019

05/16/2019

Arkansas Nuclear One HP/Post Accident Drill Report,

April 17, 2019

05/17/2019

Arkansas Nuclear One Red Team Site Drill Report,

February 6, 2019

2/28/2019

Arkansas Nuclear One ERO Red Team Drill Report,

August 2, 2017

08/31/2017

Arkansas Nuclear One 2018 NRC Exercise Report,

July 17, 2018

08/10/2018

Arkansas Nuclear One Radiological Monitoring Drill Report,

December 4, 2018

2/20/2019

Arkansas Nuclear One HP/Post Accident Drill Report,

December 4, 2018

2/19/2019

Arkansas Nuclear One Health Physics Drill 2018-01 Drill

Package

05/20/2019

Arkansas Nuclear One Blue Team Drill Report, May 30, 2018

05/30/2018

EP-2017-027

2017 Medical Drill with Pope County EMS and UAMS

2/06/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EP-2018-001

December 20, 2017 Pass Drill

01/18/2018

EP-2018-002

December 14 and 19, 2017 Environmental Sampling Drill

01/18/2018

Form 1903.004-G

EAL State and Local Agreement

2/11/2018

Form 1903.004-N

Annual LOA/Contracts Review

2/18/2018

Form 1903.004N

Annual LOA/Contracts Review

05/08/2018

Form 1903.004M

ETE Update

08/22/2017

Form 1903-004-C

Quarterly Emergency Telephone Directory Review

06/28/2019

KLD TR-1022

Arkansas Nuclear One, 2018 Population Update Analysis

09/22/2018

KLD TR-938

Arkansas Nuclear One, 2017 Population Update Analysis

09/23/2017

MS-1 Drill Report

EP-2018-20158

2018 Medical Drill with Pope County EMS and Saint Mary's

Regional Medical Center (September 27, 2018)

2/06/2018

NQ-2017-009

Emergency Preparedness Audit Package for QA-7-2017-ANO-

07/11/2017

NQ-2018-008

QA Audit Report QA-7-2018-ANO-1, 2018 QA Audit of

Emergency Preparedness at Arkansas Nuclear One (ANO)

05/10/2018

QA-07-2019-

ANO-1

Quality Assurance Audit Report

05/20/2019

NDE Reports

Form 1903.004-G

EAL State and Local Agreement

2/05/2017

Procedures

1903.004

Admin. & Maintenance of the Emergency Plan & Implementing

Procedures

1903.011

Emergency Response/Notification

1903.060

Emergency Supplies and Equipment

1903.069

Equipment Important to Emergency Response

EN-EP-306

Drills and Exercises

EN-EP-308

Emergency Planning Critiques

EN-LI-102

Corrective Action Program

EN-TQ-110

Emergency Response Organization Training

2, 13

Work Orders

WO 00439733, 00481018, 00481536, 00494038, 004388830,

2610089, 52610090, 5263126

71114.06

Corrective Action

Documents

CR-ANO-

C-2019-03055, C-2019-03063, C-2019-03064, C-2019-03065,

C-2019-03066, C-2019-03092, C-2019-03094, C-2019-03095

Procedures

OP-1903.010

Emergency Action Level Classification

71151

Calculations

CALC-ANO1-SA-

ANO-1 Mitigating System Performance Index Basis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

16-00001

CALC-ANO2-SA-

06-00001

ANO-2 Mitigating System Performance Index Basis

Corrective Action

Documents

CR-ANO-

1-2019-01658

Miscellaneous

Communicator Scenario HU6

11/13/2018

A1SPG-SRO-EAL

Emergency Action Level Classification

A1SXMLOR1902

Arkansas Nuclear One, Unit 1, Performance Evaluation

Scenario

SES-2-007

Arkansas Nuclear One, Unit 2, Dynamic Exam Scenario

SES-2-013

Arkansas Nuclear One, Unit 2, Dynamic Exam Scenario

SES-2-031

Arkansas Nuclear One, Unit 2, Dynamic Exam Scenario

Procedures

1903.057

Emergency Action Level Classification

EN-LI-114

Regulatory Performance Indicator Process

71152

Corrective Action

Documents

CR-ANO-

2-2019-01365, 2-2019-01445, 2-2019-01687, 2-2019-01746,

2-2019-01820, 2-2019-02033, 2-2019-02118,

71153

Corrective Action

Documents

CR-ANO-

2-2019-02506

Drawings

M-2235, Sheet 1

P&ID Fuel Pool System

Procedures

OP-2104.006

Fuel Pool Systems

OP-2203.002

Spent Fuel Pool Emergencies

OP-2203.012K

Annunciator 2K11 Corrective Action

50