IR 05000368/2019016

From kanterella
Jump to navigation Jump to search
NRC Post-Approval License Renewal Inspection Report 05000368/2019016
ML20101P354
Person / Time
Site: Arkansas Nuclear 
(NPF-006)
Issue date: 04/11/2020
From: Nick Taylor
NRC/RGN-IV/DRS/EB-2
To: Dinelli J
Entergy Operations
References
EPID I-2019-016-0000 IR 2019016
Download: ML20101P354 (10)


Text

April 11, 2020

SUBJECT:

ARKANSAS NUCLEAR ONE, UNIT 2 - NRC POST-APPROVAL LICENSE RENEWAL INSPECTION REPORT 05000368/2019016

Dear Mr. Dinelli:

On March 20, 2020, U.S. Nuclear Regulatory Commission (NRC) inspectors completed an in-office inspection for Arkansas Nuclear One, Unit 2. The enclosed report documents the inspection results, which were discussed with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Nicholas H. Taylor, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-368 License No. NPF-6

Enclosure:

As stated

Inspection Report

Docket Number:

05000368

License Number:

NPF-6

Report Number:

05000368/2019016

Enterprise Identifier

I-2019-016-0000

Licensee:

Entergy Operations, Inc.

Facility:

Arkansas Nuclear One, Unit 2

Location:

Russellville, AR

Inspection Dates:

December 1, 2019 through March 20, 2020

Inspectors:

I. Anchondo, Reactor Inspector

G. Pick, Senior Reactor Inspector (Lead)

Approved By:

Nicholas H. Taylor, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

IR 05000368/2019016; 12/01/2019 - 03/20/2020; Arkansas Nuclear One, Unit 2; In-Office

Post-Approval Site Inspection for License Renewal

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting a license renewal commitment evaluation for Arkansas Nuclear

One, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight

Process is the NRCs program for overseeing the safe operation of commercial nuclear power

reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

4.

OTHER ACTIVITIES (OA)

4OA5 Phase 3 Inspection Activities (IP 71003)

Phase 3 Inspection activities are performed after the licensee enters the period of

extended operation. The period of extended operation is the additional 20 years beyond

the original 40-year licensed term. Arkansas Nuclear One, Unit 2, began the period of

extended operation on July 18, 2018.

The inspectors performed this inspection to evaluate whether the licensee completed

outstanding actions required to comply with the license renewal license condition and

commitments and effectively implemented outstanding actions related to aging

management programs.

The inspectors closed Commitments 39, 41, and 42 during this inspection.

a.

Inspection Scope

During this in-office inspection, the inspectors evaluated the licensee actions related to

commitments not closed during the Phase 2 license renewal inspection (Inspection

Report 05000368/2018010 (ML18221A507)).

The inspectors reviewed program documents, design calculations, inspection results,

engineering reports, and corrective action documents. The inspectors interviewed

licensee personnel, including the program owners, and design engineers during several

teleconferences to discuss the technical resolution related to the commitments. In

addition, headquarters personnel assisted in the technical review of these commitments.

b.

Observations

1. Implement the Environmentally Assisted Fatigue Option (Section 4.3.3.1) (17940) -

Commitment 39

This program managed aging effects related to environmentally assisted fatigue. Prior

to entering the period of extended operation, the safety evaluation report required the

licensee to address the effects of environmentally assisted fatigue for several fatigue-

sensitive locations, which included:

  • Reactor vessel shell and lower head

Reactor vessel inlet and outlet nozzles

Surge line

Charging nozzle

Safety injection nozzle

Shutdown cooling system Class 1 piping

During the previous inspection, the inspectors determined that the licensee had elected

to perform the inspection option as allowed by their safety analysis report,

Section 4.3.3.1. The licensee identified two locations that would be inspected in

accordance with American Society of Mechanical Engineers Boiler and Pressure Vessel

Code (ASME),Section XI, Appendix L, Operating Plant Fatigue Assessment, and

submitted the fatigue assessment results to the NRC for review. The licensee had

preliminarily calculated that the cumulative usage factor for the other monitored locations

remained less than one (1.0) and did not require inspection. Since the calculations were

not available for review at the time of this inspection, this commitment remained open.

During this inspection, the inspectors reviewed information related to assessing

environmentally assisted fatigue for the affected components. The licensee had

submitted the fatigue assessment inspection methodology and results by

Letter 2CAN051801, License Renewal Pressurizer Surge Line and Safety Injection

Nozzle Inspection Arkansas Nuclear One, Unit 2, dated May 24, 2018 (ML18144A970).

The licensee assessed that a postulated flaw would take more than 50 years to reach an

unacceptable size; therefore, the planned 10-year inspection intervals provided

appropriate condition monitoring. After review of the information in the letter, NRC

issued a safety evaluation report on April 5, 2019 (ML19074A028), which concluded the

licensee met their commitment and established an appropriate scope, method, and

frequency of inspecting for environmentally assisted fatigue.

The inspectors reviewed the inspection results for the affected welds, which identified

that the welds contained no flaws. The inspectors reviewed the detailed fatigue

calculations referenced in Letter 2CAN051801. Overall, the inspectors determined that

the licensee had performed the calculations using an appropriate methodology. The

inspectors determined, after consulting with NRC headquarters, the licensee had not

used factors in their calculation that reflected the changes to our current state of

knowledge since they had originally performed their assessment. Following questioning,

the licensee demonstrated that, even after adjusting the calculation based on our current

state of knowledge, they provided adequate conservatism in their calculation. The

licensee demonstrated that a postulated flaw would not result in failure in less than

30 years, but inspected the affected components every 10 years.

Other than the item described above, the inspectors identified no additional concerns

with implementation of this commitment.

2. B.1.30 Chemistry Control Programs (17937, 17938, and 17939) - Commitment 41

These chemistry programs managed the effects of aging caused by fouling, cracking,

and loss of material. The primary water chemistry program controlled chemistry for the

reactor coolant system, including primary side of the steam generators and the

emergency core cooling systems, spent fuel pool system, and the chemical and volume

control system. The secondary water chemistry program controlled chemistry in the

main feedwater system, emergency feedwater system, main steam system, condensate

storage system, and steam generators.

Commitment 41 specified:

The chemistry procedure and engineering report will be revised to

address loss of the passive layer if chemistry limits are out of specification

for an extended period.

Although the inspectors had reviewed overall implementation of the primary and

secondary water chemistry programs, the inspectors had not reviewed the details

associated with the above commitment.

During this inspection, the inspectors reviewed the engineering report and the chemistry

procedure and discussed the revisions with the program owner. The inspectors

confirmed that the licensee established requirements to address loss of the passive

layer whenever chemistry limits are found out of specification.

The inspectors identified no concerns with implementation of this commitment.

3. B.1.18 Periodic Surveillance and Preventive Maintenance Program (17925) -

Commitment 42

This program managed aging effects related to change in material properties, cracking,

heat exchanger fouling, loss of material, and loss of form. The license identified specific

components included in this program because the other aging management programs

did not monitor for the identified effects.

Commitment 42 specified:

The Periodic Surveillance and Preventive Maintenance Program will be

revised to include an inspection of the alternate AC diesel generator

starting air tank.

Although the inspectors had reviewed overall implementation of the periodic surveillance

and preventive maintenance program, the inspectors had not reviewed the details

associated with the above commitment.

During this inspection, the inspectors verified that the licensee established a

periodic task to inspect that interior of the alternate AC diesel generator starting

air tank. The inspectors confirmed that the licensee identified no adverse aging

effects in the alternate AC diesel generator starting air tanks.

The inspectors identified no concerns with implementation of this commitment.

c.

Conclusion

Based on review of the actions implemented, inspection results reviewed, and interviews

with program owners, the inspectors determined that the licensee provided reasonable

assurance and demonstrated that they had implemented actions to effectively manage

the effects of aging for each respective program. The inspectors determined that the

licensee met the commitments.

4OA6 Meetings, Including Exit

The inspector presented the inspection results on March 20, 2020, to Mr. J. Dinelli, Site

Vice President, and other members of the licensee staff. The licensee acknowledged

the NRC inspection observations. The inspector retained no proprietary information and

verified that no proprietary information was documented in this report.

A-1

Attachment

SUPPLEMENTAL INFORMATION

COMMITMENTS

The inspectors reviewed chemistry control programs, in part, related to Commitments 17937,

17938, and 17939, and reviewed the periodic surveillance and preventive maintenance

program, in part, related to Commitment 17925. As a result of the reviews, the inspectors

closed Appendix A to NUREG-1828, Safety Evaluation Report Related to the License Renewal

of Arkansas Nuclear One, Unit 2, items 41 and 42 in this inspection report.

In addition, the inspectors closed Commitment 17940 and related Appendix A to NUREG-1828,

item 39.

Commitments previously closed include:

NRC closed Commitments 17908, 17909, 17914, and 17939 in Inspection Report 05000368/2017009, which included NUREG-1828, Appendix A items 6 and 28.

NRC closed the following commitments in Inspection Report 05000368/2018010:

17905, 17910, 17911, 17912, 17913, 17915, 17916, 17917, 17918, 17919, 17920, 17921,

17922, 17923, 17924, 17925, 17926, 17927, 17928, 17929, 17930, 17931, 17932, 17933,

17934, 17935, 17936, 17937, 17938, 18175, 18207, and 20017.

During review of these commitments the inspectors confirmed that the licensee had met the

conditions prescribed in NUREG-1828, Appendix A, Items 1, 2, 3, 4, 5, 7, 8, 9,10, 11, 12,

13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37,

38, and 40.

DOCUMENTS REVIEWED

1. Implement the Environmentally Assisted Fatigue Option (Section 4.3.3.1) (17940) -

Commitment 39

Condition Reports (CR-ANO-2-)

2020-00106*

  • This condition report was issued as a result of this inspection.

Calculations

Number

Title

Revision/Date

CALC-17-E-0300-06

Arkansas Nuclear One - Unit 2 Pressurizer

Surge Line 60-YR Fatigue Assessment

CALC-17-E-0300-08

Arkansas Nuclear One - Unit 2 Safety

Injection Nozzle 60-YR Fatigue Assessment

A-2

Examinations

Number

Report Number

Date

2R23 16-011

2-ISI-UT-14-016, Component 16-011

05/21/2014

2R23 16-012

2-ISI-UT-14-015, Component 16-012

05/21/2014

2R23 21-001

2-ISI-VE-14-017, Component 21-001

05/30/2014

2R23 22-001

2-ISI-VE-14-015, Component 22-001

05/31/2014

2R23 23-001

2-ISI-VE-14-018, Component 23-001

05/30/2014

2R23 24-001

2-ISI-VE-14-016, Component 24-001

05/31/2014

Miscellaneous Documents

Number

Title

Revision/Date

Basis for ASME Section XI Code Case for

Flaw Tolerance Evaluation of CASS Piping

Arkansas Nuclear One, Unit 2 - Review of

License Renewal Commitment Submittal

Regarding Environmentally-Assisted Fatigue

(EPID L-2018-LRO-0026)

04/05/2019

Case N-809

Reference Fatigue Crack Growth Rate Curves

for Austenitic Stainless Steels in Pressurized

Water Reactor Environments,Section XI,

Division 1

06/23/2015

Case N-838

Flaw Tolerance Evaluation of Cast Austenitic

Stainless Steel Piping,Section XI, Division 1

08/03/2015

Letter 2CAN051801

License Renewal Pressurizer Surge Line and

Safety Injection Nozzle Inspection

05/24/2018

NUREG/CR-6260

Application of NUREG/CR-5999 Interim

Fatigue Curves to Selected Nuclear Power

Plant Components

02/1995

PVP2015-45191

Further Validation of the Technical Basis of

Code Case N-838 for Flaw Tolerance

Evaluation of CASS Piping

PVP2017-66100

Technical Basis for Flaw Acceptance Criteria

for Cast Austenitic Stainless Steel Piping

A-3

2. B.1.30 Chemistry Control Programs (17937, 17938, and 17939) - Commitment 41

Condition Reports (CR-ANO-2-)

2017-04159

2018-00914

2018-03639

2019-02859

Miscellaneous Documents

Number

Title

Revision/Date

A2-EP-2002-002 2

ANO-2 License Renewal Project Evaluation

of Aging Management Programs,

Section 4.18.1 Primary and Secondary

Water Chemistry Control Program

Letter 2CAN120403

License Renewal Application Draft Safety

Evaluation Report Comments

12/09/2004

Procedure EN-CY-100 Conduct of Chemistry

3. B.1.18 Periodic Surveillance and Preventive Maintenance Program (17925) -

Commitment 42

Miscellaneous Documents

Number

Title

Date

Letter 2CAN120403

License Renewal Application Draft Safety Evaluation

Report Comments

12/09/2004

Work Orders

00469663

00469664