IR 05000266/2024004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000266/2024004 and 05000301/2024004
ML25017A226
Person / Time
Site: Point Beach  
Issue date: 01/21/2025
From: Travis Iskierka-Boggs
NRC/RGN-III/DORS/RPB2
To: Durbin M
Point Beach
References
IR 2024004
Download: ML25017A226 (1)


Text

SUBJECT:

POINT BEACH NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000266/2024004 AND 05000301/2024004

Dear Michael Durbin:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Point Beach Nuclear Plant. On January 14, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Travis D. Iskierka-Boggs, Acting Branch Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000266 and 05000301

License Numbers:

DPR-24 and DPR-27

Report Numbers:

05000266/2024004 and 05000301/2024004

Enterprise Identifier:

I-2024-004-0063

Licensee:

NextEra Energy Point Beach, LLC

Facility:

Point Beach Nuclear Plant

Location:

Two Rivers, WI

Inspection Dates:

October 01, 2024 to December 31, 2024

Inspectors:

J. Kutlesa, Senior Emergency Preparedness Inspector

J. Masse, Resident Inspector

V. Myers, Senior Health Physicist

A. Shaikh, Senior Reactor Inspector

M. Stafford, Senior Resident Inspector

Approved By:

Travis D. Iskierka-Boggs, Acting Branch Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Point Beach Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power and remained at or near full power throughout the remainder of the inspection period.

Unit 2 began the inspection period in a coast down for a refueling outage, at approximately 89 percent power. On October 12, 2024, operators shutdown Unit 2 from approximately 82 percent power for the scheduled refueling outage. On October 31, 2024, operators restarted Unit 2. On November 1, 2024, operators synchronized the unit to the grid, and on November 5, 2024, the unit achieved full power. The unit remained at or near full power throughout the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems and components:

main feedwater isolation valves, service water, battery inverters, and emergency diesel generator fuel oil transfer system on November 19, 2024.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 turbine driven auxiliary feedwater pump on November 7, 2024

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 spent fuel pool cooling system on October 21, 2024.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire zones 608 and 611 on October 20, 2024
(2) Fire zones 615 and 618 on October 24, 2024
(3) Fire zone 516 on October 25, 2024

===71111.08P - Inservice Inspection Activities (PWR) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities in Unit 2 during refueling outage U2R40 from October 21-25, 2024.

PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding Activities (IP Section 03.01)===

The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:

(1)

  • Ultrasonic Examination of Pipe to Elbow Weld on AC-10-SI-2001-16
  • Visual Examination of Rigid Support 29-PRB
  • Bare Metal Visual Examination of RPV Bottom Mounted Instrumentation Penetrations
  • Welding Repair on 2AF-198B PWR Inservice Inspection Activities Sample - Vessel Upper Head Penetration Inspection

Activities (IP Section 03.02) (1 Sample)

The inspectors verified that the licensee conducted the following vessel upper head penetration inspections and addressed any identified defects appropriately:

(1)

  • Bare Metal Visual Examination of RPV Upper Head Closure Surfaces PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities (IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program through a review of the following evaluations:

(1)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the Unit 2 shutdown on October 12, 2024.
(2) The inspectors observed and evaluated licensed operator performance in the control room during Unit 2 power ascension activities on October 31, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated crew performance during the biennial operational exam on October 1, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Diesel fire pump charger failure on November 4, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated risk due to reactor protection and safeguards system logic testing on October 3, 2024
(2) Elevated risk due to lowered reactor coolant system inventory during the Unit 2 refueling outage on October 14, 2023
(3) Elevated risk for the infrequently performed ORT 3A, Safety Injection Actuation with Loss of Engineered Safeguards, on October 14, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Operability of the turbine driven auxiliary feedwater pump following identification of scaffold interference on October 23, 2024
(2) Operability of 2HX-15B, accident recirculation fan motor cooling coil, following identification of a tube leak on October 29, 2024
(3) Operability of 2AF-4000, turbine driven auxiliary feedwater pump discharge to steam generator B inlet isolation valve after over thrust condition on November 6, 2024
(4) Operability of 2SI-867B, safety injection to reactor coolant loop B cold leg check valve, following elevated leak rates during testing on November 7, 2024
(5) Operability of G-01, emergency diesel generator after relays found to be out of tolerance on November 15, 2024

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage U2R40 activities from October 3, 2024, to November 15, 2024.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1)2ICP 4.24 calibration of source range detector 2N-31 after replacement on October 24, 2024

(2) Leakage testing on 2RC-431B, pressurizer spray line control valve following removal of bellows leak detection line on November 13, 2024
(3) Leakage testing of 2MS-2018A, main steam non-return check valve following valve disc replacement on December 18, 2024
(4) Containment accident recirculation fan tests following maintenance and replacement on December 19, 2024
(5) Control room emergency filtration system breaker and system testing following repair on December 23, 2024

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) ORT 3A, Safety Injection Actuation with Loss of Engineered Safeguards AC, on October 22, 2024 (2)1RMP 9056-1, calibration of relays on 4160V bus 1A-05 on November 27, 2024

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1) ORT 31, Nitrogen Supply to the Pressurizer Relief Tank, leakage testing, on October 22, 2024

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:
  • The inspectors reviewed the FEMA-approved Design Report and assessed the adequacy of Manitowoc and Kewaunee Counties Wisconsin performance of the test and maintenance activities associated with the approved Integrated Public Alert and Warning System (IPAWS) alert and notification system.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Preparedness Organization.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • EPIP 1.2.1, Emergency Action Levels and Technical Basis, Rev 28
  • EP-AA-100-1007-F02, RMS Functional Assessment for New System, Rev 2 This evaluation does not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Workers exiting the radiologically controlled area
(2) Workers and material leaving Unit 2 containment

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensees control of radiological hazards for the following radiological work:

(1) Reactor vessel disassembly
(2) Fuel sipping activities
(3) Lower cavity activities
(4) B reactor coolant pump seal replacement High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (2 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1) Unit 2 demineralizer cubicles
(2) Fuel movement boundaries Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (2 Samples)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Reactor head laydown area
(2) Reactor vent

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS09: Residual Heat Removal Systems (IP Section 02.08)===

(1) Unit 1 (July 1, 2023 through September 30, 2024)
(2) Unit 2 (July 1, 2023 through September 30, 2024)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (October 1, 2023 through September 30, 2024)
(2) Unit 2 (October 1, 2023 through September 30, 2024)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (July 1, 2023 through September 30, 2024)
(2) Unit 2 (July 1, 2023 through September 30, 2024)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) July 1, 2023 through September 30, 2024 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) July 1, 2023 through September 30, 2024

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) August 1, 2023 through July 31, 2024 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) August 1, 2023 through July 31, 2024 EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) August 1, 2023 through July 31, 2024

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) Human Performance Trends

INSPECTION RESULTS

Observation: Semiannual Trend Review 71152S The inspectors noted a trend in the human performance error rate at the station. The data shows an uptick in the 2024 error rate compared to that of 2023. However, the error rate for 2024 was comparable to previous years. In 2024, the licensee initiated 6637 Action Requests (AR). Of these, 144 were human performance related. This results in a ratio of 2.17 percent human performance ARs compared to the total. In 2023 this value was 2.07 percent. As a reference, the highest percentage in the last 5 years was 2020, at 2.68 percent. The licensee performed a trend assessment to look specifically at clearance related issues, which saw an increase leading up to and during the refueling outage. The corrective actions of this assessment were to reinforce questioning attitude amongst the maintenance and operations departments and to provide practice scenarios to these departments. The inspectors did not identify any findings or violations during their review that have not already been addressed.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 28, 2024, the inspectors presented the Inservice Inspection (ISI) Exit Meeting inspection results to Michael Durbin, Site Vice President, and other members of the licensee staff.
  • On November 8, 2024, the inspectors presented the radiation protection inspection results to Michael Durbin, Site Vice President, and other members of the licensee staff.
  • On December 20, 2024, the inspectors presented the emergency action level and emergency plan changes inspection results to D. Smith, Emergency Preparedness Manager, and other members of the licensee staff.
  • On January 14, 2025, the inspectors presented the integrated inspection results to Michael Durbin, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2502033

0-PT-FP-004 - Annual Fire Pump Cap Test CR2502037

NRCID

11/19/2024

Corrective Action

Documents

Resulting from

Inspection

2502037

NRC Identified Concerns

11/19/2024

Miscellaneous

PBNP Winter Readiness 2024-25 Letter

11/15/2024

OP-AA-102-1002

Seasonal Readiness

PC 49 Part 3

Auxiliary Building Ventilation

PC 49 Part 4

Auxiliary Building Miscellaneous and Facades

71111.01

Procedures

PC 49 Part 5

Cold Weather Checklist: Outside Areas and Miscellaneous

2500465

Pink Boric Acid Noted on Packing of 2SF-820B by NRC

Resident

11/03/2024

2500467

SF-16 Has Dry Boric Acid on the Downstream Cap

11/03/2024

2500470

SF-793B Has a Flange and Unlabeled Valve Connected to it

11/03/2024

2500824

SF Valves Have Labels that do not Match Names in CL-5C

11/06/2024

2500826

CL 5C - Spent Fuel Pool Cooling and Refueling Water

Circulating Pump Normal Operation Valve Lineup

11/06/2024

Corrective Action

Documents

Resulting from

Inspection

2501047

CL 13E Part 1 Unit 2 - Auxiliary Feedwater Valve Lineup

Turbine-Driven Unit 2

11/08/2024

110E018, Sheet 4

P&ID Auxiliary Cooling System

Drawings

M-217 Sheet 2

P&ID Auxiliary Feedwater System

CL 13E Part 1

Auxiliary Feedwater Valve Lineup Turbine-Driven Unit 2

71111.04

Procedures

CL 5C

Spent Fuel Pool Cooling and Refueling Water Circulating

Pump Normal Operation Valve Lineup

Corrective Action

Documents

2496803

Smoke Detectors in U1 Containment Simultaneously

Alarmed

10/02/2024

PFP-1-CONT-

FAC

Pre-Fire Plan Unit 1 Containment Building/Facade

Fire Plans

PFP-2-CONT-

FAC

Pre-Fire Plan Unit 2 Containment Building/Facade

EPIP 1.2.1

Emergency Action Levels and Technical Basis

71111.05

Procedures

NP 1.9.14

Fire Protection Plan

71111.08P

Corrective Action

AR 02484573

2CV-290 Boric Acid Build-Up on Valve Stem and Packing

06/23/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Gland

BAS 23-088-E

2SI-V-26 Boric Acid Leak

04/11/2023

BAS24-009

2CV-262C Boric Acid Leak

01/22/2024

BAS24-029

2CV-290 Boric Acid Leak

04/20/2024

Engineering

Evaluations

BAS24-039

2SI-829C Boric Acid Leak

06/25/2024

PB2-UT-24-001

Liquid Penetrant Examination of Welded Attachment

SI-151R-3-2H1-IWA

10/17/2024

PB2-UT-24-005

Ultrasonic Examination of Pipe to Elbow Weld on

AC-10-SI-2001-16

10/21/2024

PB2-VT-24-017

Visual Examination of Boric Acid (BMV) of Bottom Mounted

Instrumentation Penetrations

10/17/2024

PB2-VT-24-025

Visual Examination of Boric Acid (BMV) of RPV Head

Surfaces

10/21/2024

NDE Reports

PB2-VT-24-028

Visual Examination of Pipe Hanger, Support or Restraint

10/21/2024

Operability

Evaluations

WEPM-RV010-

TM-LO-000001

Point Beach Unit 1 and 2 Reactor Vessel Clevis Insert Wear

Prediction Component Assessment

AC-10-SI-2001-

UT Calibration/Examination

10/21/2024

FP-PE-WLD-02

General Welding Specification

NDE-109_012

Manual Ultrasonic Examination Using Longitudinal-Wave

Straight-Beam Techniques

NDE-173_020

PDI Generic Procedure for The Ultrasonic Examination of

Austenitic Piping Welds

Procedures

NDE-754-024

Visual Examination (VT-3) of Nuclear Power Plant

Components

Work Orders

40802726-08

Repair Welds on 2AF-198B

03/28/2023

Miscellaneous

SEG PBN LOC

000 010E

NRC Annual Operating Exam

EPIP 1.1

Course of Actions

OP 1C

Startup to Power Operation Unit 2

OP-AA-100-1000

Conduct of Operations

RESP 4.1

BOL Physics Tests

71111.11Q

Procedures

TR-AA-230-1007

Conduct of Simulator Training and Evaluation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2500395

D-600 Diesel Fire Pump Battery Voltage Low on Logs

11/03/2024

2500486

D-600 P-35B Diesel Fire Pump Starting Battery

11/03/2024

Corrective Action

Documents

2500553

P-35B Fire Pump Charger #2 Failure Alarm

11/04/2024

ER-AA-100-2002

Maintenance Rule Program Administration

71111.12

Procedures

NP 1.9.14

Fire Protection Plan

2496956

Procedural Data Lost While Using DWP on iPad (High Risk)

10/03/2024

Corrective Action

Documents

2499416

WO 40992806 CL-1E Containment Closure Activities

Concerns

10/25/2024

Corrective Action

Documents

Resulting from

Inspection

2500873

CL 1E Unit 2 - Containment Closure Checklist Unit 2

11/07/2024

U2R40 Shutdown Safety Letter

10/11/2024

PBF-1562

PBNP Shutdown Safety Assessment and Fire Inspection

Checklist

10/14/2024

Miscellaneous

PBNP Shutdown

Safety

Assessment and

Fire Inspection

Checklist

Time Stamped: 1838

10/13/2024

1ICP 02.003A

Reactor Protection System Logic Train A Surveillance Test

1ICP 02.005A

Engineered Safety Features System Logic Train A Actuation

Logic Test

CL 1E

Containment Closure Checklist Unit 2

NP 10.3.6

Shutdown Safety Review and Safety Assessment

OP 4D Part 1

Draining The Reactor Coolant System

100

OP 4E Unit 2

Reactor Coolant System Lowered Inventory Requirements

Unit 2

Procedures

OP-AA-1000

Conduct of Infrequently Performed Tests or Evolutions

40960056-01

1ICP 2.5A - Safeguards Logic Test - Train A

10/03/2024

40960071-01

1ICP 2.3A - Reactor Protection Logic Test - Train A

10/03/2024

71111.13

Work Orders

40992806-01

2CPP-59, U2C Pipe Penetration (Spare) - Implement EC 300037

10/24/2024

71111.15

Calculations

2002-0003

Service Water System Design Basis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

98-0020

Containment Recirculation Fan Motor Cooler SW Flow vs.

Temperature Requirements for Normal and Accident Modes

of Operation

2400855

G-01 Relay Maintenance Results

08/11/2021

2493045

Relays Tested on EDG G-01 per RMP 9043-18 Were Fount

out OOT

08/16/2024

2496283

Scaffold Impacting 2AF-4006 Travel

09/25/2024

2498269

2AF-4000-O Overthrust Condition

10/16/2024

2498569

2HX-15B Tube Leak Identified

10/18/2024

Corrective Action

Documents

2499818

2SI-867B Leakage Fails Under Normal TS-31 Test

Conditions

10/29/2024

110E035 Sheet 1

P&ID Safety Injection System

M-2207 Sheet 2

P&ID Service Water System

Drawings

M-2215 Sheet 1

P&ID Heating and Ventilation

Engineering

Evaluations

300123

2AF-4000 Overthrust Weak Link Review

11/04/2024

Miscellaneous

IST Background

Doc App A

PBNP Inservice Testing Background Valve Data Sheet

CMP 2.2.9

MOV Overthrust/Overtorque Review Guidance

EN-AA-203-1001

Operability Determinations

MA-AA-100-1002

Scaffold Installation, Modification, and Removal Requests

RMP 9043-18

Emergency Diesel Generator G-01 3 Year Relay

Maintenance

Procedures

TS 31

High and Low Head Safety Injection Check Valve Leakage

Test Unit 2

40819765-03

G-01; Control Relay Calibration per RMP 9043-18

08/16/2024

40860214-05

2AF-4026/Build Scaffold

09/25/2024

40860221-01

AF-04000-O: U2 MOV Actuator Diagnostics & Inspections

10/25/2024

40860221-04

2AF-4000-O, Overhaul Operator, MOV Overthrust Condition

10/25/2024

40860221-09

2AF-4000-O, Complete Operator Inspections Per ETR

300123

10/25/2024

Work Orders

40883994-01

TS-31, U2 High/Low Head SI Check Lkg Test (CSD)

10/29/2024

71111.20

Corrective Action

2498267

Sheaves in Transfer System Showed Some Signs of Wear

10/16/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Clearance

125V SAF-4067 Maint

Clearance

MS MS-2082-O Stem Lube

Miscellaneous

Clearance

TU Turbine Site Craft Tagout

2RMP 9096-1

Reactor Vessel Head Removal and Installation using Biach

Tensioning System

MA-AA-101-1000

Foreign Material Exclusion Procedure

NP 10.3.6

Shutdown Safety Review and Safety Assessment

OI 105

RCS Heatup/Cooldown Plotting

OP 1B

Reactor Startup

OP 3C Unit 2

Hot Standby to Cold Shutdown Unit 2

OP-AA-101-1000

Clearance and Tagging

RP-1A

Preparation for Refueling

109

Procedures

RP-1D

Filling and Draining the Unit 2 Refueling Cavity and Unit 2

Cavity Purification

2497821

2N-31 Source Range Detector Not Indicating

10/12/2024

2497976

2B52-40C Did Not Close When in Test Position

10/13/2024

2498012

2B52-40C Failed to Trip During ORT 3A

10/13/2024

2498029

ORT 3A U2 G02 Data Channels 5-14 Not Recorded

10/14/2024

2498569

2HX-15B Tube Leak Identified

10/18/2024

2498972

2N-31 Source Range Spiking

10/22/2024

2503684

Unexpected Start of W-14B

2/13/2024

Corrective Action

Documents

2503718

2B52-328H W-13B1 CR Recirc Fan Breaker Thermal

Overload Trip

2/14/2024

2503890

IST Program Document - Inservice Testing Program

Document

2/16/2024

Corrective Action

Documents

Resulting from

Inspection

2504190

MI 32.5 - Installation, Adjustment, or Replacement of

Live-Loaded Valve Packing

2/19/2024

541F445

P&ID Reactor Coolant System

Drawings

L-142239

Model D-100-160-2 1/2 Operator 3-1500 lb USA Std Valve

Assembly

71111.24

Engineering

Changes

299177

Pressurizer Spray Valve Bellows Telltale Line Removal

10/17/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2ICP 04.024

NIS Source Range Channels Calibration and CHAR Testing

of Source and Intermediate Range Channels

2ICP 10.015-1A

Replacement of Source/Intermediate Range NIS Detector

Assembly 2N-31/2N-35

2RMP 9306-2

Main Steam Non-Return Check Valve

Inspection/Maintenance with Cover Removed (Unit 2)

IT 315

Main Steam Line Isolation Valves (Cold Shutdown) Unit 2

MA-AA-203-1000

Maintenance Testing

MI 32.5

Installation, Adjustment, or Replacement of Live-Loaded

Valve Packing

NP 7.2.5

Repair/Replacement Program

NP 7.4.3

Post-Maintenance NDE Requirements for Power Piping

ORT 31

Nitrogen Supply to the Pressurizer Relief Tank Unit 2

ORT 3A

Safety Injection Actuation with Loss of Engineered

Safeguards AC (Train A) Unit 2

Procedures

RMP 9106

Pressurizer Spray Line Control Valve Maintenance

1RMP 9056-1

Calibration and Testing of Safety Related Protective

Relays A-05

40826730-05

2XH-015B OPS PMT-RTS

11/22/2024

40860467-01

2HX-015A/Motor Cooling Coil Insp/Cleaning (GL 89-13)

2/10/2024

40860567-01

2HX-015B/Motor Cooling Coil Insp/Cleaning (GL 89-13)

11/20/2024

40873850-02

2MS-02018A / Operations PMT (IT-315)

10/30/2024

40873850-11

2MS-02018A / Operations PMT (No Leaks)

11/06/2024

40879131-01

1A-05, Calibrate Tech Spec Relays

11/21/2024

40884248-03

2ICP 4.24 - Install Instrument Fuses and Calibrate SR N-31

10/17/2024

40956046-01

2RC-00431B / Open Inspect and Repair

10/31/2024

40956046-15

2RC-00431B / Remove Leak Det Line per EC 299177

10/20/2024

40994357-02

2N-31 Det: Replace SR/IR Detector Assy ( 2N31 / N35 )

10/16/2024

Work Orders

41001227

2B52-328H W-13B1 CR Recirc Fan Breaker Thermal Ove

2/17/2024

Miscellaneous

ML21008A217

Point Beach Nuclear Plant, and the Manitowoc County,

Kewaunee County, and The State Of Wisconsin Design

Report, and Alert And Notification System Plan

01/15/2021

71114.02

Procedures

EP 1.0

Point Beach Nuclear Plant Emergency Plan

Rev 33

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71114.03

Miscellaneous

N/A

ERO Staff Training Records: 25 Records

Various

Corrective Action

Documents

CR 02465214

Reduction in Effectiveness Identified in EC

08/23/2023

Miscellaneous

EP-AA-100-1007-

F02

RMS Functional Assessment for New System

Rev 2

EP 1.0

Point Beach Nuclear Plant Emergency Plan

Rev 33

71114.04

Procedures

EPIP 1.2.1

Emergency Action Levels and Technical Basis

Rev 28

Calculations

KLD TR - 1377

Point Beach Nuclear Plant 2023 Population Update Analysis

09/11/2023

71114.05

Miscellaneous

JNA 23-004

Fleet Nuclear Assurance Report - Emergency Preparedness

07/20/2023

Fuel Defect 2R40 Outage Preparation

Miscellaneous

23-01

Standing Order: Increased Unit 2 Monitoring Due to

Elevated Activity

06/26/2023

HP 2.17

Very High Radiation Area Personnel Access

HP 2.5

Radiation Work Permit

NISP-RP-005

Access Controls for High Radiation Areas

Procedures

RP-AA-104-1000

ALARA Implementing Procedure

24-2015

Air Sample After Head Lift

10/17/2024

24-896

Air Sample for Initial Breach from Pressurizer

10/14/2024

24-938

Air Sample Total Results for Head Lift

10/17/2024

PBPROD-M-

241015-18

Lower Cavity Blind Flange and Strainer Removal

10/15/2024

PBPROD-M-

241015-2

Upper Cavity Post Centa Door Breach

10/15/2024

PBPROD-M-

241015-20

Lower Cavity Tri-Nuke Install

10/15/2024

PBPROD-M-

241015-3

Upper Cavity Breaching RVLIS and Rx Head Vent

10/15/2024

PBPROD-M-

241016-14

B RCP Lower Platform

10/16/2024

Radiation

Surveys

PBRPOD-M-

241015-42

Lower Cavity Gripper Inspection

10/15/2024

24-2015

Cavity Activities

71124.01

Radiation Work

Permits (RWPs)

24-2016

Reactor Vessel Head - Remove/Reinstall

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

24-2050

Fuel Sipping Modification Activities

Corrective Action

Documents

Resulting from

Inspection

2502607

NRC Identified: MSPI and MRule UA Key Word Gap

2/02/2024

N/A

EP01 Drill and Exercise Performance (DEP)

01/01/2023-

2/31/2023

N/A

EP02 Emergency Response Organization Participation

(ERO)

01/01/2023-

2/31/2023

71151

Miscellaneous

PBN-BFJR-18-

054

MSPI Basis Document for PBNP

2476287

Wrong Component Event

01/10/2024

2477419

Core Drill Activity Started in Wrong Location

01/24/2024

2477499

Test Equipment not Removed Prior to Flow Block

Restoration

01/25/2024

2478119

Field Work Performed Prior to Approval of FCR

2/01/2024

2485694

24 NRC ARD Inspection - Incorrect G-501 Voltage

Documented

05/06/2024

2486377

24 NRC ARD - Missing Signature in WO Record

05/15/2024

2487439

Procedure Attachment not Filled Out as Required

05/30/2024

2492451

Exempt Source 2448-98 not Found in Designated Locked

Location

08/08/2024

2493277

Item Left in U1 Containment

08/19/2024

2494961

Wrong Red Lock Recorded During Performance of TS-81

09/09/2024

2495592

Inspection not Performed Under Correct WOs for Clearance

09/17/2024

2496029

Danger Tag Hung on Incorrect Component

09/23/2024

2496152

Escalation - PB Trend in Clearance and Tagging Issues

09/24/2024

2496236

Information Tag on Wrong Component

09/25/2024

2496383

Hourly Fire Rounds Missed

09/26/2024

2497738

Discharge Permit Missing Some Data

10/11/2024

2498313

Work Started Prior to Signing on to Correct Clearance

10/16/2024

71152S

Corrective Action

Documents

2498757

HU Investigation for Tagged Component

10/20/2024