DCL-03-032, February 2003 Monthly Operating Report for Diablo Canyon, Units 1 & 2

From kanterella
(Redirected from DCL-03-032)
Jump to navigation Jump to search
February 2003 Monthly Operating Report for Diablo Canyon, Units 1 & 2
ML030780461
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 03/14/2003
From: Becker J
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DCL-03-032, GL-97-002
Download: ML030780461 (6)


Text

Pacific Gas and ElectricCompany M James R. Becker Diablo Canyon Power Plant Vice President-Diablo Canyon P0 Box 56 March 4,2003 Operations and Station Director Avila Beach, CA 93424 805545 3462 Fax 805 545 4234 PG&E Letter DCL-03-032 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Monthly OperatinQ Rerort for February 2003

Dear Commissioners and Staff:

Attached is the Monthly Operating Report for Diablo Canyon Power Plant, Units I and 2, for February 2003. This report is submitted in accordance with Technical Specification 5.6.4 and NRC Generic Letter 97-02.

Sincerely, James . Be~cckerr LMP/1 713/R0242442 Enclosures cclenc: Paul R. Fox, American Nuclear Insurers Robert D. Glynn, Jr.

Ellis W. Merschoff, NRC Regional Administrator, Region IV David L. Proulx, NRC Senior Resident Inspector Gregory M. Rueger Girija S. Shukla, NRC Project Manager INPO Record Center A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Caltawav

  • Comanche Peak
  • Diablo Canyon e Palo Verde 9 South Texas Proiect
  • Wolf Creek

Enclosure 1 PG&E Letter DCL-03-032 FEBRUARY 2003, OPERATION SUMMARIES DIABLO CANYON POWER PLANT UNITS I AND 2 Summary of Unit 1 Operation Unit 1 began February in Mode 1 (Power Operation) at approximately 100 percent power. There were no significant operational activities.

Summary of Unit 2 Operation Unit 2 began February in Mode I at approximately 95 percent power due to an end-of cycle coast down. On February 3, 2003, operators reduced power, separated the unit from the grid and manually shutdown the reactor to Mode 3 (Hot Standby) to start refueling outage 11 (2R1 1). The unit ended the month in Mode 6 (Refueling).

Actuations of Safety or Pressurizer Power Operated Relief Valves There were no challenges to the pressurizer power operated relief valves, pressurizer safety valves, or steam generator safety valves.

Enclosure 2 PG&E Letter DCL-03-032 OPERATING DATA REPORT DOCKET NO.: 50-275 UNIT NAME: Diablo Canyon Unit 1 DATE: 03/03/2003 COMPLETED BY: L. M. Parker TELEPHONE: (805) 545-3386 REPORT MONTH: February 2003

1. Design Electrical Rating (MWe - Net): 1 1,103
2. Maximum Dependable Capacity (MWe - Net): 1,087 This Month YTD Cumulative
3. Number of Hours Reactor Critical: 672.0 1,416.0 135,642.8
4. Number of Hours Generator On-Line: 672.0 1,416.0 *134,125.6
5. Unit Reserve Shutdown Hours: 0.0 0.0 - 0.0
6. Net Electrical Energy Generated (MWH): 744,367 1,565,832 138;772,131

"* "Cumulative Hours on-line" incorporates a correction to a data entry error made in 1999.

I

Enclosure 2 PG&E Letter DCL-03-032 UNIT SHUTDOWNS DOCKET NO.: 50-275 UNIT NAME: Diablo Canyon Unit 1 DATE: 03/03/2003 COMPLETED BY: L. M. Parker TELEPHONE: (805) 545-3386 REPORT MONTH: February 2003 NO. DATE TYPE DURATION REASON1 METHOD CAUSE & CORRECTIVE (YYMMDD) F(Forced) (HOURS) OF SHUTTING ACTIONS S (Scheduled) SHUTTNG COMMENTS DOWN' N/A There were no shutdowns this month.

1. Reason 2. Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram '

C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation from Previous Month E-Operator Training/License Examination 5-Other F- Administrative G-Operational Error (Explain)

H-Other (Explain) 2

Enclosure 2 PG&E Letter DCL-03-032 OPERATING DATA REPORT DOCKET NO.: 50-323 UNIT NAME: Diablo Canyon Unit 2 DATE: 03/03/2003 COMPLETED BY: L. M. Parker TELEPHONE: (805) 545-3386 REPORT MONTH: February 2003

1. Design Electrical Rating (MWe - Net): 1 1119
2. Maximum Dependable Capacity MWe - Net): 1087 This Month YTD Cumulative
3. Number of Hours Reactor Critical: 53.4 797.4 132,155.9
4. Number of Hours Generator On-Line: 52.9 796.9 130,684.8
5. Unit Reserve Shutdown Hours: 0.0 0.0 0.0
6. Net Electrical Energy Generated (MWH): 51,064 860,958 137,552,948 3

Enclosure 2 PG&E Letter DCL-03-032 UNIT SHUTDOWNS DOCKET NO.: 50-323 UNIT NAME: Diablo Canyon Unit 2 DATE: 03/03/2003 COMPLETED BY: L. M. Parker TELEPHONE: (805) 545-3386 REPORT MONTH: February 2003 NO. DATE TYPE F (Forced)

DURATION (HOURS) REASON' METHOD OF CAUSEACTIONS

& CORRECTIVE S (Scheduled) SHUTTING DOWN 2 COMMENTS 1 030203 S 619.1 C 1 1Refueling Outage 11

1. Reason 2. Method A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation from Previous Month E-Operator Training/License Examination 5-Other F- Administrative G-Operational Error (Explain)

H-Other (Explain) 4