From: Darrell Adams
Pacific Gas & Electric Co
To: Cettin J
Office of Nuclear Reactor Regulation, Document Control Desk
References
DCL-23-068
Download: ML23221A374 (1)


Text

Dallas L. Adams Manager, Program Engineering Diablo Canyon Power Plant Mail code 104/4/427 P.O. Box 56 Avila Beach, CA 93424 805.545.6182 Dallas.Adams@pge.com A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek PG&E Letter DCL-23-068 John Cettin 10 CFR 74.15 NMMSS Program, NA-ESH-12 Germantown Building U.S. Department of Energy 1000 Independence Avenue, SW Washington, DC 20585-1290 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Nuclear Material Transaction Report for New Fuel

Dear Mr. Cettin,

Pursuant to 10 CFR 74.15(a), the enclosure provides one file in a computer-readable format of the Nuclear Material Transaction Report for materials received on July 31, 2023. The file was prepared in accordance with NUREG/BR-0006, Revision 9, Instructions for Completing Nuclear Material Transaction Reports, dated August 2020, and Nuclear Materials Management and Safeguards System (NMMSS)

Report D-24, Personal Computer Data Input for Nuclear Regulatory Commission Licensees, dated August 2016.

If you have any questions regarding the enclosure, please contact Mr. Joseph Lee at (805) 545-3348.

Sincerely, Dallas L. Adams Date Enclosure cc: Mahdi O. Hayes, NRC Senior Resident Inspector Samson S. Lee, NRC Senior Project Manager John D. Monninger, NRC Region IV Administrator NRC Document Control Desk Diablo Distribution Daniel Blount DOA for Dallas Adams 08/09/2023 m

Pacific Gas and Electric Company*