Craig D. Sutton Manager, Nuclear Radiation Protection Diablo Canyon Power Plant Mail code 104/5/521 P.O. Box 56 Avila Beach, CA 93424 805.545.4208 Craig.Sutton@pge.com A member of the STARS Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek PG&E Letter DCL-23-031 REIRS Project Manager 10 CFR 20.2206 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Annual Report of Occupational Radiation Exposure for 2022 REIRS Project Manager:
On April 4, 2023, Pacific Gas and Electric Company (PG&E) submitted the Annual Report of Occupational Radiation Exposure for individuals monitored at Diablo Canyon Power Plant during the 2022 calendar year in accordance with 10 CFR 20.2206(c). The report was created in the electronic format specified in Regulatory Guide 8.7, Revision 4, Instructions for Recording and Reporting Occupational Radiation Dose Data. The data file, NRC20230404.dat, was submitted electronically on the Radiation Exposure Information and Reporting System (REIRS) web page.
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.
If you have any questions about the report, please contact me at 805-545-4208.
Sincerely, Craig D. Sutton Date armb/50942689 cc:
Mahdi O. Hayes, NRC Senior Resident Inspector Samson S. Lee, NRC Project Manager Robert J. Lewis, NRC Acting Region IV Administrator NRC Document Control Desk Diablo Distribution 4/19/2023 Pacific Gas and Electric Company*