B12279, Forwards Major Milestone Schedule for Const & Implementation Phases of Erecting New Switchgear Bldg,Per NRC Approval of Exemption from Schedular Requirements of 10CFR50.48

From kanterella
Jump to navigation Jump to search
Forwards Major Milestone Schedule for Const & Implementation Phases of Erecting New Switchgear Bldg,Per NRC Approval of Exemption from Schedular Requirements of 10CFR50.48
ML20215E035
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 09/30/1986
From: Opeka J
CONNECTICUT YANKEE ATOMIC POWER CO.
To: Charemagne Grimes
Office of Nuclear Reactor Regulation
References
B12279, NUDOCS 8610140407
Download: ML20215E035 (5)


Text

>

CONNECTICUT YANKEE ATOMIC POWER COMPANY B E R L I N, CONNECTICUT P.o. Box 270 HARTFORD CONNECTICUT 06141-0270

"" September 30,1986 203-665-5000 Docket No. 50-213 B12279 Office of Nuclear Reactor Regulation Attn: Mr. Christopher L Grimes, Director Integrated Safety Assessment Project Directorate Division of PWR Licensing - B U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:

Haddam Neck Plant Major Implementation Milestones New Switchgear Building Construction In August,1986,(1) the NRC Staff granted the Connecticut Yankee Atomic Power Company (CYAPCO) an exemption from the schedular requirements o 10 CFR Section 50.48 in response to CYAPCO's request dated March 7, 1986.(2 The granting of this exemption was made subject to CYAPCO's submittal to the NRC Staff of a detailed implementation plan including major project milestones by September 30, 1986 for construction of the new switchgear room and subsequent bi-monthly progress reports. The granting of this exemption was also made contingent on dated July 3,1986,(which mplementation resulted fromofthe the firecommitments in CYAPCO's protection inspection and letter audit on June 16 - 20, 1986. CYAPCO remains committed to the modification described in the July 3,1986 letter as modified by the August 19 letter.(

CYAPCO herein responds fully to the additional conditions set forth in the August 25, 1986 letter from the NRC Staff.

In a letter dated June 30, 1986,(3) CYAPCO 1.rovided the NRC Staf f with the conceptual design information for the new switchgear room at the Haddam Neck (1) H. R. Denton letter to 3. F. Opeka, dated August 25,1986, " Fire Protection Exemption - Haddam Neck Plant."

(

orua (2) 3. F. Opeka letter to C.1. Grimes, dated March 7,1986, " Fire Protection -

Schedular Exemption."

SO' cgg (3) 3. F. Opeka letter to C. I. Grimes, dated July 3,1986, " Action items mo Resulting from inspection of Haddam Neck on June 16 - 20, 1986."

wt

$g (4) 3. F. Opeka letter to C. I. Grimes, dated August 19,1986, "Haddam Neck oo Plant Action Items Resulting from Appendix R Inspection of June 16 - 20, Y

O 1986."

25 (5) 3. F. Opeka letter to C. I. Grimes, dated June 30,1986, "Haddam Neck Plant m a.a. Conceptual Design of the New Switchgear Room." 49 fg,

. L ' t r2 u)L dn ey ,r . .

ne ns 0 01 *

- 'fl NRA MMr AtasL , T t I

' Plant including a description of the new facility. The detailed design of the new switchgear building is now proceeding with the contract awarded to Bechtel Eastern Power Corporation on September 22, 1986. The major milestone schedule for the construction and implementation phases of this project are provided as Attachment I.  ?

CYAPCO will provide the NRC Staff with updated bimonthly reports on the progress of this project commencing November 26,1986 (i.e., we interpret this submittal to trigger the start of the first two month interval). CYAFCO also intends to provide the NRC with sufficient information to complete the SER, consistent with the milestone schedule, to allow the Staff to perform their review concurrently with the development and construction of this project. As always CYAPCO remains available to meet with the NRC Staff to review progress and/or provide additional information that may be required to assure that the Staff review can be performed in a timely fashion.

Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY k . F. GA J. F. OpeW U Senior Vice President cc: Dr. T. E. Murley

s Attachment I Haddam Neck Plant Major Milestone Schedule New Switchgear Room

F 1 Attachment I Haddam Neck Plant Major Milestone Schedule New Switchgear Room Milestone Dates Award Contract to Architect / Engineer October 15,1986

. Completed - September 22,1986 Bimonthly Progress Report November 26,1986 Bimonthly Progress Report January 30,1987 Civil Drawings Issued for Construction March 2,1987 Construction Design Information Submitted March 31,1987 for NRC Review Bimonthly Progress Report March 31,1987 Switchgear Room Construction Begins April 1,1987 Bimonthly Progress Report May 29,1987 Major _ Equipment Purchase Orders Issued June 1,1987 Bimonthly Progress Report July 31,1987 Bimonthly Progress Report September 30,1987 Equipment Drawings Issued for Construction October 12,1987 Equipment Design Information Submitted November 30,1987 for NRC Review Bimonthly Progress Report November 30,1987 Bimo7thly Progress Report January 29,1988 Bimonthly Progress Report March 31,1988 Switchgear Room Structure Complete May 2,1988 Bimonthly Progress Report May 31,1988 Major Equipment Items Delivered to Site June 1,1988 Bimonthly Progress Report July 29,1988 Bimonthly Progress Report September 30,1988

\

Milestone Dates 1988 CY Refueling Outage (Cycle 15) Begins November 28,1988 Bimonthly Progress Report November 30,1988

' SWGR Equipment Installation Complete December 1,1988 System Tie-Ins and Testing Complete January 31,1989 Bimonthly Progress Report January 31,1989 1988 CY Refueling Outage (Cycle 15) Complete February 6,1989 Final Bimonthly Report March 31,1989 It should be noted that commencing with the 1988 refueling outage, dates are subject to change based upon the plant performance and other factors. The system tie-in and testing milestone will vary directly with the actual start date of the refueling outage. In any event, CYAPCO fully intends to complete these modifications prior to start up from the Cycle 15 outage.