Forwards LER 98-003-00 Re Concurrent Inoperability of a & B Cr.Commitments Made by Pse&G,Encl
ML20247E745
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 05/07/1998
From: Bezilla M
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20247E748 List:
References
LR-N980241, NUDOCS 9805180451
Download: ML20247E745 (2)


LER-2098-003, Forwards LER 98-003-00 Re Concurrent Inoperability of a & B Cr.Commitments Made by Pse&G,Encl
Event date:
Report date:
3542098003R00 - NRC Website

text

. -

~

l.- O PSEG Public Service Electric and Gas Compt.ny P.O. Box 236 Hancocks Bridge. New Jersey 08038-0236 Nuclear Business Unit MAY 071998 LR-N980241 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 HOPE CREEK GENERATING STATION l DOCKET NO. 50-354 UNIT NO.1 i LICENSEE EVENT REPORT NO. 98-003-00

Dear Sir:

This Licensee Event Report entitled " Concurrent inoperability of the "A" and "B" Control Room due to Missed Inservice Tests, Mis-positioned Regulators, and an incorrect Design Assumption" is being submitted pursuant to the requirements of 10CFR50.73(a)(2)(i)(B) and 10CFR50.73(a)(2)(v).

Sincerely, GG Ih.8sE2/lL&

Mark Bezilla ,,

General Manager Hope Creek Operations RAR/mw c: Distribution LER File f

^/.

9805180451 980507

~

( gDR ADOCK 05000354 i

PDR

'llle }wrr is ill)Uur llaIKh.

95 2108 AEV 694

Document Control Desk LR-N980241 Attachment A The following item represents the commitment that PSE&G is making to the NRC re;ative to LER 354/98-003-00:

1. Procedures to appropriately test the check valves will be developed by July 1,1998, which is prior to the next scheduled performance of these IST tests.
2. The engineering evaluation to determine the actual minimum low temperature for operation of SACS without an operable Instrument Air system, or an appropriate backup system, will be developed by July 9,1998.
3. Operating procedures will be revised to reflect the actual minimum low temperature for SACS when the engineering evaluation is completed. Operating procedures will also be developed to provide information relative to the operation of the regulators.

These procedure revisions will be completed by August 7,1998.

4. Training on the design, operations, and periodic testing of the backup nitrogen system will be provided to the operators by September 1,1998.
5. The workbook used in the preparation of this design change will be reviewed for enhancements. The procedures will be revised by July 31,1998 to separate the valve group and IST group signatures, as well as to incorporate other enhancements discovered during this review, as appropriate.
6. Lessons learned from this event will be discussed with Design Engineering, Maintenance Engineering, and Operations personnel. These discussions will be completed by September 30,1998.

[