Forwards LER 97-036-00,discussing Discrepancy Where Overload Relays for Makeup & Purification Sys High Pressure Injection Valves Were Not Set in Automatic Reset Mode of Operation
ML20199H137
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 11/21/1997
From: Rencheck M
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20199H141 List:
References
3F1197-10, NUDOCS 9711260028
Download: ML20199H137 (1)


LER-2097-036, Forwards LER 97-036-00,discussing Discrepancy Where Overload Relays for Makeup & Purification Sys High Pressure Injection Valves Were Not Set in Automatic Reset Mode of Operation
Event date:
Report date:
3022097036R00 - NRC Website

text

- _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ .- -- - - - ..

/

s Florida >

> Power

= . ,

om .x.: -

November 21, 1997 ,

3F119710 ,

U.S. Nuclear Regulatory Commission Attn: Docurnent Control Desk Washington, D.C. 20555-0001

Subject:

LICENSEE EVENT REPORT (LER) 50-302/97-036-00

Dear Sir:

Please find the enclosed Licensee Event Report (LER) 50-302/97-036-00. This LER discusses a discrer,ancy where the overload relays for the Makeup and Purification (MU) System High Pressure injection (HPI) valves were not set in the automatic reset mode of operation. This report is neing submitted pursuant to 10CFR50.73.

Sincerely,

/4/9 $4/L \

M. W. Rencheck Director

\

Nuclear Engineering and Projects MWR/pmp

-( hg  !

Encloswes

{

xc: Regional Administrator, Region 11 Senior Resident inspector NRR Project Manager 9711260028 971121 {-((,gj(}l((l]lg((((}l PDR ADOCK 0S000302 ,,,,....