Discusses FPC 970819 Request for Temporary Relief from ASME Code Section XI Requirements to Repair ASME Class 3 Nuclear Service & Decay Heat Sea Water System Piping.Forwards SE Containing Results of Staff Review
ML20217F994
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 10/15/1999
From: Wiens L
NRC (Affiliation Not Assigned)
To: Cowan J
FLORIDA POWER CORP.
Shared Package
ML20217F997 List:
References
TAC-MA6367, NUDOCS 9910210150
Download: ML20217F994 (3)


Text

b

~

a

- Mr. John P ul Cowan October 15, 1999 Vice Przsident, Nucle r Optr:tions

, ' Florida Pow;r Corpor; tion ATTN: Manager, Nuclear Licensing (NA1B)

Crystal River Energy Complex 15760 W. Power Line Street '

Crystal River, Florida 34428-6708

SUBJECT:

REQUEST FOR TEMPORARY RELIEF FROM ASME CODE REPAlR REQUIREMENTS FOR ASME CLASS 3 NUCLEAR SERVICE AND DECAY HEAT SEA WATER SYSTEM - CRYSTAL RIVER UNIT 3 (TAC NO. MA6367)

Dear Mr. Cowan:

By letter dated August 19,1997, Florida Power Corporation'(FPC) requested temporary

. relief from the American Society of Mechanical Engineers (ASME) Code,Section XI requirements to repair ASME Class 3 Nuclear Service and Decay Heat Sea Water System 1

Piping. Included with this submittal was the engineering evaluation of the flaw, which showed that the structuralintegrity of the piping'was adequate for continued plant operation. The staff's evaluation and conclusions related to the FPC regt.est a e contained in the enclosed Safety Evaluation. Prior to the cornpletion of proceetir.ginis request, Crystal River Unit 3 entered a refueling outage, which eliminated th e conditk n that necessitated the request for relief.

However, the results of the staff's review cre being provided for your records.

Sincerely, WA.N ns,Ye"nYorhoject Manager, Section 2

' Project Directorate ll Division of Licensing Project Management Office of Nuclear Reactor acaulation Docket No. 50-302

Enclosure:

Safety Eva!uation cc w/ enclosure: See next page -

&,e ln.}& fimdf 06h Ot*

c s

m DISTRIBUTION:

RScholl(e-mailSE only RFS)

\\

'Dochet FNe' SSheng

't PUBLIC OGC CrystalReading

'ACRS BClayton -

' LWert, Ril fy LWiens SPeterson Y

DOCUMENTNAME: G:\\PDil-2\\ Crystal \\ RELA 6367.WPD l

re m e am or me m s,em. e, ese s c -c - cm.o or arrecs,,,.,,va,a a.

t-cm,,e. m u,cs,w.

u - u. cm OFMCE PDil-2\\PM, M

PDil-2\\LA i PDil-2\\SCm

~

NAME LWieneftMC*J BCIsyton. U SPeterebtf DATE 1Gb99 1DW99 Y 1GL'199 l1W 199 1W /99 ORD CM 9910210150 5 1015

~

PDR ADOCK 05000302 P

PDR

z.

l' pa ttoo j

pr.

<4-UNITED STATES 3

,j NUCLEAR REGULATORY COMMISSION

'2-WASHINGTON. D.C. 20555-0001 kg..... /

October 15, 1999

- Mr. John Paul Cowan Vice Preside'nt, Nuclear Operations Florida Power Corporation ATTN: Manager, Nuclear Licensing (NA18)

Crystal River Energy Complex i-15760 W. Power Line Street

?

Crystal River, Florida 34420-6708

SUBJECT:

REQUEST FOR TEMPORARY RELIEF FROM ASME CODE REPAIR REQUIREMENTS FOR ASME CLASS 3 NUCLEAR SERVICE AND DECAY HEAT SEA WATER SYSTEM - CRYSTAL RIVER UNIT 3 (TAC NO. MA6367)

Dear Mr. Cowan:

' By letter dated August 19,1997, Florida Power Corporation (FPC) requested temporary relief from the American Society of Mechanical Engineers (ASME) Code,Section XI requirements to repair ASME Class 3 Nuclear Service and Decay Heat Sea Water System 1

' Piping. Included with this submittal was the engineering evaluation of the flaw, which showed that the structuralintegrity of the piping was adequate for continued plant operation. The staff's evaluation and conclusions related to the FPC request are contained in the enclosed Safety Evaluation. Prior to the completion of processing this request, Crystal River Unit 3 entered a j

refueling outage, which eliminated the condition that necessitated the request for relief.

' However, the results of the staff's review are being provided for your records.

Sincerely, y, t~I L. A. Wiens, Senior Project Manager, Section 2 Project Directorate il Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

Safety Evaluation cc w/ enclosure: See next page J: -

1 Mr. John Paul Cowan CRYSTAL RIVER UNIT NO. 3 Flonda Power Corporation cc:

J Mr. R. Alexander Glenn Chairman I

Corporate Counsel (MAC-BT15A)

Board of County Commissioners Flonda Power Corporation C.trus County P.O. Box.14042

'110 North Apopka Avenue St. Petersburg, Florida 33733-4042

. Invemess, Florida 34450-4245 Mr. Charies G. Pardee, Director Ms. Sherry L. Bemboft, Director Nuclear Plant Operations (PA4A)

Nuclear Regulatory Affairs (NA2H)

Flonda Power Corporation.

Florida Power Corporation Crystal River Energy Complex Crystal River Energy Complex 15760 W. Power Line Street 15760 W. Power Line Street

- Crystal River, Florida 34428-6708 Crystal River, Florida 34428-6708 Mr. Michael A. Schoppman Senior Resident inspector Framatome Technologies Inc.

Crystal River Unit 3 1700 Rockville Pike, Suite 525 U.S. Nuclear Regulatory Commission Rockville, Maryland 20852 6745 N. Tallahassee Road i

Crystal River, Florida 34428 Mr. William A. Passetti, Chief Department of Health Mr. Gregory H. Halnon Bureau of Radiation Control Director, Quality Programs (SA2C) 2020 Capital Circle, SE. Bin #C21 Florida Power Corporation Tallahassee, Florida 32399-1741 Crystal River Energy Complex 15760 W. Power Line Street Attomey General Crystal River, Florida 34428-6708 I)epartment of Legal Affairs

'Jhe CapNI Yallahssee, Florida 32304 4

MrcJoe Myprs, Director Division of Emergency Preparedness Department of Community Affairs 274G Oenterview Drive i

Tallahassee, Florida 32399-2100 j

i I

l I