IR 05000387/2023004 | 7 February 2024 | Integrated Inspection Report 05000387/2023004 and 05000388/2023004 | |
IR 05000387/2023010 | 11 December 2023 | Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 | Safe Shutdown Fire Barrier Aging Management Time Critical Operator Action License Renewal Fire Protection Program |
IR 05000387/2023003 | 3 November 2023 | Integrated Inspection Report 05000387/2023003 and 05000388/2023003 | Enforcement Discretion Temporary Modification Functionality Assessment Aging Management Significance Determination Process Foreign Material Exclusion Operability Determination License Renewal Through-Wall Leak Offsite Circuit Fire Protection Program Exclusive Use |
IR 05000387/2023301 | 20 September 2023 | Initial Operator Licensing Examination Report 05000387/2023301 and 05000388/2023301 | |
IR 05000387/2023005 | 31 August 2023 | Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2023005 and 05000388/2023005) | Commercial Grade Dedication Cyber Security License Renewal |
IR 05000387/2023002 | 1 August 2023 | Integrated Inspection Report 05000387/2023002 and 05000388/2023002 | Shutdown Margin Enforcement Discretion Nondestructive Examination Temporary Modification Functionality Assessment Aging Management Operability Determination License Renewal Liquid penetrant Fire Protection Program Dissimilar Metal Weld Power change |
IR 05000387/2023401 | 7 June 2023 | Security Baseline Inspection Report 05000387/2023401 and 05000388/2023401 | Fitness for Duty Fatigue Rule |
IR 05000387/2023001 | 12 May 2023 | Integrated Inspection Report 05000387/2023001 and 05000388/2023001 | High Radiation Area Enforcement Discretion Probabilistic Risk Assessment Temporary Modification Functionality Assessment FLEX Aging Management Significance Determination Process Scram Discharge Volume Operability Determination License Renewal Fire Protection Program Coast down Unidentified leakage |
IR 05000387/2022006 | 1 March 2023 | Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2022006 and 05000388/2022006) | Commercial Grade Dedication Cyber Security License Renewal Exemption Request COVID-19 |
IR 05000387/2022004 | 8 February 2023 | Integrated Inspection Report 05000387/2022004 and 05000388/2022004 | Stroke time Enforcement Discretion Temporary Modification Cyber Security Functionality Assessment Scram Discharge Volume Operability Determination Severe Accident Management Guideline License Renewal Through-Wall Leak Fire Protection Program Unidentified leakage |
IR 07200028/2022001 | 15 December 2022 | Independent Spent Fuel Storage Installation (ISFSI) - NRC Inspection Report No. 07200028/2022001 | Non-Destructive Examination Tornado Missile Hydrostatic Fire Protection Program |
IR 05000387/2022403 | 29 November 2022 | Security Baseline Inspection Report 05000387/2022403 and 05000388/2022403 | |
IR 05000387/2022501 | 28 November 2022 | Emergency Preparedness Biennial Exercise Inspection Report 05000387/2022501 and 05000388/2022501 | Fuel cladding |
IR 05000387/2022404 | 9 November 2022 | Cyber Security Inspection Report 05000387/2022404 and 05000388/2022404 (Cover Letter Only) | Cyber Security Affidavit |
IR 05000387/2022003 | 8 November 2022 | Integrated Inspection Report 05000387/2022003 and 05000388/2022003 | Shutdown Margin Safety Limit Minimum Critical Power Ratio Internal Flooding Past operability Enforcement Discretion Probabilistic Risk Assessment Temporary Modification Functionality Assessment Condition Adverse to Quality FLEX Significance Determination Process Large early release frequency Operability Determination Fire Protection Program Power change Unidentified leakage |
IR 05000387/2022013 | 28 September 2022 | Design Basis Assurance Inspection (Teams) Inspection Report 05000387/2022013 and 05000388/2022013 | Stroke time FLEX Large early release frequency Battery sizing |
IR 05000387/2022005 | 31 August 2022 | Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2022005 and 05000388/2022005) | Commercial Grade Dedication Cyber Security License Renewal Exemption Request COVID-19 COVID19 |
IR 05000387/2022010 | 11 August 2022 | Biennial Problem Identification and Resolution Inspection Report 05000387/2022010 and 05000388/2022010 | Reactor Vessel Water Level Half scram Enforcement Discretion Condition Adverse to Quality Significance Determination Process Large early release frequency Fast acting solenoid valve Power Uprate |
IR 05000387/2022401 | 11 August 2022 | Material Control and Accounting Program Inspection Report 05000387/2022401 and 05000388/2022401 (Cover Letter Only) | Affidavit |
IR 05000387/2022002 | 4 August 2022 | Integrated Inspection Report 05000387/2022002 and 05000388/2022002 | High Radiation Area Internal Flooding Enforcement Discretion Nondestructive Examination Temporary Modification Functionality Assessment FLEX Aging Management Significance Determination Process Operability Determination License Renewal Fire Protection Program |
IR 05000387/2022001 | 9 May 2022 | Integrated Inspection Report 05000387/2022001 and 05000388/2022001 | Safe Shutdown Past operability Enforcement Discretion Emergency Lighting Functionality Assessment FLEX Significance Determination Process Scram Discharge Volume Large early release frequency Operability Determination Fire Protection Program Coast down |
IR 05000387/2022011 | 7 March 2022 | Post-Approval Site Inspection for License Renewal - Phase 2 Inspection Report 05000387/2022011 | Aging Management License Renewal |
IR 05000387/2021006 | 2 March 2022 | Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2021006 and 05000388/2021006) | Fitness for Duty Cyber Security License Renewal Exemption Request COVID-19 |
IR 05000387/2022402 | 16 February 2022 | Security Baseline Inspection Report 05000387/2022402 and 05000388/2022402 | Fitness for Duty |
IR 05000387/2021403 | 11 February 2022 | Cyber Security Problem Identification and Resolution Inspection Report 05000387/2021403 and 05000388/2021403 (Cover Letter Only) | Cyber Security Affidavit |
IR 05000387/2021004 | 11 February 2022 | Integrated Inspection Report 05000387/2021004 and 05000388/2021004 | Ultimate heat sink Internal Flooding Enforcement Discretion Temporary Modification Cyber Security Functionality Assessment Significance Determination Process Operability Determination Through Wall Leak Fire Protection Program |
IR 05000387/2021010 | 13 December 2021 | Design Basis Assurance Inspection (Programs) Inspection Report 05000387/2021010 and 05000388/2021010 | Ultimate heat sink Scram Discharge Volume Power-Operated Valves Weak link |
IR 05000387/2021011 | 4 November 2021 | Temporary Instruction 2515/194 Inspection Report 05000387/2021011 and 05000388/2021011 | Probabilistic Risk Assessment Open Phase Condition Coronavirus |
IR 05000387/2021003 | 3 November 2021 | Integrated Inspection Report 05000387/2021003 and 05000388/2021003 | Safety Limit Minimum Critical Power Ratio Enforcement Discretion Functionality Assessment Significance Determination Process Operability Determination License Renewal Maintenance Rule Program Pandemic Coronavirus COVID-19 Through-Wall Leak Fire Protection Program Scaffolding Power Uprate |
IR 05000387/2021401 | 25 October 2021 | Security Baseline Inspection Report 05000387/2021401 and 05000388/2021401 | Coronavirus COVID-19 |
IR 05000387/2021402 | 23 September 2021 | Security Baseline Inspection Report 05000387/2021402 and 05000388/2021402 | Coronavirus COVID-19 |
IR 05000387/2021301 | 17 September 2021 | Initial Operator Licensing Examination Report 05000387/2021301 and 05000388/2021301 | |
IR 05000387/2021005 | 1 September 2021 | Updated Inspection Plan for the Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2021005 and 05000388/2021005) | Fitness for Duty Operator Manual Action Cyber Security Open Phase Condition License Renewal Exemption Request Power-Operated Valves Power Operated Valves COVID-19 |
ML21224A240 | 24 August 2021 | Security Baseline Inspection Report Cover Letter 2021 FOF | |
IR 05000387/2021002 | 4 August 2021 | Integrated Inspection Report 05000387/2021002 and 05000388/2021002 | High Radiation Area Ultimate heat sink Internal Flooding Temporary Modification Functionality Assessment Condition Adverse to Quality Scram Discharge Volume Operability Determination License Renewal Maintenance Rule Program Coronavirus COVID-19 Fire Protection Program |
IR 05000387/2021001 | 5 May 2021 | Integrated Inspection Report 05000387/2021001 and 05000388/2021001 | Stroke time Commercial Grade Dedication Enforcement Discretion Nondestructive Examination Temporary Modification Functionality Assessment Test box Significance Determination Process Operability Determination License Renewal Coronavirus COVID-19 Fire Protection Program Power change Coast down |
IR 05000388/2021012 | 4 March 2021 | EA-20-131: Susquehanna Steam Electric Station, Unit 2 - NRC Investigation Report No. 1-2020-001 and NRC Inspection Report No. 05000388/2021012 | High Radiation Area Locked High Radiation Area Significance Determination Process |
IR 05000387/2020006 | 3 March 2021 | Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2020006 and 05000388/2020006) | Fitness for Duty Operator Manual Action Open Phase Condition License Renewal Exemption Request Power-Operated Valves Power Operated Valves COVID-19 |
IR 05000387/2020403 | 10 February 2021 | Cyber Security Problem Identification and Resolution Inspection Report 05000387/2020403 and 05000388/2020403 (Cover Letter Only) | Cyber Security Affidavit |
IR 05000387/2020004 | 8 February 2021 | Integrated Inspection Report 05000387/2020004 and 05000388/2020004 | Internal Flooding Past operability Cyber Security Emergency Lighting Functionality Assessment FLEX B.5.b Significance Determination Process Operability Determination Coronavirus COVID-19 Through Wall Leak Fire Protection Program |
IR 05000387/2020501 | 18 November 2020 | Emergency Preparedness Biennial Exercise Inspection Report 05000387/2020501 and 05000388/2020501 | Pandemic Coronavirus COVID-19 |
IR 05000387/2020003 | 5 November 2020 | Integrated Inspection Report 05000387/2020003 and 05000388/2020003 | High Radiation Area Internal Flooding Temporary Modification Functionality Assessment Operability Determination Pandemic Coronavirus COVID-19 Fire Protection Program |
IR 05000387/2020012 | 27 October 2020 | Triennial Fire Protection Inspection Report 05000387/2020012 and 05000388/2020012 | Safe Shutdown Fire Barrier Operator Manual Action License Renewal Coronavirus COVID-19 Fire Protection Program Fire Watch Hourly Fire Watch |
IR 05000387/2020005 | 31 August 2020 | Updated Inspection Plan (Inspection Reports 05000387/2020005 and 05000388/2020005) | Fitness for Duty Internal Flooding Operator Manual Action Open Phase Condition License Renewal Exemption Request Power-Operated Valves Power Operated Valves COVID-19 |
IR 05000387/2020011 | 18 August 2020 | Biennial Problem Identification and Resolution Inspection Report 05000387/2020011 and 05000388/2020011 | Enforcement Discretion Condition Adverse to Quality Coronavirus COVID-19 |
IR 05000387/2020002 | 11 August 2020 | Integrated Inspection Report 05000387/2020002 and 05000388/2020002 | Internal Flooding Hydrostatic Enforcement Discretion Nondestructive Examination Temporary Modification Functionality Assessment Significance Determination Process Foreign Material Exclusion Operability Determination Coronavirus COVID-19 EVT-1 Liquid penetrant Fire Protection Program Scaffolding Downpower |
IR 05000387/2020401 | 2 July 2020 | Security Baseline Inspection Report 05000387/2020401 and 05000388/2020401 | Coronavirus COVID-19 |
IR 05000387/2020001 | 5 May 2020 | Integrated Inspection Report 05000387/2020001 and 05000388/2020001 | Reactor Vessel Water Level High Radiation Area Enforcement Discretion Functionality Assessment Locked High Radiation Area Scram Discharge Volume Operability Determination Coronavirus COVID-19 Fire Protection Program Power change Coast down |
IR 05000387/2019006 | 3 March 2020 | Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2019006 and 05000388/2019006) | Open Phase Condition License Renewal Power-Operated Valves Power Operated Valves |
IR 05000387/2020010 | 21 February 2020 | Temporary Instruction 2515/194 Inspection Report 05000387/2020010 and 05000388/2020010 | Open Phase Condition |