IR 05000387/2020012

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000387/2020012 and 05000388/2020012
ML20301A482
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 10/27/2020
From: Glenn Dentel
Engineering Region 1 Branch 2
To: Berryman B
Susquehanna
Dentel G
References
IR 2020012
Download: ML20301A482 (15)


Text

October 27, 2020

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000387/2020012 AND 05000388/2020012

Dear Mr. Berryman:

On October 8, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Susquehanna Steam Electric Station, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, X /RA/

Signed by: Glenn T. Dentel

Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety

Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000387 and 05000388

License Numbers:

NPF-14 and NPF-22

Report Numbers:

05000387/2020012 and 05000388/2020012

Enterprise Identifier: I-2020-012-0006

Licensee:

Susquehanna, LLC

Facility:

Susquehanna Steam Electric Station, Units 1 and 2

Location:

Berwick, PA

Inspection Dates:

September 21, 2020 to October 8, 2020

Inspectors:

C. Bickett, Senior Reactor Inspector

E. DiPaolo, Senior Reactor Inspector

D. Kern, Senior Reactor Inspector

Approved By:

Glenn T. Dentel, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Susquehanna Steam Electric Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Inadequate Diesel-Driven Fire Pump 3-Hour Fire Barrier Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000387,05000388/2020012-01 Open/Closed None (NPP)71111.21N.05 The team identified a finding of very low safety significance (Green) involving a non-cited violation (NCV) of Unit 1 License Condition 2.C.(6) and Unit 2 License Condition 2.C.(3) for failure to implement and maintain in effect all provisions of the approved fire protection program as described in the Fire Protection Review Report (FPRR) for the facility and as approved by the NRC. Specifically, Susquehanna failed to enclose the diesel-driven fire pump within a 3-hour rated fire enclosure as described in the FPRR.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21N.05 - Fire Protection Team Inspection (FPTI)

Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===

The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:

(1) Fire Protection Water Supply System
(2) Residual Heat Removal System
(3) Automatic Depressurization System/Safety-Relief Valves
(4) Fire Barrier System

Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)

The inspectors verified that the following fire protection program administrative controls were implemented in accordance with the current licensing basis:

(1) Combustible Control Program
(2) Fire Watch Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors reviewed the following changes to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and to verify that fire protection program documents and procedures affected by the changes were updated:

(1) Engineering Change 1544685, Fire Pump Replacement

INSPECTION RESULTS

Inadequate Diesel-Driven Fire Pump 3-Hour Fire Barrier Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000387,05000388/2020012-01 Open/Closed

None (NPP)71111.21N.05 The team identified a finding of very low safety significance (Green) involving a non-cited violation (NCV) of Unit 1 License Condition 2.C.(6) and Unit 2 License Condition 2.C.(3) for failure to implement and maintain in effect all provisions of the approved fire protection program as described in the Fire Protection Review Report (FPRR) for the facility and as approved by the NRC. Specifically, Susquehanna failed to enclose the diesel-driven fire pump within a 3-hour rated fire enclosure as described in the FPRR.

Description:

Both the motor-driven and diesel-driven fire pumps are located in close proximity within the Circulating Water Pump House. The diesel-driven fire pump is located inside an enclosure that was described by the SSES FPRR to be 3-hour fire rated to prevent both fire pumps from being damaged by a single fire, thus affecting their capability to provide fire protection water during an event. During a tour of the Circulating Water Pump House, the team observed a gap, approximately 1-inch wide, in the junction of the diesel-driven fire pump enclosure cinder block wall and the Circulating Water Pump House interior wall. The gap was filled with an unknown board-type material that resembled polystyrene. The team questioned whether the gap and material were depicted on fire barrier drawings of the enclosure.

Construction drawings of the Circulating Water Pump House showed the diesel-driven fire pump enclosure walls were 3-hour fire rated but did not depict or note the gap or the filler material. The team noted that the drawings specified the rooms ceiling was a poured concrete slab with a gap between the slab and Circulating Water Pump House wall. That gap was specified to be filled with a compressible material.

Susquehanna sampled the filler material, concluded it was most likely polystyrene, and that the material was combustible. As a result, the team concluded that Susquehanna failed to enclose the diesel-driven fire pump within a 3-hour rated fire enclosure as described in the FPRR, and both fire pumps were not assured protection from being damaged by a single fire.

Corrective Actions: Susquehanna declared the diesel-driven fire pump room fire barrier non-functional and established an hourly fire watch as a compensatory measure. Susquehanna performed an evaluation of the configuration per NRC Generic Letter 86-10. That evaluation concluded the deficient condition did not negatively impact the barriers ability to prevent a single fire from disabling both the motor-driven and diesel-driven fire pumps.

Corrective Action References: CR-2020-13254 and CR-2020-13799

Performance Assessment:

Performance Deficiency: The team determined that the failure to enclose the diesel-driven fire pump within a 3-hour fire rated enclosure, as described in Section 4.1 of the SSES FPRR, was a performance deficiency that was within Susquehannas ability to foresee and correct.

As a result, both fire pumps (i.e., the motor-driven fire pump and the diesel-driven fire pump)were not assured protection from being damaged by a single fire.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, failing to enclose the diesel-driven fire pump within a 3-hour rated enclosure did not assure that both fire pumps were protected from being damaged by a single fire which could have affected their capability to provide fire protection water during a fire event. In addition, this finding is more than minor because it was similar to Example 3.g of IMC 0612, Appendix E, Examples of Minor Issues. Regardless of the final operability or functionality, the as-found condition was such that there was reasonable doubt with respect to the availability, reliability or capability of systems.

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Appendix F was applicable in this case because the finding was associated with fire water supply systems. This issue screened as Green in Step 1.4.3 because adequate fire water capacity was still available for protection of equipment important to safe shutdown in the most limiting location onsite. Susquehanna performed a detailed evaluation of the arrangement in the Circulating Water Pump House.

The evaluation concluded that the deficient condition did not negatively impact the degraded fire barriers ability to prevent a single fire from disabling both the motor-driven and diesel-driven fire pumps. In addition, the site is equipped with a backup diesel-driven fire pump, remote to the Circulating Water Pump House, that could be placed in service per plant operating procedures.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance. The installation of the non-fire rated material used as a fire barrier was performed during the construction of the diesel-driven fire pump enclosure. Although a periodic inspection is performed on Circulating Water Pump House fire barriers, the scope of the inspection was to visually identify degradation that could prevent barriers from meeting their design function. The inspectors concluded that identification of incorrect fire barrier material was beyond the scope of the periodic inspection.

Enforcement:

Violation: Unit 1 License Condition 2.C.(6) and Unit 2 License Condition 2.C.(3), in part, requires Susquehanna Nuclear, LLC to implement and maintain in effect all provisions of the approved fire protection program as described in the FPRR for the facility and as approved by the NRC. SSES FPRR, Section 4.1, Fire Protection Water Supply System, stated that the diesel-driven fire pump is enclosed within a 3-hour fire rated enclosure which prevents both fire pumps (i.e., the motor-driven fire pump and the diesel-driven fire pump)from being damaged by a single fire.

Contrary to the above, since July 17, 1982, the effective date of the Unit 1 operating license, until September 24, 2020, when the issue was entered into the corrective action program, Susquehanna failed to enclose the diesel-driven fire pump within a 3-hour fire rated fire enclosure which prevents both fire pumps from being damaged by a single fire.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 8, 2020, the inspectors presented the triennial fire protection inspection results to Mr. Brad Berryman and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.05 Calculations

EC-013-0852

Evaluation for Identification and Disposition of Appendix R

Section III.G Non-Compliant Cables

Revision 1

EC-013-1031

Documentation to Support Qualification of the Penetration

Seal Installation at SSES

Revision 3

EC-013-1040

Combustible Loading Data for Input to CRIMP

Revision 5

EC-013-1040

Combustible Loading Data for Input to CRIMP

Revision 5

EC-013-1873

Operator Manual Actions Feasibility Analysis

Revision 4

EC-018-0843

SSES 10 CFR 50 Appendix R Compliance Manual

Revision 47

EC-083-0660

Number of Open SRVs Required in Shutdown Cooling

Revision 1

EC-PUPC-20400

EPU Task Report T0400 - Containment System Response

Revision 5

EC-THYD-1064

MAAP Analysis of Appendix R Scenarios

Revision 3

Corrective Action

Documents

CR 2018-08886

CR-2016-22822

CR-2017-19925

CR-2018-02016

CR-2018-06103

CR-2018-07710

CR-2018-14540

CR-2018-16833

CR-2018-17185

CR-2019-04113

CR-2019-12711

CR-2019-13600

CR-2020-07321

CR-2020-11023

CR-2020-12789

NCR 87-0898

Corrective Action

Documents

Resulting from

Inspection

AR-2020-12955

AR-2020-13012

AR-2020-13081

AR-2020-13149

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR-2020-13241

AR-2020-13247

CR-2020-13030

CR-2020-13032

CR-2020-13103

CR-2020-13229

CR-2020-13230

CR-2020-13254

CR-2020-13270

CR-2020-13271

CR-2020-13419

CR-2020-13439

CR-2020-13570

CR-2020-13756

CR-2020-13771

CR-2020-13779

CR-2020-13782

CR-2020-13783

CR-2020-13851

CR-2020-13896

CR-2020-13899

CR-2020-13912

Drawings

D-107415

Fire Protection Engine Driven Fire Pump Control Scheme

0S1401, Sheet 1

Revision 12

D-193314

Circuit Breaker Interruption Impact Diagram 208/120V AC

Panel 1Y629, Sheet 54

Revision 7

E-105012, Sheet

Circulating Water Pumphouse Water Treatment Building

Fire Protection

Revision 5

E-105566

Circulating Water Pumphouse and Water Treatment

Building Sections and Details

Revision 3

E-106227,

Sheets 1, 2, 3,

and 6

Fire Protection System

Revision 61

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

E-266

Motor Driven Fire Pump 0P512 and Jockey Fire Pump

0P543, Sheets 1 and 2

Revision 14

E-690, Sheet 1

Appendix R Safe Shutdown Manual Actions List

Revision 8

Engineering

Changes

EC 1544685

Fire Pump Replacement Project

Revision 9

Engineering

Evaluations

86-10 Fire Hazards Analysis Evaluation for Diesel-Driven

Fire Pump Fire Barrier Gap

10/06/2020

Fire Protection Screening Document 00109, Fire Pump

Replacement

01/16/2015

Maintenance Rule Evaluation 0S573 (Back-up Diesel

Driven Fire Pump) Charge Air Cooler Gasket Leak

07/16/2020

50.59 SD 02291

Maintaining Door 571D in the Open Position

Revision 0

C-1072

Specification for the Inspection of Fire Barriers for

Compliance with PPL Susquehanna LLC Technical

Requirements Manual

Revision 6

CR 1198879

Evaluation of NRC Information Notice 2009-29, Potential

Failure of Fire Water Supply Pumps to Automatically Start

Due to a Fire

E-1012

Electrical Separation Criteria

Revision 2

EC-013-1027

Technical Evaluation of Fire Barrier Surveillance

Requirements

Revision 8

Engineering

Work Request 631730

Investigate the Physical Separation of Cable for 0P512

and 0P511

01/31/2007

FPSD 00160

Fire Protection Program Screen for Maintaining Door 571R

in the Open Position

Revision 0

SSES-1-LI-012-

ME-002-R0

Fire Pump Upgrade Replacement Project-Code

Compliance Review

Revision 0

Miscellaneous

Vendor Manual 0S573M JU/JW/JX Models Electronic

Engines for Fire Pump Applications

March 2017

Susquehanna Steam Electric Station Fire Protection

Review Report

Revision 24

Time Critical and Time Sensitive Operator Action

Validation per NDAP-QA-0343

2016

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

TCOA Event #34 Validation

10/05/2020

Vendor Technical Manual-Torna Tech-Operation,

Installation and Maintenance for Diesel Engine Fire Pump

Controller, Model GPD

9502-09

TRAK2000 Cable Management System (CRIMP) Software

Verification & Validation Results Report

Revision 20

IEEE-384-1974

IEEE Trial-Use Standard Criteria for Separation of Class

1E Equipment and Circuits

IEEE-384-2008

IEEE Standard Criteria for Independence of Class 1E

Equipment and Circuits

LDCN 5331

Fire Water Treatment Technical Change

01/05/2018

NFPA 20-1974

Centrifugal Fire Pumps

OT-013-019

Diesel Driven Fire Pump 0P511 Performance Test

August 2019

OT-013-020

Motor Driven Fire Pump 0P512 Performance Tes

January

2019

OT-013-021

Backup Diesel Driven Fire Pump 0P592 Performance Test

June 2020

PT-013-042

Month Inspection of Non-Reg Fire Rated

Assemblies/Barrier

Revision 8

SO-013-001

Monthly Diesel and Motor Driven Fire Pump Run

August 2020

SO-013-001B

Monthly Backup Diesel Fire Pump Run

August 2020

TP-013-065

EC 1544685 Partial 3 Initial Field Acceptance Testing

October

2016

TP-013-066

EC 1544685 Partial 2 Initial Field Acceptance Testing

October

2016

TP-013-250

EC 1544685 Partial 1 Initial Field Acceptance Testing

December

2015

TRM 3.7.3

Suesquehanna Unit 1 Technical Requirements Manual,

Fire Protection

03/31/2006

Procedures

AOP-149-001

RHR Abnormal Operating Procedure

Revision 4

AOP-151-001

Core Spray Abnormal Operating Procedure

Revision 2

DC-OP-011

Post-Fire Recovery Actions

Revision 18

EO-100-030

Unit 1 Response to Station Blackout

Revision 40

LA-0526-001

Diesel Fire Pump Control Panel 0C526

Revision 5

NDAP-QA-0101

Document Review

Revision 8

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NDAP-QA-0343

Time Critical and Time Sensitive Operator Actions

Revision 4

NDAP-QA-0440

Control of Transient Combustible/Hazardous Materials

Revision 23

NDAP-QA-0443

Firewatch Procedure

Revision 17

NDAP-QA-0446

Fire Barrier Program

Revision 11

NDAP-QA-0449

Fire Protection Program

Revision 19

NSEP-AD-0440

Fire Protection Program License Renewal Program Basis

Document

Revision 23

ON-013-001

Response to Fire

Revision 50

ON-SDC-101

Loss of Shutdown Cooling

Revision 4

OP-013-001

Fire Protection System

Revision 61

OP-013-003

Backup Fire Protection System

Revision 35

SE-013-006

24-Month Inspection of Common Fire Rated Penetration

Seals

Revision 13

SE-013-007

Month Inspection of Unit Common Fire Barriers

Revision 12

SE-013-008

Month Inspection of Common Fire Doors

Revision 14

SE-013-009

Month Inspection of Fire Windows/Fire Dampers and

Associated Hardware

Revision 7

SE-113-006

Unit 1 24 Month Inspection of Fire Rated Penetration

Seals

Revision 12

SE-113-007

Month Inspection of Unit 1 Fire Barriers

Revision 14

SE-113-008

Month Inspection of Unit 1 Fire Doors

Revision 12

SE-213-006

Unit 2 24 Month Inspection of Fire Rated Penetration

Seals

Revision 11

SE-213-007

Month Inspection of Unit 2 Fire Barriers

Revision 14

SE-213-008

Month Inspection of Unit 2 Fire Doors

Revision 13

SO-100-007

Daily Operations Surveillance

09/17/2020

SO-200-007

Unit 2 Daily Operations Surveillance

09/16/2020

Self-

Assessments

Fire Protection Program Self-Assessment

08/10/2020

Work Orders

RTSV 1910271

RTSV 1910555

RTSV 1910555

RTSV 1996346

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RTSV 2004186

RTSV 2072714

RTSV 2077949

RTSV 2170087

RTSV 2184813

WO 2182656

WO 2296915