IR 05000387/2022013

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000387/2022013 and 05000388/2022013
ML22270A222
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 09/28/2022
From: Mel Gray
NRC/RGN-I/DORS
To: Berryman B
Susquehanna
Gray M
References
IR 2022013
Download: ML22270A222 (17)


Text

September 28, 2022

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000387/2022013 AND 05000388/2022013

Dear Brad Berryman:

On August 25, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2 and discussed the results of this inspection with Kevin Cimorelli, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Susquehanna Steam Electric Station, Units 1 and 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC Resident Inspector at Susquehanna Steam Electric Station, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety

Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000387 and 05000388

License Numbers:

NPF-14 and NPF-22

Report Numbers:

05000387/2022013 and 05000388/2022013

Enterprise Identifier: I-2022-013-0004

Licensee:

Susquehanna Nuclear, LLC

Facility:

Susquehanna Steam Electric Station, Units 1 and 2

Location:

Berwick, PA

Inspection Dates:

August 7, 2022 to August 25, 2022

Inspectors:

C. Bickett, Senior Reactor Analyst

J. DeBoer, Senior Project Engineer

B. Dyke, Operations Engineer

J. Lilliendahl, Senior Emergency Response Coordinator

J. Schoppy, Senior Reactor Inspector

G. Stock, Senior Resident Inspector

Approved By:

Mel Gray, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Susquehanna Steam Electric Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Establish Appropriate Work Order Instructions for Work Activities on a Safety-Related Residual Heat Removal Service Water Valve Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000387/2022013-01 Open/Closed

[H.1] -

Resources 71111.21M The team identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," because Susquehanna personnel did not establish appropriate work order instructions for work activities on the Unit 1 safety-related residual heat removal service water (RHRSW) system.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02)

=

(1) Time sensitive operator action - Align 'E' Emergency Diesel Generator to U2 ESS Bus
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance records, and corrective action history
  • Equipment/environmental controls and qualification
  • Adequacy of design (calculations and modifications)
  • Surveillance testing and test results
  • System and component level performance monitoring
  • Equipment protection from fire, flood, steam, water intrusion, or spray
  • Heat removal, cooling water and ventilation
  • Operator actions
  • Energy source availability (electricity, fuel, air)

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(2) Unit 2 ESS 4.1kV Switchgear 2A201 Bus (Failure to Operate)
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • Maintenance records and corrective action history
  • Adequacy of design (calculations and modifications)
  • Surveillance testing and test results
  • System and component level performance monitoring
  • Control logic
  • Component adequacy for minimum voltage
  • Protection coordination (load in-rush and full load current)
  • Operator actions
  • Energy source availability (electricity, steam, fuel, air)

The team used Appendix B guidance for Circuit Breakers, Cables, Electrical Loads, Motor Control Centers (MCCs), and As-built System.

(3) Unit 1 250VDC Battery 1D650
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Design calculations
  • Surveillance testing and recent test results
  • Energy source availability (electricity)

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electric Loads, and As-Built System.

(4) Unit 1 Residual Heat Removal Service Water (Failure to Provide Suppression Pool Cooling)
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Equipment/environmental controls and qualification
  • Design calculations
  • Surveillance testing and recent test results
  • System and component level performance monitoring
  • Equipment protection from fire, flood, and water intrusion or spray
  • Operator actions
  • Heat removal cooling water and ventilation

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02) (1 Sample)

(1) Unit 1 High Pressure Coolant Injection System (Failure to Operate)
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance records, and corrective action history
  • Surveillance testing and test results
  • System and component level performance monitoring
  • Control logic
  • Operator actions
  • Process medium availability (water, air, electrical signal)
  • Energy source availability (electricity, steam, fuel, air)

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1) DEC 2471627 - RHRSW Cable FF1S0601A Repair
(2) DEC 1974016 - 1X240 Engineered Safeguard System Load Center Transformer Replacement
(3) DEC 2159657 - Add a Hydraulic Booster to 'E' EDG Governor
(4) DEC 2489798 - Increase Set Point of PSV21213A
(5) TDC 2308928 - Bypass Battery Cell #120 on Battery 2D660, 250VDC Battery Bank B

Review of Operating Experience Issues (IP Section 02.06) (2 Samples)

(1) NRC Information Notice 2019-01: Inadequate Evaluation of Temporary Alterations, dated March 12, 2019
(2) NRC Information Notice 2020-02: Flex Diesel Generator Operational Challenges

INSPECTION RESULTS

Failure to Establish Appropriate Work Order Instructions for Work Activities on a Safety-Related Residual Heat Removal Service Water Valve Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000387/2022013-01 Open/Closed

[H.1] -

Resources 71111.21M The team identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," because Susquehanna personnel did not establish appropriate work order instructions for work activities on the Unit 1 safety-related residual heat removal service water (RHRSW) system.

Description:

On April 17, 2020, operators initiated CR 2020-05941 to document that the HV-11210A RHRSW heat exchanger (HX) inlet valve stem appeared to separate from the motor operator. At the time, Unit 1 was in a refueling outage, Mode 5, with irradiated fuel in the vessel, with the A loop of RHRSW in service supporting shutdown cooling (SDC) operation.

Operators attempted to adjust HV-11210A for SDC temperature control but noted no change in system flow and pressure. Operators confirmed actuator motor operation locally, but observed no valve stem travel. The as-left position of the valve was midway open (approximately 45%) with sufficient flow to satisfy SDC requirements for plant conditions.

Based on this position, operators determined that the A residual heat removal (RHR) SDC subsystem remained operable. At the time, the B RHR SDC subsystem was also operable and available. Operators satisfactorily maintained SDC in service on the A loop of RHRSW until placing the B SDC subsystem in service on April 18, 2020, in order to troubleshoot and repair the HV-11210A. The Susquehanna Fix It Now (FIN) team performed troubleshooting under Work Order 2335031 and replaced and properly torqued the actuator coupling bolts on April 19, 2020. Following a successful post-maintenance test (PMT), operators declared the HV-11210A valve operable.

During the design bases inspection, the team reviewed CR 2020-05941 and Susquehannas associated corrective actions and noted that the Management Review Committee (MRC)assigned the CR a significance level 4 which resulted in a broke/fix approach with no causal analysis. Based on subsequent review, the team identified that maintenance removed the HV11210A actuator from the valve under Work Order 2197505 earlier in the April 2020 refueling outage to facilitate inspection of the RHRSW piping inlet flange supplying the A RHR HX. Following the planned maintenance, maintenance personnel completed a leak check PMT on April 7, 2020, and operators completed a successful stroke time test on April 7, 2020, and declared the valve operable. However, the team noted that Work Order 2197505 did not contain adequate guidance to either maintain the coupling intact between the valve and actuator when removing the valve from the RHRSW piping or to retorque the coupling bolts to the proper torque value if reassembly of the coupling joint was required. The team concluded that the maintenance personnels failure to adequately torque the stem to actuator coupling bolts directly contributed to the subsequent malfunction of the valve during SDC operations on April 17, 2020. In response to the teams assessment, the licensee initiated CR 2022-12358 on August 8, 2022, to address the work order instruction deficiencies. The team noted that the assignment of the initial CR (2020-05941) as a significance level 4 in April 2020, with no causal analysis and/or extent-of-condition review, represented a missed opportunity for the licensee to self-identify the underlying performance deficiency and evaluate the potential extent-of-condition in a more timely manner commensurate with the potential safety significance.

In addition, the team reviewed the extent-of-condition as maintenance personnel had performed similar work activities on the Unit 1 B RHRSW HX supply valve (HV-11210B),

Unit 2 A RHRSW HX supply valve (HV-21210A), and Unit 2 B RHRSW HX supply valve (HV-21210B). HV 11210B was removed under Work Order 2366440 in April 2022. HV 21210A was removed under Work Order 2277134 in April 2021. HV 21210B was removed under Work Order 2114861 in April 2019. The three work orders documented that the valve and actuator were not decoupled for the respective valves; thus, the team determined that continued operability of these safety-related valves was not called into question based on the extent-of-condition review. However, the team identified that two of the three work orders also contained less than adequate guidance with respect to the coupling torque. Precaution 4.2 in Work Order 2277134 stated that the valve and actuator were to be removed as a unit (DO NOT remove the operator from the valve). However, there was not adequate guidance in the other two work orders (2366440 & 2114861) to maintain the valve and actuator coupled. In fact, for Work Order 2114861, a pen and ink change was made to the work order on March 19, 2019, prior to the work commencing, to remove HBC and actuator as needed.

However, in that case, the documentation provided in the work order package indicated that that option was not exercised and the actuator was not removed. In addition, those two work orders did not provide guidance for retorqueing the coupling if the actuator was removed.

In reviewing the work history and operating experience associated with these RHRSW valves, the team noted that the licensee had encountered previous issues with actuator coupling bolts becoming loose in 2015. Specifically, on March 23, 2015, the licensee initiated CR 2015-8083 to address loose actuator coupling bolts that caused the Unit 2 A RHRSW HX supply valve (HV-21210A) to fail to close while attempting to shut down the 2A RHRSW pump. The team noted that the licensees short-term corrective actions following the malfunction in March 2015 appeared much more thorough and responsive than their actions following the malfunction in April 2020. In particular, their actions in 2015 included an extent-of condition review, causal analysis, and implementing a recurring task preventive maintenance task to perform coupling torque checks.

Although the valve failure in April 2020 was self-revealing, the licenses initial corrective actions consisted of initiating a CR (level 4) and assigning the FIN team to troubleshoot and repair (a broke/fix approach) without performing an associated causal analysis or extent-of-condition review. Additional NRC follow-up during the 2022 design basis assurance inspection resulted in the identification of the inadequate work order instructions and prompted the extent-of-condition review to assess the continued operability of similar Unit 1 and Unit 2 RHRSW valves. (See extent-of-condition review discussed above.) As such, due to the NRC value-added during the inspection, the team determined that the issue was best classified as NRC-identified vice self-revealing.

Corrective Actions: The licensees immediate corrective actions included initiating CR 2020-05941 and repairing the valve in April 2020. Subsequently, the licensee initiated CR 2022-12358 to revise the work instruction library files associated with valves HV11210A/B and HV21210A/B to clarify that the valve and motor operator are to be removed as a unit and to not disturb the electrical setup or mechanical connections. In addition, the action stated to also consider revising the work instructions to add steps to be taken if the motor operator would need to be removed to ensure that the proper procedures and operating manuals associated with the motor operator and stem coupling are considered.

Corrective Action References: CR 2020-05941 and CR 2022-12358

Performance Assessment:

Performance Deficiency: The licensee did not provide adequate work order instructions related to planned work on the safety-related A RHR HX inlet flange resulting in the subsequent in service malfunction of RHRSW valve HV 11210A. Specifically, Work Order 2197505 did not provide adequate guidance to either maintain the coupling intact between the valve and actuator when removing the valve from the RHRSW piping or to retorque the coupling bolts to the proper torque value if reassembly of the coupling joint was required. The team concluded that the failure to develop and implement adequate work order instructions was reasonably foreseeable and preventable and was a performance deficiency given the licensees internal operating experience in 2015.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the team determined that maintenance work activities involving the HV 11210A RHRSW valve adversely affected the availability, reliability, and capability of the RHRSW system. The team compared this performance deficiency against examples in IMC 0612, Appendix E, Examples of Minor Issues, effective January 1, 2021, and found similarities to example 4.c. Specifically, the HV 11210A valve was returned to service after work activities but because of the inadequate work order instructions, maintenance decoupled the stem and actuator but did not adequately re-torque the bolts during reassembly resulting in a subsequent malfunction of the valve while in service for SDC.

Significance: The inspectors assessed the significance of the finding using IMC 0609, Appendix G, Shutdown Safety SDP. In accordance with IMC 0609, Appendix G, 1, Exhibit 3, the team determined that the finding screened to Green since the deficiency affected the design or qualification of a mitigating SSC that maintained its operability.

Cross-Cutting Aspect: H.1 - Resources: Leaders ensure that personnel, equipment, procedures, and other resources are available and adequate to support nuclear safety.

Contrary to this, Susquehanna personnel did not ensure that work order instructions were adequate to support safety-related work on the RHRSW system.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, states that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 25, 2022, the inspectors presented the design basis assurance inspection (teams) inspection results to Kevin Cimorelli, Site Vice President and other members of the licensee staff.
  • On August 30, 2022, the inspectors presented the results of their review of FLEX generator testing to Dave Ambrose, Engineering General Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

EC-054-1027

Pipe-Flo Model - ESW and RHRSW Systems

EC-088-0505

Unit 1 and Unit 2 Class 1E 250VDC System Voltage Drop

Calculation

EC-088-0506

Class 1E 250VDC Battery Sizing and Battery Charger Sizing

for 1D650, 2D650, and 2D660

EC-088-1005

Battery 1D650 Load Profile

EC-FLEX-0013

Fukushima Flex Generators - RHR Motor Start and Load

Flow Analysis

EC-FLEX-0015

Fukushima Flex Generators - Phase 2 Load Flow Analysis

EC-RISK-1162

Performance Criteria for EDG E Ability to Substitute

EC-SOPC-0618

Relay Setting Calculation for Transformer 1X240 Circuit

Breaker Overcurrent at Bus 1A204 and

Undervoltage/Overvoltage at Load Center 1B240

EC-SOPC-0739

RHR Pump Unit 1 and 2

Corrective Action

Documents

AR-2014-02355

AR-2015-08278

CR-2014-21439

CR-2015-08083

CR-2017-12589

CR-2018-09178

CR-2018-13000

CR-2019-07041

CR-2019-10706

CR-2020-01392

CR-2020-03941

CR-2020-05274

CR-2020-05597

CR-2020-05920

CR-2020-05941

CR-2020-09452

CR-2021-11116

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-2021-12192

CR-2021-14609

CR-2021-14690

CR-2022-04654

CR-2022-05704

CR-2022-05939

CR-2022-11912

CR-2022-12999

Corrective Action

Documents

Resulting from

Inspection

CR-2022-12068

CR-2022-12077

CR-2022-12078

CR-2022-12089

CR-2022-12103

CR-2022-12107

CR-2022-12109

CR-2022-12118

CR-2022-12125

CR-2022-12128

CR-2022-12130

CR-2022-12137

CR-2022-12138

CR-2022-12170

CR-2022-12194

CR-2022-12196

CR-2022-12211

CR-2022-12212

CR-2022-12249

CR-2022-12271

CR-2022-12351

CR-2022-12353

CR-2022-12358

CR-2022-12592

CR-2022-12670

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-2022-12740

CR-2022-12859

CR-2022-12864

CR-2022-12866

CR-2022-12868

CR-2022-12964

CR-2022-12973

CR-2022-12978

CR-2022-12990

CR-2022-13002

CR-2022-13006

CR-2022-13007

Drawings

E-11, Sheet 1

Unit 1 and Common Single Line Meter and Relay Diagram

25VDC and 250VDC

E-11, Sheet 2

Unit 1 Single Line Meter and Relay Diagram 125VDC and

250VDC

E106260 Sheet 1

Unit 1 High Pressure Coolant Injection P&ID

E107150 Sheet 1

Susquehanna SES Unit 1 and 2 Single Line Diagram Station

E107154 Sheet 2

Susquehanna SES Unit 2 Single Line Meter and Relay

Diagram 4.16KV Engineering Safeguards Power System

M-112

Unit 1 RHR Service Water P&ID

Engineering

Changes

DEC 1974016

1X240 Engineered Safeguard System Load Center

Transformer Replacement

DEC 2159657

Add a Hydraulic Booster to the EDG E Governor

DEC 2489798

Design Equivalent Change Package - Increase Set Point of

PSV21213A

TDC 2308928

Temporary Bypass Battery Cell #120 on Battery 2D660

Miscellaneous

DBD004

Design Basis Document for High Pressure Coolant Injection

System

DBD009

Design Basis Document for ESW, RHRSW, and Ultimate

Heat Sink

IOM224 Section

A

Wafer-Sphere Butterfly Valves Installation, Maintenance and

Operating Instructions

05/01/1996

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-AD-327-1

SCRAM Event Summary (Unit 1)

05/23/2022

SE-116-301

RHRSW System Leakage Test

06/22/2022

SM-188-104

Monthly Div I 1D650-250VDC Battery Discharge Test

04/04/2020

SO-116-A02

Quarterly RHRSW Valve Exercising Division I

04/08/2020

SO-116-A03

Quarterly Residual Heat Removal Service Water (RHRSW)

System Flow Verification Division I

06/22/2022

SO-116-A04

Residual Heat Removal Service Water (RHRSW) System

Comprehensive Flow Verification Division I

09/22/2021

SO-116-B03

Quarterly Residual Heat Removal Service Water (RHRSW)

System Flow Verification Division II

04/08/2022

and

06/14/2022

SO-116-B04

Residual Heat Removal Service Water (RHRSW) System

Comprehensive Flow Verification Division II

09/16/2021

SO-152-004

Quarterly HPCI Valve Exercising

06/06/2022

SO-152-006

High Pressure Coolant Injection Comprehensive Flow

Verification

2/16/2020

SUS-ISTPLN-

100.0

SSES Unit 1 Inservice Testing Program

Procedures

DC-FLEX-010

4160 VAC Connection to E DG and ESS Buses

IP-ENG-001

Standard Design Process

MFP-QA-5250

Control Structure PLRT and Reactor Building NLRT

Boundary Breaches and Penetration Seals

N-DAP-QA-0343

Time Critical and Time Sensitive Operator Actions

NDAP-QA-0409

Door, Floor Plug and Hatch Control

NDAP-QA-0423

Station Pump and Valve Test Program

NDAP-QA-0515

Control and Calibration of Plant Measuring and Test

Equipment (M&TE)

NDAP-QA-1218

Temporary Changes

ON-LOOP-101

Unit 1 Loss of All Offsite Power

ON-LOOP-201

Unit 2 Loss of All Offsite Power

OP-024-004

Transfer and Test Mode Operations of Diesel Generator E

OP-116-001

RHR Service Water

OP-149-002

RHR Shutdown Cooling

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-152-001

HPCI System

Work Orders

256448

1413955

1862427

1887276

1906956

1919129

1984180

1992666

2040721

2114861

2130256

2183390

2197505

2197657

2198398

212723

22772

274265

277134

279019

299854

2301244

2312553

2318398

2335031

2336487

2336487

2341550

2360013

2364432

2366440

2377028

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2405665

2441817

2471399

27845

2543385

2544558

2562247

2562501