Forwards Updated Listing of Items Which May Not Be Complete Until After Initial Fuel Loading & Items Which Will Be Completed Prior to & After Initial Criticality.No Unreviewed Safety Questions Involved
ML18081A538
Person / Time
Site: Salem PSEG icon.png
Issue date: 11/09/1979
From: Mittl R
Public Service Enterprise Group
To: Parr O
Office of Nuclear Reactor Regulation
References
NUDOCS 7911150344
Download: ML18081A538 (3)


Text

. :' ~ -0 PS~G
  • Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 Phone 201/430-7000 November 9; 1979 Director of Nuclear Reactor Regulation u.s. Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Mr. Olan D. Parr, Chief Light Water Reactors Branch 3 Division of Project Management Gentlemen:

REVISED REQUEST FOR DEFERMENT INCOMPLETE ITEMS NO. 2 UNIT SALEM NUCLEAR GENERATING STATION DOCKET NO. 50-311 Public Service Electric and Gas Company.hereby transmits an updated listing of items, including preoperational tests, which may not be complete until after initial fuel loading.

This listing updates and supersedes our letter of July 18, 1979 to incorporate completion of testing in the Radiation Monitoring System prior to initial fuel loading~

Safety evaluations are provided which illustrate that the incompleteness of these items at the time of initial fuel loading will have no adverse effect on the health and safety of the general public or station personnel.

The listing identifies those items which will be completed prior to and after initial criticality. We have concluded that these items do not involve an unreviewed safety ques-tion and have no effect on the safe operation and reliabil-ity of the plant.

Should you have questions in this regard, please do not hes-itate to contact us.

Very truly yours, r.t~:r/-

General Manager -

Licensing and Environment Engineering and Construction Attachment HH3 l The Energy People

  • ?911150 3'1 <f A 95-0942

Mr. Olan D. Parr 11/9/79 EAL: jb BCC Vice President - Engineering and Construction Vice President - Production General Manager - Licensing and Environment General Manager - Electric Production Manager Nuclear Operations Manager Salem Station Manager - Salem Projects HH3 2

SALEM NUCLEAR GENERATING STATION NO. 2 UNIT ITEMS TO BE COMPLETED PRIOR TO INITIAL CRITICALITY Description Safety Evaluation

1. Main Steam Safety Valve The valve has been repaired.

24M515 was gagged during Valve testing will require Main Hot Functional Testing. Steam System partial pressure; the remaining portion of system pres-sure will be simulated by mechani-cal assist. Therefore, the valves will not be untested before the system reaches its maximum pres-sure. This procedure, along with the other safety valves in the line, provides adequate overpres-sure protection and will have no detrimental effect on system func-tion or plant safety.

ITEMS TO BE COMPLETED AFTER INITIAL CRITICALITY Description Safety Evaluation

1. Circulating Water System: The operation of the Circulating The operational tests of Water System is not a safety re-of circulators 21B; 22B lated function. Three of the six and 23A will not be circulators have been tested and completed. accepted and are available for Mode I operation. The remaining three circulators will be fully tested and operational prior to exceeding 50% of rated thermal power.

The Generator was run at 1800 RPM

2. SUP 50.20, Initial Syn- during Hot Functional Testing, but chronization of Generator, was not synchronized. Synchroni-has not been performed. zation after Initial Criticality will not affect the safe operation or reliability of the system.

EAL: jb:

11/9/79 HH3 3