ML17354B016

From kanterella
Revision as of 15:06, 22 April 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Fermi U1: CY2018 Master Inspection Plan
ML17354B016
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 12/20/2017
From: Rhex Edwards
NRC/RGN-III
To: Mann K
DTE Electric Company, DTE Energy
References
Download: ML17354B016 (1)


Text

Edwards, Rhex From: Sent: To:

Subject:

Dear Mr. Mann,

Edwards, Rhex Wednesday, December 20, 2017 12:13 PM kyle.man n@dteenergy.co m Fermi Ul: CY2018 Master Inspection Plan In accordance with Inspection Manual Chapter (IMC) 2561, "Decommissioning Power Reactor Inspection Program," the NRC Region Ill staff developed a Master Inspection Plan (MIP) for the Enrico Fermi Atomic Power Plant, Unit 1, for calendar year 2018. The inspection plan is based on your current performance and your planned decommissioning activities for the site in January through December 2018. Below is a list of the periodic inspection procedures we expect to use during our inspections. The procedures used during each inspection will depend on the specific activities being conducted at the site. Additional discretionary inspection procedures may be used if decommissioning activities warrant. We will gladly discuss any questions you may have regarding this MIP. If you have questions, please contact me at (630) 829-9722. If you have questions related to security inspections, please contact the Plant Support Branch Chief at 630-829-9500. Sincerely, Rhex Edwards Inspection Procedure Start Date End Date 37801: Safety Reviews, 11/01/2018 12/01/2018 Design Changes, and Modifications 71801: Performance and 11/02/2018 12/02/2018 Status Review 83750: Occupational 11/03/2018 12/03/2018 Radiation Exposure 84750: Radioactive Waste 11/04/2018 12/04/2018 Treatment, Effluent and Environmental Monitoring 86750: Waste 11/05/2018 12/05/2018 Management and Transportation 1