MONTHYEARML23340A1322023-12-0606 December 2023 NRR E-mail Capture - (External_Sender) Fermi 2 Audit Clarifications - EPID L-2023-LLA-0092 ML24011A2072023-11-17017 November 2023 Approval to Conduct NRC Appendix C Inspection Procedure 93100 at Fermi-2 ML23277A1332023-10-0303 October 2023 NRR E-mail Capture - ECCS Strainer Risk Informed Licensing Amendment - Audit Questions ML23276A0052023-10-0202 October 2023 NRR E-mail Capture - (External_Sender) Fermi EDG Crankcase Trip LAR RAI Response ML23250A2732023-09-0707 September 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request to Revise TS 3.8.1, AC Sources - Operating, Surveillance Requirement 3.8.1.12 ML23244A0022023-08-30030 August 2023 NRR E-mail Capture - Fermi 2 - Acceptance of Relief Request RR-A25 for Extended License Period ML23241B0162023-08-24024 August 2023 Exigent License Amendment Request for Additional Information RAI-12 (EPID L-2023-LLA-0112) (Email) ML23235A1822023-08-23023 August 2023 Exigent LAR Request for Additional Information NRC-23-0055, NRR E-mail Capture - (External Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-00552023-08-16016 August 2023 NRR E-mail Capture - (External_Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-0055 NRC-23-0028, NRR E-mail Capture - (External Sender) Fermi Relief Request RR-A25 (NRC-23-0028)2023-08-0707 August 2023 NRR E-mail Capture - (External_Sender) Fermi Relief Request RR-A25 (NRC-23-0028) ML23199A2472023-07-14014 July 2023 Acceptance Review License Amendment Pertaining to ECCS Strainer Performance Evaluation ML23163A1742023-06-12012 June 2023 NRR E-mail Capture - Fermi 2 - Acceptance of Requested Licensing Action Regarding Amendment to Revise SR 3.8.1.2 in TS 3.8.1, AC Sources - Operating NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi ML23146A0622023-05-25025 May 2023 Acceptance of Requested Licensing Action Regarding Amendment to Correct Non-Conservative TS 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage ML23131A1912023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Fermi 2 LAR (EDG Crankcase Trip) - 6-Month Review ML23115A1452023-04-25025 April 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Changes to TS 3.8.1, AC Sources - Operating ML23076A0222023-03-14014 March 2023 Email SUNSI Action Related to Fermi Unit 1 Safety Hazards Summary Report (ML23066A135) ML23010A0962023-01-10010 January 2023 NRR E-mail Capture - Fermi 2 - Acceptance Review of the Requested Licensing Action Re License Amendment Request to Revise TS 3.8.1 ML22241A0622022-08-29029 August 2022 NRR E-mail Capture - Fermi 2: Acceptance Review of LAR Regarding Adoption of TSTF-582 ML22027A3612022-01-26026 January 2022 U1: CY2022 Inspection Plan, Docket No. 05000016, License No. DPR-9 ML21350A0482021-11-18018 November 2021 NRR E-mail Capture - (External_Sender) Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi Nuclear Power Plant, Unit 2 ML21266A4342021-09-20020 September 2021 Acceptance of DTE Request for Exemption from 10 CFR 72.44(d)(3) for Fermi 2 ML21214A1492021-08-0202 August 2021 License Amendment Request: Request for Additional Information ML21209A0132021-07-27027 July 2021 NRR E-mail Capture - Petition Review Board Initial Assessment of 2.206 Petition Regarding Fermi Unit 2 - Follow-Up to July 12, 2021 Email ML21194A0282021-07-12012 July 2021 NRR E-mail Capture - Petition Review Board Initial Assessment of 2.206 Petition Regarding Fermi Unit 2 - Continuance on Fall 2020 Emails ML21126A0532021-05-0404 May 2021 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Revised Relief Request RR A-39 ML21116A2572021-04-21021 April 2021 NRR E-mail Capture - Fermi 2 - Acceptance Review Licensing Amendment Request to Revise Technical Specifications ML21089A3962021-03-30030 March 2021 NRR E-mail Capture - (External_Sender) Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi Nuclear Power Plant, Unit 2 ML21084A1322021-03-19019 March 2021 NRR E-mail Capture - (External_Sender) Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi Nuclear Power Plant, Unit 2 ML21026A1372021-01-25025 January 2021 NRR E-mail Capture - Acceptance Review: Fermi 2 Revised Relief Request RR-A39 ML20329A3802020-11-23023 November 2020 NRR E-mail Capture - Fermi 2 (COVID-19) Part 73 Exemption Request ML20275A2962020-09-30030 September 2020 NRR E-mail Capture - (External_Sender) Action - Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi 2 Nuclear Power Plant ML20289A1032020-09-29029 September 2020 NRR E-mail Capture - Petition Review Board Initial Assessment of 2.206 Petition Regarding Fermi Unit 2 ML20289A1052020-09-24024 September 2020 NRR E-mail Capture - Status Update on 2.206 Petition Regarding Fermi Unit 2 ML20261H9282020-08-14014 August 2020 NRR E-mail Capture - (External_Sender) Action - Request for Comments on the Proposed Issuance of Amendments to Technical Specifications for Fermi 2 Nuclear Power Plant ML20239A9682020-08-12012 August 2020 NRR E-mail Capture - Fermi 2 LAR: RAI for Revision to Technical Specifications to Change the Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML20195A2762020-07-0909 July 2020 NRR E-mail Capture - Your Request for Extension of Part 26 Exemption Date - Documentation of Our Discussion on July 8, 2020 ML20181A4102020-06-29029 June 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 Licensing Amendment Request to Adopt TSTF-563 ML20239A7962020-06-26026 June 2020 NRR E-mail Capture - Screening Result of 2.206 Petition Regarding Fermi Unit 2 ML20149K4242020-05-19019 May 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 Relief Request RR-A42 ML20073E4222020-03-12012 March 2020 NRR E-mail Capture - Fermi 2: Relief Request VRR-004, Minor Clarifications to Ensure Consistency with the Specific Language in the ASME Code ML20029F0232020-01-29029 January 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 Relief Requests (Proposed Alternatives), VRR-010 and VRR-011 for the Fourth 10-year IST Program ML20017A1782020-01-17017 January 2020 Relief Request #1 for Four RHR Valves (E1150F006A/B/C/D) ML20015A3012020-01-14014 January 2020 E-mail Fermi 1: CY2020 Master Inspection Plan ML20008D5752020-01-0808 January 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 - LAR to Revise Technical Specification for Secondary Containment Surveillance Requirements ML20008D1582020-01-0707 January 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 - LAR to Revise Technical Specification for Secondary Containment Surveillance Requirements ML19346F1192019-12-12012 December 2019 NRR E-mail Capture - Acceptance Review: Fermi 2 - LAR to Revise Technical Specification Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML19346F1432019-12-12012 December 2019 NRR E-mail Capture - Fermi 2 - LAR Revise TS Regarding Steam Dome Pressure - Revised Estimate in the Hours to Complete the Amendment ML19304A2142019-10-30030 October 2019 NRR E-mail Capture - Acceptance Review: Fermi 2 Proposed Alternative VRR-004, Rev. 1, Relief to Confirm Obturator Position at Seat Leakage Testing Frequency 2023-09-07
[Table view] |
Text
From: Arora, Surinder Sent: Thursday, July 9, 2020 11:10 AM To: Margaret M Offerle
Subject:
Your Request for Extension of Part 26 Exemption Date - Documentation of Our Discussion on July 8, 2020
- Peg, I wanted to document our telephone discussions we had with your staff, on July 8, 2020, in connection with your request for extension of the previously approved Part 26 exemption (DTE Request: NRC 20-0045, ADAMS Accession No. 20188A339).
We discussed the following items during this phone call:
- Your request dated July 6, 2020 for extension of the previously approved date did not include information pertaining to the cumulative fatigue effects that may be encountered in extension period. Specifically, you were requested to see item 16 of the Frequently Asked Questions (FAQs) about COVID-19 Part 26 Work Hour Control Exemption, posted on the NRC website. Item 16 of the FAQs relates to the process for obtaining extension of the initial exemption like yours.
- The NRC staff from the Human Factors group explained to your staff why the information related to the cumulative fatigue was necessary for the NRC staff to review your request for extension.
- Your staff understood the needed information and you agreed to supplement your application by providing the required information on COB July 9, 2020.
- Regarding your request to obtain approval by July 10, you were explained that in light of the additional information required from you, this date is not practical. However, if the supplementary information provided by you was sufficient, the NRC staff will try to provide approval by July 14, 2020, which is the date the current approval expires.
List of Attendees:
DTE : Margret Offerle, Derek Corrin, and Alicia Davis NRC: Craig Erlanger, Chris Miller, Gregory Suber, Christian Cowdrey, David Desaulniers, Ed Miller, Robert Kuntz, and Surinder Arora
- Thanks, SURINDER ARORA, PE Project Manager, Fermi 2 US NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION (NRR)
DIVISION OF OPERATING REACTOR LICENSING (DORL)
Plant Licensing Branch III (LPL3)
Phone: 301 415-1421 Email: Surinder.Arora@nrc.gov
Hearing Identifier: NRR_DRMA Email Number: 672 Mail Envelope Properties (MN2PR09MB468322E4D004C9FE83B5041794640)
Subject:
Your Request for Extension of Part 26 Exemption Date - Documentation of Our Discussion on July 8, 2020 Sent Date: 7/9/2020 11:09:46 AM Received Date: 7/9/2020 11:09:00 AM From: Arora, Surinder Created By: Surinder.Arora@nrc.gov Recipients:
"Margaret M Offerle" <margaret.offerle@dteenergy.com>
Tracking Status: None Post Office: MN2PR09MB4683.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2093 7/9/2020 11:09:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: