Initiation Administration
Questions
Answers Results Other: ML092460553, ML092460595, ML092460596, ML100190073, ML100190074, ML100190075, ML100190076, ML100190077, ML101300006, ML101900448, ML101900449, ML101900450, ML101950497, ML101950498, ML103050187, ML110460160, ML110880302, ML11171A060, ML111920326, ML111950133, ML112031112, ML112081701, ML112160736, ML11221A013, ML112450479, ML112460008, ML112460009, ML113340186, ML120050150, ML120250137, ML12313A203, ML12313A204, ML12313A206, NRC-2010-0117, Final Environmental Assessment and Finding of No Significant Impact - Federal Register Notice - Related to the Proposed License Amendment to Increase the Maximum Reactor Power Level | |
MONTHYEARML1001900772004-03-31031 March 2004
[Table View]GE-NE-0000-0024-6517-R0, Safer/Gestr Loss-of-Coolant Accident Analysis for GE14 Fuel. Project stage: Other ML0916101032009-05-27027 May 2009 License Amendment Request (LAR) Pursuant to 10 CFR 50.90: Extended Power Uprate Project stage: Request ML0918906662009-07-0808 July 2009 E-mail from R. Guzman to J. Dosa Acceptance Review Results of NMP2 Extended Power Uprate Application Project stage: Acceptance Review ML0919402542009-07-15015 July 2009 Acceptance Review of License Amendment Request Extended Power Uprate Project stage: Acceptance Review ML0924605502009-08-28028 August 2009 Response to Acceptance Review Comments License Amendment Request for Extended Power Uprate Project stage: Request ML0924605962009-08-28028 August 2009 Attachment 2 - CDI Report 09-26NP, Revision 0, (Non-Proprietary) Stress Assessment of Nine Mile Point, Unit 2 Steam Dryer at CLTP and EPU Conditions, Part 2 of 2 Project stage: Other ML0924605952009-08-28028 August 2009 Attachment 2 - CDI Report 09-26NP, Revision 0, (Non-Proprietary) Stress Assessment of Nine Mile Point, Unit 2 Steam Dryer at CLTP and EPU Conditions, Part 1 of 2 Project stage: Other ML0924605532009-08-28028 August 2009 Attachment 3 - CDI Report 08-08NP, Revision 2, (Non-Proprietary) Acoustic and Low Frequency Hydrodynamic Loads at CLTP Power Level on Nine Mile Point, Unit 2 Steam Dryer to 250 Hz Project stage: Other ML0924502742009-09-0202 September 2009 Acceptance Review Determination of Amendment Request and Supplemental Information Extended Power Uprate Project stage: Acceptance Review ML1019704202009-09-18018 September 2009 E-mail from R. Guzman to J. Dosa Request for Additional Information - Clarification of Applicability of GEH Methods Project stage: RAI ML0928100032009-10-0808 October 2009 Request for Additional Information Nine Mile Point Unit 2 (NMP2) Extended Power Uprate Application License Amendment Request Project stage: RAI ML0930800012009-11-13013 November 2009 Request for Additional Information Extended Power Uprate Project stage: RAI ML0931900032009-11-18018 November 2009 Request for Additional Information the License Amendment Request for Extended Power Uprate Project stage: RAI ML0934300032009-12-10010 December 2009 Request for Withholding Information from Public Disclosure - Proposed License Amendment for Extended Power Uprate Operation, Supplement Dated August 28, 2009 C.D.I Proprietary Documents - Nine Mile Point Nuclear Station Unit No. 2 Project stage: Withholding Request Acceptance ML0932706132009-12-10010 December 2009 Request for Withholding Information from Public Disclosure - Proposed License Amendment for Extended Power Uprate Operation Dated May 27, 2009 C.D.I Proprietary Documents - Nine Mile Point Nuclear Station Unit No. 2 Project stage: Withholding Request Acceptance ML0934106852009-12-10010 December 2009 Request for Withholding Information from Public Disclosure - Proposed License Amendment for Extended Power Uprate Operation Dated May 27, 2009 GEH Proprietary Documents - Nine Mile Point Nuclear Station Unit No. 2 Project stage: Withholding Request Acceptance ML0935110252009-12-23023 December 2009 Request for Additional Information Extended Power Uprate License Amendment Request Project stage: RAI ML1001900722009-12-23023 December 2009 Response to Request for Additional Information, Regarding License Amendment Request for Extended Power Uprate Operation Project stage: Response to RAI ML1001900732009-12-31031 December 2009 C.D.I. Technical Note No. 09-17NP, Limit Curve Analysis with ACM Rev. 4 for Power Ascension at Nine Mile Point, Unit 2, Revision 0 Project stage: Other ML1001900742009-12-31031 December 2009 C.D.I. Report No. 08-08NP, Acoustic and Low Frequency Hydrodynamic Loads at CLTP Power Level on Nine Mile Point Unit 2 Steam Dryer to 250 Hz, Revision 3 Project stage: Other ML1001900752009-12-31031 December 2009 CDI Report No. 09-26NP, Stress Assessment of Nine Mile Point, Unit 2 Steam Dryer at CLTP and EPU Conditions, Cover to Page 62, Revision 1 Project stage: Other ML1001900762009-12-31031 December 2009 CDI Report No. 09-26NP, Stress Assessment of Nine Mile Point, Unit 2 Steam Dryer at CLTP and EPU Conditions, Page 63 Through 130, Revision 1 Project stage: Other ML1019704362010-01-12012 January 2010 E-mail from R. Guzman to T. Darling Request for Additional Information - Extended Power Uprate LAR Standby Liquid Control System Project stage: RAI ML1019704452010-01-27027 January 2010 E-mail from R. Guzman to T. Darling Request for Additional Information Extended Power Uprate - Clarification for Piping NDE Review Project stage: RAI ML1019704532010-02-0101 February 2010 E-mail from R. Guzman to T. Darling Request for Additional Information Extended Power Uprate LAR - Clarification in Fire Protection Review RAI D1, D3 Project stage: RAI ML1005505992010-02-19019 February 2010 Response to Request for Additional Information Regarding License Amendment Request for Extended Power Uprate Operation Project stage: Response to RAI ML1006301122010-03-10010 March 2010 Request for Additional Information - Extended Power Uprate License Amendment Request Mechanical & Civil Engineering Review Project stage: RAI ML1006902762010-03-10010 March 2010 E-mail from R.Guzman to T.Darling Request for Additional Information - Containment & Ventilation Branch - Extended Power Uprate Project stage: RAI ML1006301082010-03-10010 March 2010 Request for Additional Information Steam Dryer Review of the License Amendment Request for Extended Power Uprate Operation Project stage: RAI ML1005508412010-03-16016 March 2010 Letter Transmitting the Draft Environmental Assessment for Nine Mile Point Nuclear Station Extended Power Uprate for Unit No. 2 Project stage: Draft Other ML1006804292010-04-0202 April 2010 Request for Withholding Information from Public Disclosure - Proposed License Amendment for Extended Power Uprate Operation, Supplement Dated December 23, 2009 GEH Proprietary Documents - Nine Mile Point Nuclear Station Unit No. 2 Project stage: Withholding Request Acceptance ML1006804412010-04-0202 April 2010 Request for Withholding Information from Public Disclosure - Proposed License Amendment for Extended Power Uprate Operation, Supplement December 23,2 009 C.D.I Proprietary Documents - Nine Mile Point Nuclear Station Unit No. 2 Project stage: Withholding Request Acceptance ML1006804482010-04-0202 April 2010 Request for Withholding Information from Public Disclosure - Proposed License Amendment for Extended Power Uprate Operation, Supplement February 19, 2010 GEH Proprietary Documents - Nine Mile Point Nuclear Station Unit No. 2 Project stage: Withholding Request Acceptance ML1008500412010-04-0202 April 2010 Summary of Audit Related to the Review of the Extended Power Uprate License Amendment Request of Nine Mile Point Nuclear Station, Unit No. 2 Project stage: Approval ML1008500512010-04-0202 April 2010 Correction Notice to Draft Environmental Assessment for Nine Mile Point Nuclear Station Proposed Extended Power Uprate Amendment for Unit No. 2 Project stage: Draft Other ML1008501072010-04-0202 April 2010 Letter Transmitting Correction to the Notice for the Draft Environmental Assessment and Finding of No Significant Impact for Nine Mile Point Nuclear Station, Unit No. 2 Project stage: Draft Other ML1013000062010-04-14014 April 2010 Follow-Up Questions - EPU Vessels and Integrity Review Project stage: Other ML1011206582010-04-16016 April 2010 Response to Request for Additional Information Re License Amendment Request for Extended Power Uprate Operation Project stage: Response to RAI ML1013803072010-05-0707 May 2010 Response to Request for Additional Information Regarding Steam Dryer Review of the License Amendment Request for Extended Power Uprate Operation Project stage: Response to RAI ML1013200242010-05-10010 May 2010 E-mail from R. Guzman to T. Darling/J. Dosa Request for Additional Information - LOCA Analysis, Extended Power Uprate Project stage: RAI ML1012504242010-05-11011 May 2010 Request for Additional Information Extended Power Uprate License Amendment Request - Reactor System Review Project stage: RAI ML1016101682010-06-0303 June 2010 Response to Request for Additional Information Regarding the License Amendment Request for Extended Power Uprate Operation- Reactor Systems Review Project stage: Response to RAI ML1015908092010-06-0808 June 2010 Request for Additional Information Extended Power Uprate - Probabilistic Risk Assessment Review Project stage: RAI ML1015906522010-06-10010 June 2010 Review of Extended Power Uprate Application and Revised Review Schedule Project stage: Approval ML1019604812010-06-15015 June 2010 E-mail from R.Guzman to T.Darling Request for Additional Information Follow-up RAI - Reactor Systems/Criticality Analysis Project stage: RAI ML1019004492010-06-30030 June 2010 C.D.I. Report No. 10-10NP, Acoustic and Low Frequency Hydrodynamic Loads at CLTP Power Level on Nine Mile Point Unit 2 Steam Dryer to 250 Hz Using ACM Rev. 4.1, Rev. 1 Project stage: Other ML1019004502010-06-30030 June 2010 Calculation SIA 100632.301, Revision 0, May 2010 Nine Mile Point Unit 2 Main Steam Line Strain Gage Data Reduction. Project stage: Other ML1019004482010-06-30030 June 2010 C.D.I. Report No. 10-09NP, ACM Rev. 4.1: Methodology to Predict Full Scale Steam Dryer Loads from In-Plant Measurements, Rev. 1 (Non-Proprietary) Project stage: Other ML1019004472010-06-30030 June 2010 Response to Request for Additional Information Regarding the License Amendment Request for Extended Power Uprate Operation - Steam Dryer and Probabilistic Risk Assessment Project stage: Response to RAI ML1019504952010-07-0909 July 2010 Response to Request for Additional Information Regarding the License Amendment Request for Extended Power Uprate Operation, Non-Proprietary Version of Continuum Dynamics, Inc. Report 10-11 Project stage: Response to RAI 2010-02-01 |
ML110460160 | |
Person / Time | |
---|---|
Site: | Nine Mile Point |
Issue date: | 01/31/2011 |
From: | Teske M E Continuum Dynamics |
To: | Office of Nuclear Reactor Regulation |
References | |
TAC ME1476 CDI 10-09NP, Rev 3 | |
Download: ML110460160 (47) | |
Similar Documents at Nine Mile Point | |
---|---|
Category:Report
MONTHYEARNMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024
[Table view]Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations NMP1L3563, Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208)2023-12-0404 December 2023 Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) NMP1L3545, Supplemental Information Letter to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems .2023-08-0404 August 2023 Supplemental Information Letter to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems . NMP1L3515, Submittal of Emergency Relief Request I5R-11 Concerning the Installation of a Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208)2023-03-27027 March 2023 Submittal of Emergency Relief Request I5R-11 Concerning the Installation of a Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) NMP1L3469, Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits2022-06-30030 June 2022 Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping ML20303A1752020-10-23023 October 2020 Proposed Relief Request from Section XI Repair/Replacement Documentation for Bolting Replacement of Pressure Retaining Bolting ML20190A1482020-07-0808 July 2020 FAQ 20-01 NMP Scram Final Approved ML20100F6822020-04-0909 April 2020 Submittal of Analytical Evaluation of Recirculation Discharge Nozzle-to-Safe End Weld Indication ML19228A0232019-08-15015 August 2019 Proposed Alternative to Utilize Code Case N-879 NMP2L2695, Supplement Information and Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request for One Time Extension to The.2018-12-0707 December 2018 Supplement Information and Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request for One Time Extension to The. NMP1L3229, Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe ...2018-08-20020 August 2018 Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe ... ML18018B2922018-01-18018 January 2018 Appendix a, Justification for Continued Operation, Component Review Summary Sheet ML18018B2912018-01-18018 January 2018 Pipe Crack Task Force Report ML18018A9652018-01-18018 January 2018 Nine Mile Point, Unit 1 - Equipment Qualification Program and Tables I - Equipment Qualification Reports and Table Ii - TMI Action Plan ML18018B0122018-01-18018 January 2018 Semi-Annual Radioactive Effluent Release Report July-December 1999 ML17251A0452017-09-20020 September 2017 - Staff Assessment of Flooding Focused Evaluation (CACs No. MG0087 and MG0088) ML17109A3652017-04-13013 April 2017 Pressure and Temperature Limits Report ML17079A3842017-03-24024 March 2017 Summary of the U.S. Nuclear Regulatory Commission Staff'S Review of the Spring 2016 Steam Generator Tube Inservice Inspections ML17037A6862017-02-0606 February 2017 Table 7.2-1 ML17037A7032017-02-0606 February 2017 Table 7.2-1 (Cont'D) ML17027A0162017-01-27027 January 2017 10 CFR 50.46 Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors RS-16-178, High Frequency Supplement to Seismic Hazard Screening Report2016-11-0202 November 2016 High Frequency Supplement to Seismic Hazard Screening Report ML16231A4522016-08-30030 August 2016 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 2 of Order EA-13-109 (Severe Accident Capable Hardened Events) ML16223A8532016-08-25025 August 2016 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 2 of Order EA-13-109 (Severe Accident Capable Hardened Vents) RS-16-091, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2016-06-14014 June 2016 Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML16160A0942016-06-0808 June 2016 ASP ANALYSIS- REJECT- Nine Mile Point Unit 1 Automatic Reactor Scram Due to Main Steam Isolation Valve Closure (LER 220-2015-004) ML15153A6602015-06-16016 June 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Re ML15028A1492015-02-11011 February 2015 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-13-109, Severe Accident Capable Hardened Vents RS-14-277, Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 12014-09-24024 September 2014 Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 ML15022A6612014-07-31031 July 2014 Stress Re-Evaluation of Nine Mile Point Unit 2 Steam Dryer at 115% CLTP, CDI Report No. 14-08NP, Revision 0, Non-proprietary Version ML14153A4102014-07-24024 July 2014 Staff Assessment of Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation ML14176A9612014-06-24024 June 2014 Submittal of Non-Proprietary BWROG Technical Product, BWROGTP-11-006 - ECCS Containment Walkdown Procedure, Rev 1 (January 2011), as Formally Requested During the Public Meeting Held on April 30, 2014 ML14167A3492014-06-20020 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident (Tac. MF0249 & MF0250) ML15022A6622014-05-31031 May 2014 Acoustic and Low Frequency Hydrodynamic Loads at 115% CLTP Target Power Level on Nine Mile Point Unit 2 Steam Dryer to 250 Hz Using ACM Rev. 4.1R, C.D.I. Report No. 14-09NP, Revision 1, Non-proprietary Version ML15023A0312014-04-30030 April 2014 Computation of Cumulative Usage Factor for the 115% CLTP Power Level at Nine Mile Point Unit 2 with the Inboard RCIC Valve Closed, C.D.I. Technical Note No. 14-04NP, Revision 0, Non-proprietary Version ML14099A1962014-03-31031 March 2014 Constellation Energy Nuclear Group, LLC - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task. ML14064A3242014-02-28028 February 2014 000N2495-R1-NP, Rev. 0, Nine Mile Point Nuclear Station Unit 2 Comparison of Mellla+ Reference Design to Cycle 15 Design Characteristics. ML14071A4782014-02-21021 February 2014 Response to Nrc'S Request for Cashflow Statements Regarding Application for Order Approving Transfer of Operating Authority and Conforming License Amendments ML14351A4272014-01-31031 January 2014 000N2528-SRLR, Revision 1, Supplemental Reload Licensing Report for Nine Mile Point 2 Reload 14 Cycle 15 Extended Power Uprate (3988 Mwt) / MELLLA (99-105% Flow). ML14064A3222014-01-31031 January 2014 00N0123-SRLR, Rev. 2, Supplemental Reload Licensing Report for Nine Mile Point 2 (NMP2) Reload 14 Cycle 15 Extended Power Uprate (Epu)/Maximum Extended Load Line Limit Plus (Mellla+). ML14024A4422014-01-0707 January 2014 Submittal of Report in Accordance with 10 CFR 26.719(c)(1) Regarding Unsatisfactory Blind Performance Sample Testing ML14064A3232013-12-31031 December 2013 000N0123-FBIR-NP, Rev. 0, Fuel Bundle Information Report for Nine Mile Point 2 Reload 14 Cycle 15. ML13225A5842013-12-19019 December 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML13338A6632013-12-11011 December 2013 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Nine Mile Point, Unit 1, TAC No.: MF1129 ML13338A6642013-12-11011 December 2013 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Nine Mile Point, Unit 2, TAC No.: MF1130 ML13311A0542013-11-0404 November 2013 Pressure and Temperature Limits Report (PTLR) PTLR-2, Revision 0 (Draft B) ML13316B1102013-11-0101 November 2013 Attachment 9 - Global Nuclear Fuel Report GNF-0000-0156-7490-RO-NP, Gnf Additional Information Regarding the Requested Change to the Technical Specification SLMCPR, Dated August 26, 2013 (Non-proprietary) ML13311A0552013-09-30030 September 2013 Fluence Extrapolation in Support of NMP2 P-T Cure Update, MPM-913991, September 30, 2013, Attachment 3 ML13197A2222013-07-12012 July 2013 Supplemental Response to 10 CFR 50.54(f) Request for Information, Recommendation 2.3, Seismic 2024-07-24 Category:Technical MONTHYEARNMP1L3545, Supplemental Information Letter to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems .2023-08-0404 August 2023
[Table view]Supplemental Information Letter to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems . NMP1L3469, Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits2022-06-30030 June 2022 Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping ML20100F6822020-04-0909 April 2020 Submittal of Analytical Evaluation of Recirculation Discharge Nozzle-to-Safe End Weld Indication ML19228A0232019-08-15015 August 2019 Proposed Alternative to Utilize Code Case N-879 NMP2L2695, Supplement Information and Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request for One Time Extension to The.2018-12-0707 December 2018 Supplement Information and Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request for One Time Extension to The. NMP1L3229, Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe ...2018-08-20020 August 2018 Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe ... ML18018B0122018-01-18018 January 2018 Semi-Annual Radioactive Effluent Release Report July-December 1999 ML18018A9652018-01-18018 January 2018 Nine Mile Point, Unit 1 - Equipment Qualification Program and Tables I - Equipment Qualification Reports and Table Ii - TMI Action Plan ML17109A3652017-04-13013 April 2017 Pressure and Temperature Limits Report ML17037A7032017-02-0606 February 2017 Table 7.2-1 (Cont'D) ML17037A6862017-02-0606 February 2017 Table 7.2-1 RS-14-277, Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 12014-09-24024 September 2014 Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 ML15022A6612014-07-31031 July 2014 Stress Re-Evaluation of Nine Mile Point Unit 2 Steam Dryer at 115% CLTP, CDI Report No. 14-08NP, Revision 0, Non-proprietary Version ML14176A9612014-06-24024 June 2014 Submittal of Non-Proprietary BWROG Technical Product, BWROGTP-11-006 - ECCS Containment Walkdown Procedure, Rev 1 (January 2011), as Formally Requested During the Public Meeting Held on April 30, 2014 ML15022A6622014-05-31031 May 2014 Acoustic and Low Frequency Hydrodynamic Loads at 115% CLTP Target Power Level on Nine Mile Point Unit 2 Steam Dryer to 250 Hz Using ACM Rev. 4.1R, C.D.I. Report No. 14-09NP, Revision 1, Non-proprietary Version ML15023A0312014-04-30030 April 2014 Computation of Cumulative Usage Factor for the 115% CLTP Power Level at Nine Mile Point Unit 2 with the Inboard RCIC Valve Closed, C.D.I. Technical Note No. 14-04NP, Revision 0, Non-proprietary Version ML14064A3242014-02-28028 February 2014 000N2495-R1-NP, Rev. 0, Nine Mile Point Nuclear Station Unit 2 Comparison of Mellla+ Reference Design to Cycle 15 Design Characteristics. ML14071A4782014-02-21021 February 2014 Response to Nrc'S Request for Cashflow Statements Regarding Application for Order Approving Transfer of Operating Authority and Conforming License Amendments ML14064A3222014-01-31031 January 2014 00N0123-SRLR, Rev. 2, Supplemental Reload Licensing Report for Nine Mile Point 2 (NMP2) Reload 14 Cycle 15 Extended Power Uprate (Epu)/Maximum Extended Load Line Limit Plus (Mellla+). ML14351A4272014-01-31031 January 2014 000N2528-SRLR, Revision 1, Supplemental Reload Licensing Report for Nine Mile Point 2 Reload 14 Cycle 15 Extended Power Uprate (3988 Mwt) / MELLLA (99-105% Flow). ML14064A3232013-12-31031 December 2013 000N0123-FBIR-NP, Rev. 0, Fuel Bundle Information Report for Nine Mile Point 2 Reload 14 Cycle 15. ML13225A5842013-12-19019 December 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML13338A6632013-12-11011 December 2013 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Nine Mile Point, Unit 1, TAC No.: MF1129 ML13338A6642013-12-11011 December 2013 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Nine Mile Point, Unit 2, TAC No.: MF1130 ML13311A0542013-11-0404 November 2013 Pressure and Temperature Limits Report (PTLR) PTLR-2, Revision 0 (Draft B) ML13316B1102013-11-0101 November 2013 Attachment 9 - Global Nuclear Fuel Report GNF-0000-0156-7490-RO-NP, Gnf Additional Information Regarding the Requested Change to the Technical Specification SLMCPR, Dated August 26, 2013 (Non-proprietary) ML13311A0552013-09-30030 September 2013 Fluence Extrapolation in Support of NMP2 P-T Cure Update, MPM-913991, September 30, 2013, Attachment 3 ML13197A2222013-07-12012 July 2013 Supplemental Response to 10 CFR 50.54(f) Request for Information, Recommendation 2.3, Seismic ML13078A3232013-02-28028 February 2013 XGEN-2012-25-NP, Revision 1, Westinghouse Engineering Report, Technical Basis for the Inspection Frequency of the Modified Alloy 718 Jet Pump Beam, Attachment 2 ML13066A1692013-02-28028 February 2013 Units I and 2, Overall Integrated Plan for Reliable Hardened Vents ML12313A2032012-10-26026 October 2012 Attachment 1, NMP2 Extended Power Uprate, Power Ascension Test Report ML12313A2042012-10-26026 October 2012 Attachment 2, Final Steam Dryer Stress Report, Continuum Dynamics, Incorporated Report No. 12-18NP, Attachment 3, Affidavit from CDI ML12277A0902012-10-12012 October 2012 Technical Letter Report on Aging Management Program Audits at Ginna and Nine Mile Point 1 ML12284A1842012-09-30030 September 2012 Attachment 3, Final EPU Steam Dryer Load Definition CDI Report No. 12-20NP, Acoustic and Low Frequency Hydrodynamic Loads at 115% CLTP Target Power Level on Nine Mile Point, Unit 2 Steam Dryer to 250 Hz Using ACM Rev. 4.1 ML12284A1852012-06-30030 June 2012 Attachment 4, Steam Dryer Limit Curves CDI Technical Note No. 12-13NP, Limit Curves with ACM Rev. 4.1 for the 100% Power Level Basis at Nine Mile Point, Unit 2, Revision 1 ML12170A8692012-06-30030 June 2012 Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition ML11221A0132011-08-0505 August 2011 Attachment 3, Continuum Dynamics, Inc Technical Note No. 11-17NP, Limit Curve Analysis with ACM Rev. 4.1 for Power Ascension at Nine Mile Point Unit 2, Revision 1. (Non-Proprietary) ML11208B7732011-07-0808 July 2011 Report No. 1100539.401, Rev. 1, Nine Mile Point Unit 1, Steam Dryer Support Bracket Flaw Evaluation. ML11188A1952011-06-28028 June 2011 Calculation S0VESSELM035 (SIA File No. 1100566.301), Reactor Pressure Vessel Head Weld Flaw Evaluation, Rev. 00.00 ML11171A0602011-05-31031 May 2011 Attachment 3, CDI Report No. 11-04NP, Stress Evaluation of Nine Mile Point Unit 2 Steam Dryer Using ACM Rev. 4.1 Acoustic Loads, Revision 0. (Non-Proprietary), Attachment 4, Affidavit from Continuum Dynamics, Inc ML1108803022011-03-31031 March 2011 NEDO-33636, Fuel Storage Criticality Safety Analysis of New Fuel Storage Racks - GE14, Attachment 3, (Non-Proprietary) ML1104601602011-01-31031 January 2011 Attachment 1, CDI Report No. 10-09NP, ACM Rev. 4.1: Methodology to Predict Full Scale Steam Dryer Loads from In-Plant Measurements, Revision 3 ML12135A6232011-01-14014 January 2011 Off-Site Dose Calculation Manual (Odcm), Revision 32 ML1035003652010-12-13013 December 2010 Holtec Report No. HI-2012621 (Non-Proprietary), Criticality Safety Evaluation for the Nine Mile Point 2 Rack Installation Project ML1021702952010-07-30030 July 2010 Attachment 5, Continuum Dynamics, Inc., CDI Report No. 10-12NP, Design and Stress Evaluation of Nine Mile Point Unit 2 Steam Dryer Modifications for EPU Operation ML1021701862010-07-28028 July 2010 Attachment 4, Structural Integrity Associates, Inc., Flaw Evaluation of Indications in the Nine Mile Point Unit 2 Steam Dryer Vertical Support Plates Considering Extended Power Uprate Flow Induced Vibration Loading ML1019004492010-06-30030 June 2010 C.D.I. Report No. 10-10NP, Acoustic and Low Frequency Hydrodynamic Loads at CLTP Power Level on Nine Mile Point Unit 2 Steam Dryer to 250 Hz Using ACM Rev. 4.1, Rev. 1 ML1021701852010-06-30030 June 2010 Attachment 3, Global Nuclear Fuel - Americas, LLC, MCNP01A, Low Enriched UO2 Pin Lattice in Water Critical Benchmark Evaluations Using ENDF/B-V Nuclear Cross-Section Data, Revision 1 ML1019004482010-06-30030 June 2010 C.D.I. Report No. 10-09NP, ACM Rev. 4.1: Methodology to Predict Full Scale Steam Dryer Loads from In-Plant Measurements, Rev. 1 (Non-Proprietary) 2023-08-04 |