IR 05000387/2024001
ML24134A093 | |
Person / Time | |
---|---|
Site: | Susquehanna |
Issue date: | 05/13/2024 |
From: | Jon Greives NRC/RGN-I/DORS |
To: | Berryman B Susquehanna |
References | |
IR 2024001 | |
Download: ML24134A093 (1) | |
Text
May 13, 2024
SUBJECT:
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -
INTEGRATED INSPECTION REPORT 05000387/2024001 AND 05000388/2024001
Dear Brad Berryman:
On March 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2. On April 29, 2024, the NRC inspectors discussed the results of this inspection with Edward Casulli, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Jonathan E. Greives, Chief Projects Branch 4 Division of Operating Reactor Safety
Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000387 and 05000388
License Numbers: NPF-14 and NPF-22
Report Numbers: 05000387/2024001 and 05000388/2024001
Enterprise Identifier: I-2024-001- 0053
Licensee: Susquehanna Nuclear, LLC
Facility: Susquehanna Steam Electric Station, Units 1 and 2
Location: 769 Salem Blvd., Berwick PA
Inspection Dates: January 1, 2024 to March 31, 2024
Inspectors: J. England, Senior Resident Inspector E. Brady, Resident Inspector H. Anagnostopoulos, Senior Health Physicist A. Kostick, Health Physicist
Approved By: Jonathan E. Greives, Chief Projects Branch 4 Division of Operating Reactor Safety
Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Susquehanna Steam Electric Station,
Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period at rated thermal power and was at or near full rated thermal power with the following exceptions. On January 19, 2024, the unit was down powered to percent for a rod pattern adjustment and returned to rated thermal power. On February 2, 2024, the unit was down powered to approximately 81 percent for a rod pattern adjustment and channel distortion testing and returned to rated thermal power. On February 9, 2024, the unit was down powered to approximately 83 percent for a rod pattern adjustment and returned to rated thermal power. On February 23, 2024, the unit was down powered to approximately 92 percent for a rod pattern adjustment and returned to rated thermal power. On February 24, 2024, the unit commenced coast down and shut down for the refueling outage on March 25, 2024, and remained shut down for the remainder of the inspection period.
Unit 2 began the inspection period at rated thermal power and was at or near full rated thermal power with the following exception. On March 22, 2024, the unit was down powered to approximately 59 percent for a rod sequence exchange. The unit was returned to rated thermal power on March 23, 2024, and remained at or near rated thermal power for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identific ation and Resolution, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown (IP Section 03.01) (3 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1 residual heat removal on January 4, 2024
- (2) Unit 2 'A' core spray during 'B' core spray surveillance testing on January 11, 2024
- (3) Unit 1 standby gas treatment during 'C' essential service supply bus work and fuel moves (Yellow risk) on March 31, 2024
71111.05 - Fire Protection
Fire Area Walkdown and Inspection (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Unit Common control structure, 806-foot elevation, standby gas treatment room, fire zone (FZ) 0-30A, on January 3, 2024
- (2) Unit 1 reactor building, 749-foot elevation, FZ 1-5A-N, 1-5A-S, and 1-5A-W, on January 8, 2024
- (3) Units 1 and 2 reactor building, 818-foot elevation, refueling bay, FZ 0-8A, on January 24, 2024
- (4) Unit 2 reactor building, 645-foot elevation, high-pressure coolant injection pump room, FZ 2-1C, on February 21, 2024
- (5) Unit 1 turbine building, 656, 676, and 699-foot elevations, condenser gallery, mezzanine, pad 1 and 2, FZ 1-31D, 1-32D, and 1-33C on March 27, 2024
Fire Brigade Drill Performance (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated fire brigade performance during an unannounced fire drill on February 28, 2024.
71111.07A - Heat Exchanger/Sink Performance
Annual Review (IP Section 03.01) (1 Sample)
The inspectors evaluated readiness and performance of:
- (1) Unit 1 'A' residual heat removal heat exchanger
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during shutdown and cooldown for the Unit 1 planned refueling outage on March 24 and 25, 2024.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed Unit 1 simulator and classroom training for plant shutdown and cooldown on March 20, 2024.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (1 Sample)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:
- (1) Unit Common 'E' emergency diesel generator on January 22, 2024
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management (IP Section 03.01) (4 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Unit 1 division 1 planned work on core spray system on January 9, 2024
- (2) Unit 2 division 1 planned work on residual heat removal heat exchanger bypass valve during the week of January 29, 2024
- (3) Unit 1 elevated risk during reactor vessel disassembly during the week of March 25, 2024
- (4) Unit 1 bus outage on 1A203 on March 30 and 31, 2024
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Unit 1 high-pressure coolant injection with water in lube oil system on January 11, 2024
- (2) Unit 2 'B' core spray pump due to breaker instantaneous overcurrent flag on January 12, 2024
- (3) Unit Common loss of 1D240 due to failure of uninterruptable power supply battery bank on March 28, 2024
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)
(1) (Partial)
The inspectors evaluated Unit 1 refueling outage U123RIO activities from March 25 to 31, 2024. The inspectors completed sections a., b.1, b.2, c.3, c.4, c.6, c.7, and c.8.
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (IP Section 03.01) (2 Samples)
- (1) Unit Common 'C' emergency diesel generator planned maintenance and unplanned fuel line replacement on January 25, 2024
- (2) Unit Common emergency service water pipe replacement on February 15, 2024
Surveillance Testing (IP Section 03.01) (3 Samples)
- (1) Unit 1 SO-150-016, Reactor Core Isolation Cooling Functional Test at Remote Shutdown Panel (1C201A), on February 20, 2024
- (2) Unit 1 SI-180- 305, Quarterly Calibration of Reactor Vessel Water Level Channels LIS-B21-1N024 A, B, C, D, on February 27, 2024
- (3) Unit 1 SO-124-117, Division I Diesel Generator Loss-of-Coolant Accident Loss of Offsite Power Test (Infrequently Performed Test or Evolution), on March 27 and 28, 2024
Inservice Testing (IP Section 03.01) (1 Sample)
- (1) Unit 2 SO-250-002, Quarterly Reactor Core Isolation Cooling Flow Verification, on January 25, 2024
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)
- (1) Unit 1 SE-159-023, Local Leak-Rate Test of Main Steam Line Isolation Valves Penetration Number X-7C, on March 25, 2024
71114.06 - Drill Evaluation
Required Emergency Preparedness Drill (1 Sample)
- (1) The inspectors evaluated the conduct of an emergency preparedness drill including a dropped fuel rod and a leak in the spent fuel pool on February 21,
RADIATION SAFETY
71124.03 - In-Plant Airborne Radioactivity Control and Mitigation
Permanent Ventilation Systems (IP Section 03.01) (1 Sample)
The inspectors evaluated the configuration of the following permanently installed ventilation systems:
- (1) Unit 1 reactor building, zone 3, high-efficiency particulate air and charcoal filter units 1F216A, 1F217A, and 1F218A
Temporary Ventilation Systems (IP Section 03.02) (1 Sample)
The inspectors evaluated the configuration of the following temporary ventilation systems:
- (1) High-efficiency particulate air ventilation unit servicing the down-draft step off pad system on the 818-foot elevation of the refueling floor
Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)
- (1) The inspectors evaluated the licensees use of respiratory protection devices.
Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)
- (1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.
71124.04 - Occupational Dose Assessment
Source Term Characterization (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.
External Dosimetry (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated how the licensee processes, stores, and uses external dosimetry.
Internal Dosimetry (IP Section 03.03) (2 Samples)
The inspectors evaluated the following internal dose assessments:
- (1) Internal dose calculation for employee Kxxxxx6 for an event on April 15, 2023
- (2) Internal dose calculation for employee Jxxxxxxxxxx2 for an event on April 15, 2023
Special Dosimetric Situations (IP Section 03.04) (2 Samples)
The inspectors evaluated the following special dosimetric situations:
- (1) Licensee procedures for limiting exposures for declared pregnant workers, including a review of completed declarations
- (2) Shallow dose equivalent evaluation for a personnel contamination event on March 31,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours (IP Section 02.01)===
- (1) Unit 1 January 1, 2023 through December 31, 2023
- (2) Unit 2 January 1, 2023 through December 31, 2023
IE03: Unplanned Power Changes per 7000 Critical Hours (IP Section 02.02) (2 Samples)
- (1) Unit 1 January 1, 2023 through December 31, 2023
- (2) Unit 2 January 1, 2023 through December 31, 2023
IE04: Unplanned Scrams with Complications (IP Section 02.03) (2 Samples)
- (1) Unit 1 January 1, 2023 through December 31, 2023
- (2) Unit 2 January 1, 2023 through December 31, 2023
BI01: Reactor Coolant System Specific Activity (IP Section 02.10) (2 Samples)
- (1) Unit 1 January 1, 2023 through December 31, 2023
- (2) Unit 2 January 1, 2023 through December 31, 2023
BI02: Reactor Coolant System Leak Rate (IP Section 02.11) (2 Samples)
- (1) Unit 1 January 1, 2023 through December 31, 2023
- (2) Unit 2 January 1, 2023 through December 31,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On February 7, 2024, the inspectors presented the in-plant airborne radioactivity control and mitigation inspection results to Derek Jones, Plant Manager, and other members of the licensee staff.
- On February 7, 2024, the inspectors presented the occupational dose assessment inspection results to Derek Jones, Plant Manager, and other members of the licensee staff.
- On April 29, 2024, the inspectors presented the integrated inspection results to Edward Casulli, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
Plant Corrective Action AR-2024-02277
Status Documents CR-2024- 01430
Resulting from CR-2024- 02110
Inspection CR-2024- 03947
CR-2024- 03949
CR-2024- 03951
CR-2024- 03952
CR-2024- 03953
CR-2024- 04823
CR-2024- 04824
CR-2024-06207
71111.04 Corrective Action CR-2024-05081
Documents CR-2024- 05082
Resulting from
Inspection
Drawings E106256 Susquehanna SES Unit 1 P&ID Residual Heat Removal Revision 72
E106680 P&ID HVAC Control Diagram Reactor Building Standby Revision 35
Gas Treatment System, Sheet 3
M-2152 Unit 2 Core Spray P&ID Revision 31
Procedures CL-070-0012 Standby Gas Treatment System Mechanical Revision 11
SO-251-001A Monthly Core Spray A Loop Discharge Line Filled and Revision 2
Valve Alignment Verification
71111.05 Corrective Action CR-2024-03071
Documents
Corrective Action CR-2024-00490
Documents CR-2024- 01447
Resulting from CR-2024- 02789
Inspection
71111.05 Fire Plans FP-1-CS-806-A Control Structure - El. 806 Revision 0
FP-1-RB-749 Susquehanna SES Prefire Plan Unit 1 749 Revision 0
FP-1-RB-818 Susquehanna Prefire Plan Revision 0
FP-1-TB-656-13 Condenser Pad 1 (FZ 1-31D) Revision 0
FP-1-TB-656-14 Condenser Pad 2 (FZ 1-31D) Revision 0
FP-1-TB-676-12 Condenser Gallery (FZ 1-32D) Revision 0
FP-1-TB-699-8 Condenser Mezzanine (FZ 1-33C) Revision 0
FP-2-RB-818 Susquehanna Prefire Plan Revision 0
Procedures NDAP-QA-0409 Door Floor, Plug, and Hatch Control Revision 24
NDAP-QA-0440 Control of Transient/Combustible/Hazardous Material Revision 28
71111.07A Corrective Action CR-2024-04915
Documents
Resulting from
Inspection
Procedures M-1453 Nuclear Engineer Specification for Heat Revision 9
Exchanger Tube Plugging
MT-116-002 RHR Heat Exchanger Cleaning, Inspection, and Repair Revision 17
Work Orders 2576462
71111.11Q Procedures GO-100-004 Plant Shutdown to Minimum Power Revision 91
GO-100-005 Plant Shutdown to Hot/Cold Shutdown Revision 75
OP-103-001 13.8 KV Electrical System Revision 38
SI-178-215A Functional Test and Signal to Noise Ratio Test of Source Revision 13
Range Monitor (SRM) Channel 1A (SRM-C51-1K600A)
SO-156-009 Reactor Mode Switch in Shutdown Control Rod Revision 5
Withdrawal Block Channel Functional Test
71111.12 Corrective Action CR-2024-01248
Documents CR-2024- 01353
CR-2024-03014
71111.13 Corrective Action CR-2024-04720
Documents CR-2024- 04791
CR-2024-05203
71111.13 Procedures NDAP-QA-0340 Protected Equipment Program Revision 43
ON-YPNL-101 Loss of Instrument Bus Revision 14
Tagout 03-001 Outage Offsite Power - U123RIO
Tagout 04-001 1A203 - ESS Bus 1C OOS - U123RIO
Tagout 16-001 RHRSW 1B Pump - U123RIO
Tagout 24-001 'D' Emergency DG - U123RIO
Tagout 24-001 'B' Emergency DG - U123RIO
71111.15 Corrective Action CR-2023-15041
Documents CR-2024- 00849
CR-2024-00919
Corrective Action CR-2024-01752
Documents CR-2024- 04123
Resulting from
Inspection
Drawings E-156 Susquehanna SES Unit 2 Schematic Diagram Revision 19
Core Spray Pump 2B
Miscellaneous HPCI HV-155-F001 Adverse Condition Monitoring and Contingency Plan Revision 6
Unit 1 (Steam Admission Valve) Seat Leakage
Work Orders 2261092
71111.20 Corrective Action CR-2024-04826
Documents CR-2024- 04827
Resulting from CR-2024- 04829
Inspection
Miscellaneous Shutdown Safety Rick Management Plan Unit 1 23rd Revision 0
Refueling and Inspection Outage
Procedures IC-180-005 Installation and Removal of Temporary Unit 1 RPV Revision 10
Shutdown Level Instrument
71111.24 Corrective Action CR-2024-04694
Documents CR-2024- 04695
Resulting from
Inspection
71111.24 Procedures MT-024-024 Diesel Engine Analysis and Load Balancing Revision 23
SE-159-023 LLRT of Main Steam Line Isolation Valves Penetration Revision 24
Number X-7C
SI-180-305 Quarterly Calibration of Reactor Vessel Water Level Revision 37
Channels LIS-B21-1N024 A, B, C, D
SO-024-001C Monthly Diesel Generator 'C' Operability Test Revision 29
SO-124-117 Division I Diesel Generator LOCA LOOP Test Revision 11
(Infrequently Performed Test or Evolution)
SO-150-016 RCIC Functional Test at Remote Shutdown Panel Revision 2
(1C201A)
SO-250-002 Quarterly RCIC Flow Verification Revision 61
Work Orders 2511404
2575640-0
2669143
RTSV 2682036
71114.06 Procedures EP-104-1003 Drill and Exercise Evaluation Revision 2
71151 Corrective Action DI-2023-00514
Documents DI-2023- 02217
DI-2023- 03680
DI-2023- 04608
DI-2023- 06217
DI-2023- 08562
DI-2023-10392
DI-2023-11422
DI-2023-11503
DI-2023-12847
DI-2023-16148
DI-2023-17495
DI-2023-18867
DPA-01-DI-2023-00427
DPA-02-DI-2023-00427
DPA-03-DI-2023-00427
DPA-04-DI-2023-00427
DPA-05-DI-2023-00427
DPA-06-DI-2023-00427
DPA-07-DI-2023-00427
DPA-08-DI-2023-00427
DPA-09-DI-2023-00427
DPA-10- DI-2023-00427
DPA-11-DI-2023-00427
DPA-12-DI-2023-00427
13