Category:Letter
MONTHYEARPLA-8145, Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-81452024-10-21021 October 2024 Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-8145 ML24291A1562024-10-16016 October 2024 Missed Annual Inventory Required by 40 CFR 266, Subpart in PLE 0026645 PLA-8148, Registration for the Use of Spent Fuel Storage Casks 311, 308, and 3102024-10-15015 October 2024 Registration for the Use of Spent Fuel Storage Casks 311, 308, and 310 PLA-8141, Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-81412024-09-18018 September 2024 Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-8141 PLA-8142, Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-81422024-09-18018 September 2024 Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-8142 ML24260A2312024-09-17017 September 2024 Senior Reactor and Reactor Operator Initial License Examinations 05000387/LER-2024-002, B Diesel Generator Inoperable Due to Failed Excitation System Linear Reactor2024-09-16016 September 2024 B Diesel Generator Inoperable Due to Failed Excitation System Linear Reactor ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24233A2192024-09-0303 September 2024 – Authorized Alternative to Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code IR 05000387/20240052024-08-29029 August 2024 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2024005 and 05000388/2024005) 05000387/LER-2023-004-01, Manual Reactor Scram Due to Degraded Main Condenser Vacuum2024-08-26026 August 2024 Manual Reactor Scram Due to Degraded Main Condenser Vacuum 05000387/LER-2024-001-01, Main Steam Isolation Valve Leakage Due to Valve Body Seat Wear2024-08-21021 August 2024 Main Steam Isolation Valve Leakage Due to Valve Body Seat Wear IR 05000387/20240022024-08-12012 August 2024 Integrated Inspection Report 05000387/2024002 and 05000388/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification PLA-8117, 23rd Refueling Outage Owners Activity Report (PLA-8117)2024-07-23023 July 2024 23rd Refueling Outage Owners Activity Report (PLA-8117) ML24197A0982024-07-15015 July 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000387/2024010 and 05000388/2024010 ML24127A2262024-05-29029 May 2024 Issuance of Amendment Nos. 288 and 272 Adoption of TSTF-563 PLA-8126, Response to Request for Confirmation of Information Regarding Relief Request 1RR062024-05-29029 May 2024 Response to Request for Confirmation of Information Regarding Relief Request 1RR06 PLA-8122, Annual Radiological Environmental Operating Report (PLA-8122)2024-05-28028 May 2024 Annual Radiological Environmental Operating Report (PLA-8122) PLA-8123, Main Steam Isolation Valve Leakage2024-05-23023 May 2024 Main Steam Isolation Valve Leakage PLA-8115, Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115)2024-05-23023 May 2024 Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115) IR 05000387/20240012024-05-13013 May 2024 Integrated Inspection Report 05000387/2024001 and 05000388/2024001 IR 05000387/20244042024-05-0707 May 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000387/2024404 and 05000388/2024404 ML24082A1372024-04-22022 April 2024 Issuance of Amendment Nos. 287 and 271 Adoption of TSTF-568, Revision 2 and Associated Technical Specification Changes PLA-8094, Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-80942024-04-22022 April 2024 Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-8094 PLA-8095, 2023 Annual Radiological Environmental Operating Report (PLA-8095)2024-04-22022 April 2024 2023 Annual Radiological Environmental Operating Report (PLA-8095) PLA-8101, Re 2023 Annual Report of Radiation Exposure2024-04-22022 April 2024 Re 2023 Annual Report of Radiation Exposure PLA-8102, Annual Environmental Operating Report (Nonradiological) PLA-81022024-04-11011 April 2024 Annual Environmental Operating Report (Nonradiological) PLA-8102 PLA-8113, Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113)2024-04-11011 April 2024 Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113) PLA-8112, Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-81122024-04-0909 April 2024 Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-8112 PLA-8110, Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110)2024-04-0404 April 2024 Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110) PLA-8100, Property Insurance Program (PLA-8100)2024-04-0101 April 2024 Property Insurance Program (PLA-8100) ML24092A4022024-04-0101 April 2024 Annual Financial Report (PLA-8098) PLA-8109, Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109)2024-03-21021 March 2024 Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109) ML24067A2512024-03-19019 March 2024 Authorized Alternative to Requirements of the ASME Code PLA-8107, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance2024-03-19019 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance ML24044A2532024-03-14014 March 2024 Associated Independent Spent Fuel Storage Installation – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0077 (Security Notifications, Reports, and Recordkeeping & Suspicious Activity Reporting)) IR 05000387/20240112024-02-29029 February 2024 Commercial Grade Dedication Inspection Report 05000387/2024011 and 05000388/2024011 IR 05000387/20230062024-02-28028 February 2024 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2023006 and 05000388/2023006) ML24039A1882024-02-27027 February 2024 Issuance of Amendment Nos. 286 and 270 Changes to Technical Specifications for Control Rods ML24037A3072024-02-22022 February 2024 Summary of Regulatory Audit in Support of Relief Request 5RR-02 PLA-8099, Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099)2024-02-13013 February 2024 Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099) IR 05000387/20230042024-02-0707 February 2024 Integrated Inspection Report 05000387/2023004 and 05000388/2023004 PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) IR 05000387/20230102023-12-11011 December 2023 Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 PLA-8088, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088)2023-12-0505 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088) PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 2024-09-06
[Table view] Category:Inspection Plan
MONTHYEARIR 05000387/20240052024-08-29029 August 2024 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2024005 and 05000388/2024005) IR 05000387/20244042024-05-0707 May 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000387/2024404 and 05000388/2024404 IR 05000387/20230062024-02-28028 February 2024 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2023006 and 05000388/2023006) ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information IR 05000387/20230052023-08-31031 August 2023 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2023005 and 05000388/2023005) IR 05000387/20220062023-03-0101 March 2023 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2022006 and 05000388/2022006) IR 05000387/20220052022-08-31031 August 2022 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2022005 and 05000388/2022005) IR 05000387/20210062022-03-0202 March 2022 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2021006 and 05000388/2021006) ML22041A1562022-02-10010 February 2022 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000387/2022013 and 05000388/2022013 ML21312A1012021-11-0808 November 2021 Information Request to Support Post-Approval Site Inspection for License Renewal; Inspection Report 05000387/2022011 ML21236A2662021-11-0808 November 2021 Ti 2515/194 Inspection Documentation Request IR 05000387/20210052021-09-0101 September 2021 Updated Inspection Plan for the Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2021005 and 05000388/2021005) ML21210A2232021-07-29029 July 2021 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000387/2021010 and 05000388/2021010 IR 05000387/20200062021-03-0303 March 2021 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2020006 and 05000388/2020006) IR 05000387/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Reports 05000387/2020005 and 05000388/2020005) ML20149K4492020-05-28028 May 2020 Notification of Conduct of a Fire Protection Team Inspection IR 05000387/20190062020-03-0303 March 2020 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2019006 and 05000388/2019006) ML20056E4392020-02-21021 February 2020 Ti 2515/194 Inspection Documentation Request IR 05000387/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000387/2019005 and 05000388/2019005) ML19191A0652019-07-10010 July 2019 Information Request for Triennial Baseline Design Bases Assurance Inspection (Team); Notification to Perform Inspection 05000387/2019011 and 05000388/2019011 IR 05000387/20180062019-03-0404 March 2019 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2018006 and 05000388/2018006) IR 05000387/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000387/2018005 and 05000388/2018005) IR 05000387/20170062018-02-28028 February 2018 Annual Assessment Letter for Susquehanna Units 1 and 2 (Report 05000387-2017006 and 05000388-2017006 Report 05000387-2017402 and 05000388-2017402 Report 05000387-2017501 and 05000388-2017501) IR 05000387/20170052017-08-28028 August 2017 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 Letter with Report 22 (Report 05000387/2017005 and 05000388/2017005) IR 05000387/20160062017-03-0101 March 2017 Annual Assessment Letter for Susquehanna Units 1 and 2 Report Nos. 05000387/2016006 and 05000388/2016006 IR 05000387/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2, (Report 05000387/2016005 and 05000388/2016005) IR 05000387/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Inspection Report 05000387/2015006 and 05000388/2015006) IR 05000387/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2015005 and 05000388/2015005) IR 05000387/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2014001 and 05000388/2014001) IR 05000387/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000387-14-006 and 0500388-14-006 IR 05000387/20130012014-03-0404 March 2014 ROP-14 2013 Susquehanna Steam Electric Station, Units 1 & 2, Annual Assessment Letter for Report 05000387/2013001 and 05000388/2013001 and Inspection Plan IR 05000387/20130062013-09-0303 September 2013 Mid-cycle Performance Review and Inspection Plan Report 05000387-13-006 and 05000388-13-006 IR 05000387/20120012013-03-0404 March 2013 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2012001 and 05000388-12-001) IR 05000387/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2012006 and 05000388/2012006) IR 05000387/20110012012-03-0101 March 2012 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2011001 and 05000388/2011001) ML1124304692011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Susquehanna Steam Electric Station, Units 1 and 2 IR 05000387/20100012011-03-0404 March 2011 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2, EOC-11 (Report 05000387/2010001 and 05000388/2010001) ML1024404622010-09-0101 September 2010 IR 05000387-10-001 and 05000388-10-001 on 08/11/2010 for Susquehanna Steam Electric Station, Units 1 & 2, Mid-Cycle Assessment Letter 2010 ML1006210392010-03-0303 March 2010 Annual Assessment Letter - Susquehanna Steam Electric Station, Units 1 and 2 (05000387-10-001 and 05000388-10-001) ML0924402702009-09-0101 September 2009 Mid-Cycle Performance Assessment Letter - Susquehanna Steam Electric Station IR 05000387/20090012009-03-0404 March 2009 Annual Assessment Letter - Susquehanna Steam Electric Station (05000387-09-001 and 05000388-09-001) ML0824704642008-09-0202 September 2008 2008 Mid-Cycle Performance Assessment Letter - Susquehanna ML0734707322007-12-13013 December 2007 ROP 8 - Susquehanna - Change to Inspection Plan, 12/13/07 ML0724306552007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan, for 07/01/2007 - 12/31/2008 IR 05000387/20070012007-03-0202 March 2007 Annual Assessment Letter - Susquehanna Steam Electric Station (Report 05000387/2007001 and 05000388/2007001) ML0624305252006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Susquehanna Steam Electric Station ML0606204502006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Susquehanna Steam Electric Station (Report 05-387/2006001 and 05-388/2006001) ML0524207002005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Susquehanna ML0718301432005-03-14014 March 2005 CH-ER-314, Rev 1, SSES Environmental Inspection Plan Procedure. IR 05000387/20050012005-03-0202 March 2005 Annual Assessment Letter for 05000387-05-001 and 05000388-05-001 2024-08-29
[Table view] |
Text
UNITED STATES March 4, 2013
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR SUSQUEHANNA STEAM ELECTRIC STATION, UNlTS 1 AND 2 (REPORT 05000387/2012001 AND 05000388/2012001)
Dear Mr. Rausch:
On February 12, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Susquehanna Steam Electric Station (Susquehanna) Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from January 1, 2012 through December 31, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The security inspection plan will be sent via separate correspondence.
The NRC determined that the performance at Susquehanna Unit 1 during the most recent quarter was within the Regulatory Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because of one finding having low to moderate safety significance (i.e.,
white) associated with the Initiating Events Cornerstone. The White finding was related to an internal flooding event on July 16, 2010, which required the operators to insert a manual scram and isolate the normal heat sink.
Unit 1 began the assessment period in the Degraded Cornerstone Column of the NRCs ROP Action Matrix due to the White finding discussed above and a White PI for Unplanned Scrams per 7000 critical hours. On May 7, 2012, the NRC issued an interim 95002 supplemental inspection report and follow-up assessment letter (ML1215A374), which closed the White PI and held the White finding open. This moved Unit 1 to the Regulatory Response Column. A follow up 95002 inspection was completed on December 14, 2012. The associated inspection report and follow up assessment letter (ML13025A325) was issued on January 25, 2013. This inspection closed the White finding and moved Unit 1 to the Licensee Response Column of the NRC Action Matrix effective January 25, 2013. Therefore, the NRC plans to conduct ROP baseline inspections at Unit 1.
The NRC determined the performance at Susquehanna Unit 2 during the most recent quarter was within the Licensee Response Column of the NRC=s ROP Action Matrix because all inspection findings had very low safety significance (i.e., green), and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at Unit 2. The NRC evaluates cross-cutting themes to determine whether a substantive cross-cutting issue (SCCI) exists in a particular area and to encourage licensees to take appropriate actions before more significant performance issues emerge. In our 2011 Mid-Cycle assessment letter dated September 1, 2011 (ML112430469), a SCCI was identified in the Corrective Action Program (CAP) component of the Problem Identification and Resolution cross-cutting area related to P.1(c) - Evaluation of Identified Problems. This SCCI in P.1(c) was continued in the 2011 Annual Assessment letter (ML12061A021) and the 2012 Mid-Cycle assessment letter (ML12248A066). Our letters indicated this SCCI in P.1(c) will remain open until PPL has demonstrated sustainable performance improvement as evidenced by effective implementation of an appropriate corrective action plan that results in no safety significant findings and a notable reduction in the overall number of inspection findings with the same cross-cutting aspect.
The NRC has determined the exit criteria were not met because there was not a notable reduction in the number of findings and the corrective action plans associated with monitoring progress were not effectively implemented. Specifically, there were four findings with an aspect of P.1 (c) related to evaluation quality. While PPL implemented a number of appropriate corrective action plans, PPLs monitoring of its progress did not provide reliable information that would demonstrate sustainable performance improvement.
This letter is the fourth consecutive assessment letter documenting a substantive cross-cutting issue with the same cross-cutting aspect. Consistent with guidance in NRC Inspection Manual Chapter 0305, Section 14.04, the NRC requests that during the upcoming Annual Assessment Public Meeting, PPL describe the status of your corrective action plans, trends in your internal metrics related to evaluation quality, and your plans to ensure the effectiveness of your actions.
In addition, to facilitate discussion during the Annual Assessment Public Meeting, the NRC requests PPL provide a written letter on the docket by April 3, 2013, summarizing your corrective actions, trends in your progress, and any adjustments you made as a result of your internal reviews. The NRC plans to complete baseline inspections later this year focused on these elements of your corrective action plans related to the SCCI in P.1(c). Finally, the NRC is aware of your plans to complete an independent third party safety culture assessment in the first quarter of 2013. As part of our baseline inspections, the NRC plans to review your analysis of the results for insights related to progress in corrective action program evaluation quality.
Additionally, in our 2011 Annual Assessment letter assessment letter dated March 1, 2012 (ML12061A021), the NRC opened a second SCCI in the Resources component of the Human Performance cross-cutting area related to H.2(c) - Documentation, Procedures and Component Labeling. The SCCI was continued in the 2012 Mid-Cycle assessment letter (ML12248A066).
Our letters indicated this SCCI with an aspect in H.2(c) will remain open until PPL has demonstrated sustainable performance improvement as evidenced by effective implementation of an appropriate corrective action plan that results in no safety significant findings and a notable reduction in the overall number of inspection findings with the same cross-cutting aspect. During this assessment period, the NRC determined that PPL demonstrated sustainable performance improvement related to this SCCI. In 2012, there were no safety significant findings identified with an aspect in H.2(c) and there was a notable reduction from four to two of findings with an aspect in H.2(c). Additionally NRC inspections determined PPL corrective action plans were being effectively implemented related to your Procedures Upgrade Project, permanent Station Procedures Group, and augmented oversight by management of staff procedures use and adherence. As a result, the substantive cross-cutting issue in Human Performance related to H.2(c), Documentation, Procedures and Component Labeling is closed.
The enclosed inspection plan lists the inspections scheduled through June 30, 2014. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to baseline inspections, the NRC will perform Temporary Instruction (TI) 182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks.
Additionally, from January 1 to December 31, 2012, the NRC issued three severity level IV traditional enforcement violations associated with impeding the regulatory process. Therefore, the NRC plans to conduct an inspection using Inspection Procedure (IP) 92723, Follow-up Inspection of Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period, to follow-up on these violations. The NRC has conducted similar inspections using IP 92723 at Susquehanna in 2010 and 2012 for violations impeding the regulatory process. The NRC intends to review previous traditional enforcement violations associated with the IP 92723 inspections in 2010 and 2012 to evaluate the recurring nature of these issues, the efficacy of prior corrective actions and extent of cause. This inspection will be scheduled and completed once you inform the NRC of your readiness for the inspection.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Mel Gray at (610)337-5209 with any questions you have regarding this letter.
Sincerely,
/RA/
William M. Dean, Regional Administrator Docket Nos. 50-387; 50-388 License Nos. NPF-14, NPF-22 Enclosure: Susquehanna Steam Electric Station Inspection/Activity Plan cc w/encl: Distribution via ListServ
ML13059A425 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP RI/ORA NAME ARosebrook/ AAR MGray/ MG DRoberts/ DJR WDean/ WMD DATE 02/ 20/13 02/ 26/13 02/27/13 02/ 28/13