ML22132A295

From kanterella
Revision as of 09:54, 2 September 2023 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Framatome, Inc., Submittal of Triennial Update to Decommissioning Funding Plan (DFP) for the Richland Nuclear Fuel Fabrication Facility
ML22132A295
Person / Time
Site: Framatome ANP Richland
Issue date: 05/12/2022
From: Travis Tate
Framatome
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
Shared Package
ML22132A294 List:
References
TJT;22:007
Download: ML22132A295 (2)


Text

framatome May 12, 2022 TJT;22:007 Director, Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington DC 20555-0001 Attn: Document Control Desk

Subject:

Triennial Update to Decommissioning Funding Plan (DFP) for the Framatome Inc. Richland Nuclear Fuel Fabrication Facility (License No. SNM-1227; Docket No. 70-1257)

References:

(1) Letter, T.J. Tate to USNRC Document Control Desk; Triennial Update to Decommissioning Funding Plan (DFP) for Framatome Inc. Richland Fuel Fabrication Facility (License No. SNM-1227, Docket No. 70-1257);

January 28, 2021.

(2) Letter, J, Zimmerman to T.J. Tate; Framatome Inc. -Amendment 16 to Material License SNM-1227; Triennial Update to Decommissioning Funding Plan (Enterprise Project Identifier L-2021-DFA-0000), August 12, 2021.

Dear Sir:

The purpose of this correspondence to convey a corrected final updated Decommissioning Funding Plan (DFP) for Framatomes Richland nuclear fuel fabrication facility. NRC regulations at 10 CFR 70.25(e) require that decommissioning cost estimates be adjusted at intervals not exceeding three years. Framatomes Decommissioning Cost Estimate update was submitted via Reference 1 and ultimately approved by the NRC via Reference 2.

The attached DFP includes the finalized NRC approved financial assurance instruments that have been incorporated into the finalized DFP. It also includes a certification by Framatomes CFO.

The DFP is a proprietary document and Framatome requests that the NRC handle it as such. This transmittal letter is not proprietary when the attachments are removed.

Framatome Inc.

2101 Horn Rapids Road Richland, WA 99354 Tel: (509) 376-8100 w w w.fram ato me.com

US NRC TJT:22:007 May 12, 2022 Page 2 If you have any questions or require additional information, please feel free to contact Calvin Manning of my staff at 509-375-8327 or me at 509-375-8550.

Very truly yours, Timothy J. Tate, Manager Environmental, Health, Safety and Licensing Attachments:

1. Attachment 1 Affidavit requesting that the Framatome Decommissioning Funding Plan be handled as proprietary information.
2. Attachment 2 (proprietary), E10-05-001, Version 4.0, Decommissioning Funding Plan.

Cc: Osiris Siurano-Perez Richard Jervey