Submits Final Response to IE Bulletin 79-02 Re safety-related Concrete Expansion Anchors.Stringent Design Criteria & Systematic QA Program Inplemented to Ensure Proper Installation & Testing of Anchors
ML20076G225
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 06/01/1983
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
REF-SSINS-6820 IEB-79-02, IEB-79-2, L-83-339, NUDOCS 8306140581
Download: ML20076G225 (2)


Text

I P. O. 80x 14000, JUNO BE ACH, F L 33408 L .i O d Ui'l } FLORIDA POWER & LIGHT COMPANY l June 1, 1983 L-83-339 Mr. James P. O'Reilly Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta St., Suite 2900 Atlanta, GA 30303

Dear Mr. O'Reilly:

Re: ST. LUCIE UNIT NO. 2 '

DOCKET 50-389 IE BULLETIN 79-02

References:

. 1) Uhrig to O'Reilly letter, L-79-180, dated July 2, 1979

2) Uhrig to O'Reilly letter, L-80-19, dated June 14, 1980
3) Uhrig to Eisenhut letter, L-82-408, dated Sept. 21, 1982 The St. Lucie Unit No. 2 Operating License -(NPF-16) Attachment 1, " Items To Be Completed Prior to Exceeding 57. Rated Power", requires that Bulletin 79-02 be complete to the satisfaction of Region II. In order to close out this license condition . Florida Power & Light Company (FPL), via this letter, is submitting our final response to this bulletin.

FPL previously reviewed and responded to this bulletin in the referenced letters. This correspondence stated that the overall philosophy at St.

Lucie Unit No. 2 was to avoid the use of concrete expansion anchors through the design effort. However, due to design restraints, it was occasionally necessary to use expansion anchors on Category I restraints / hangers. FPL employed stringent design criteria when expansion anchors were used. In addition, a systematic Quality Control program was implemented to ensure proper installation and testing. All safety-related expansion anchors installed to date have been inspected to the criteria of Bulletin 79-02.

It should be noted that continuing construction efforts, although limited, will continue until 57. power (i.e., Appendix "R" work, etc.). If in this effort expansion anchors are used, the present program will be employed. For future plant changes to the operating plant, FPL implemented a process called a Plant Change / Modification (PC/M) procedure which ensures that any future change to expansion anchors will use the criteria .

outlined in Bulletin 79-02.

~

8306140581 830601 PDR ADOCK 05000389 C PDR t j0 fEIi PEOPLE: . SERVING PEOPLE

ST. LUCIE UNIT NO. 2 DOCKET 50-389 IE BULLETIN 79-02 -

Region II inspectors have previously inspected our in process efforts and documentation. All completed documentation to Bulletin 79-02 are maintained at the site.

This letter completes the reporting requirements for Bulletin 79-02.

,.Very truly yours, Robert E. Uhrig Vice President Advanced. Systems and Technology REU/PPC/rms O